Grid
Utility-scale generation, storage, transmission, and the markets that run them.
RSS feed for Grid →NERC files data center reliability standards at FERC, asks for speed
NERC filed CLO-001-1, CLO-002-1 and CLO-003-1, a new family of reliability standards for computational loads such as data centers and crypto miners, at FERC on November 17, 2026, with revised FAC-001-5 and FAC-002-5, and asked for expedited action. Comments are due December 17.
NRC draft EIS preliminarily backs license for Orano's Oak Ridge plant
NRC staff's draft environmental impact statement for Orano's Project IKE enrichment plant in Oak Ridge, Tennessee, preliminarily recommends a 40-year license, finding impacts SMALL with mitigation. The NRC's safety review is now expected to finish in June 2027.
Hai Long completes construction; some Dogger Bank A turbines need work
Hai Long marked construction completion of its 73-turbine Taiwan project of more than 1 GW on November 17, 2026, and SSE said some early Dogger Bank A turbines need more work. Vattenfall and CIP picked Siemens Gamesa for Zeevonk Phase I, the European Commission cleared up to €9.45 billion for IJmuiden Ver Gamma, and the UK set notional £1 budgets for CfD Allocation Round 8 until it sees the bids.

SPP files $25/MWh bid cap for flexible loads in FERC large-load package
Southwest Power Pool filed a Price Adaptive Load Service at FERC on November 19, 2026 (ER27-578): non-firm service for flexible, price-sensitive loads whose energy bids are capped at $25/MWh, against MISO's $100, NYISO's $200 and ISO New England's $250/MWh triggers, with implementation targeted for the second quarter of 2028. A companion filing (ER27-577) directly assigns delivery-point upgrade costs above the lesser of $25 million or $500,000 per MW to the requesting customer.

Senate passes BAAJA permitting bill 62-33, sending it to the House
The Senate passed H.R. 2347, the vehicle for the Bipartisan American Affordability and Jobs Act, 62-33 on November 19, 2026, with the Capito substitute's permitting, transmission and data center cost provisions. The House, which passed H.R. 2347 as an unrelated tax bill in April, must now act on the Senate's version.

GM Energy and WeaveGrid launch V2G pilot for SCE customers in ELRP
GM Energy and WeaveGrid are launching a vehicle-to-grid pilot with select GM EV owners in Southern California Edison's territory, GM said on November 19, 2026. Eligible SCE customers in the Emergency Load Reduction Program may get up to $8,000 toward a V2H system and up to $8,099 toward eligible installation and interconnection costs through the California Energy Commission.
PJM transmission owners ask FERC for 10-year minimum data center contracts
The PJM Transmission Owners asked FERC on November 16, 2026 for a pro forma cost recovery agreement under which data centers commit for at least ten years to 80 to 100 percent of their firm transmission charges, backed by collateral sized to the full projected bill. PG&E and Southern California Edison proposed 15-year minimum revenue obligations backed by five years of security.

Scottish ministers consent Muir Mhòr floating wind farm of up to 1 GW
The Scottish Government on November 19, 2026 consented Muir Mhòr, a floating offshore wind farm of up to 67 turbines and up to 1 GW about 63 km off Aberdeenshire, owned by Fred. Olsen Seawind. Conditions require an approved seabird compensation plan before construction, a radar scheme agreed with the MOD before turbines go up, and a fishing zone of at least 13 km² kept free of infrastructure.

PJM board approves $5.1B Valley Link estimate and later in-service dates
PJM's Board of Managers approved on November 17, 2026 a revised Valley Link estimate of $5.115 billion in 2026 dollars, up from roughly $3 billion in 2024 dollars, with in-service dates moved from June 1, 2029 to between January 2030 and May 2031.

New York staff back 5 GW nuclear goal and open-book reactor deals
New York Department of Public Service staff recommended on November 18, 2026 that the Public Service Commission adopt an 8.4 GW Nuclear Reliability Backbone with 5 GW of new advanced nuclear, backed by performance-based revenue support that could include state equity, limited cost overrun risk sharing and early-stage support, and procured through competitive open-book negotiation. NYSERDA and the department completed the state's Advanced Nuclear Master Plan the same day.

DOE offers Grid United up to $2.8B loan for Wyoming east-west grid tie
The US Department of Energy's Office of Energy Dominance Financing offered Grid United a conditional loan commitment of up to $2.8 billion on November 17, 2026 for the Wyoming Intertie, an approximately 106-mile, up-to-1,800 MW link between the eastern and western US grids. The loan closes only after right-of-way, permits and capacity contracts are in hand.

EU reaches provisional deal to cap permit times for grids and storage
Parliament and the Council's Irish presidency provisionally agreed on November 18, 2026, on EU rules setting permitting deadlines for renewables, grids, storage and recharging stations, the permitting half of the Commission's European grids package. Small solar, storage (hydrogen excluded) and chargers would need a permit only above 200 kW, double the 100 kW the Commission proposed.

MISO and NYISO propose $100 and $200/MWh cutoffs for non-firm large loads
MISO and NYISO filed large-load rules at FERC on November 16, 2026, answering its June 18 show-cause orders. MISO's proposed GRITS service would interrupt non-firm load when local prices exceed $100/MWh; NYISO's Non-Firm Withdrawal Service carries a $200/MWh bid cap. MISO proposes a study of about five months, a $250,000 application fee and security equal to upgrade costs; NYISO's study cycle runs about 18 months to two years, and New York's utilities would recover a large load's upgrade costs over 15 years.

Austin widens its battery VPP; Puerto Rico's reaches 114,428 participants
Austin Energy's Power Partner Battery pilot now takes Tesla, Generac and Enphase home batteries as well as SolarEdge and FranklinWH, with a $500 rebate and $75 a year per kW of average event output. Puerto Rico's CBES program called 14 events in September 2026 with a record 114,428 participants, and Vattenfall chose Kraken to run its German batteries, wind and solar as a virtual power plant.
US storage passes 200 GWh installed as Q3 additions slip 1% on the year
The US installed 14.3 GWh of energy storage in Q3 2026, 1% less than in Q3 2025, and has passed 200 GWh installed to date, according to SEIA and Benchmark Mineral Intelligence. Installations through September reached 48.3 GWh, up 20% year over year.

PJM asks FERC to study generators and large loads in one 12-month pass
PJM Interconnection filed its Fast Energization Process at FERC on November 16, 2026 (ER27-531), studying generator interconnection and Large Load transmission service requests together in one 12-month cluster that PJM says takes half the time of its current cycle. PJM asks for an order within 120 days and expects the first application window in late November 2027.

Google signs 50 MW superhot geothermal PPA with Quaise in Oregon
Google signed a power purchase agreement for 50 MW from Quaise Energy's Project Obsidian in Central Oregon, Quaise announced November 17, 2026, with deliveries as early as 2030 to support Google's data center operations in The Dalles. The first phase uses conventional drilling; Quaise's millimeter wave drill is slated for the second, and OPB reports a 10-mile line to La Pine is needed.

PJM files ride-through rules for data centers, existing ones included
PJM filed tariff revisions at FERC on November 16, 2026 (ER27-522) requiring transmission customers serving Large Computational Loads, 50 MW sites with 25 MW or more on power electronics, to meet minimum ride-through requirements set in PJM's manuals. Existing loads get no exemption; at the requested effective date they have until at least January 16, 2028 to comply.

Rooppur 1 starts 350 MW trial supply, Bangladesh's first nuclear power
Unit 1 of Bangladesh's Rooppur Nuclear Power Plant began supplying 350 MW to the national grid on a trial basis at 3:16 p.m. on November 17, 2026, the project said. Commercial supply at full capacity follows a 10-month trial operation under the contract with the Russian contractor.
Samsung SDI to supply Jupiter Power 16 GWh of Indiana-made LFP batteries
Samsung SDI said on November 16, 2026 that its US subsidiary signed a deal to supply Jupiter Power with 16 GWh of LFP batteries, produced in Indiana, over three years starting in 2029, which Samsung estimates is worth several trillion won. Including an earlier deal, Samsung puts its total orders from Jupiter at about 27 GWh.
Jackery supplies Every Electric's NYC window-AC battery program
Jackery and Every Electric said on November 16, 2026 that Jackery is lead hardware provider for Every Electric's New York City A/C Powerbank Program, which they put at about 2,000 portable power stations in more than 1,000 households and 4 MWh of flexible storage in Con Edison territory.
TotalEnergies venture pulls $16 billion H2 Magallanes from Chile review
TEC H2 MAG SpA, developer of TotalEnergies' $16 billion H2 Magallanes green hydrogen and ammonia project, asked on November 12, 2026 to withdraw it from Chile's environmental review, saying demand for green molecules had not developed enough to secure long-term contracts on viable terms and equipment costs had not fallen as forecast. Chile's Environmental Assessment Service closed the review the next day.

Chashma-5 dome set, TVA moves on Watts Bar renewal, CANDU study for Türkiye
Pakistan placed the dome on its 1,200 MW Chashma-5 unit on November 10, 2026. TVA's board that day let its chief executive decide on renewing both Watts Bar reactor licenses and approved serving more than 100 MW to a Korea Zinc subsidiary, and AtkinsRéalis said on November 12 it will study CANDU reactors for Türkiye.
Lydian's 600 MWh Utah battery is online; NYSERDA opens second storage round
Lydian Energy said on November 10, 2026 that its 150 MW / 600 MWh Faraday battery in Utah, contracted to PacifiCorp in support of Meta's Eagle Mountain data center, began operating on September 18. NYSERDA issued ISCRFP26-1, its second bulk storage solicitation, on November 12; the EBRD signed €50 million for a Tunisian solar plant with a 10 MW / 20 MWh battery, and Calibrant closed a $145 million debt facility.
WeaveGrid to run Hyundai-Kia smart charging, Zaptec at 1M, Meta-Nevoya I-10
WeaveGrid said on November 12, 2026 that it will power the smart-charging platform for Hyundai and Kia drivers in the US, with vehicle-to-grid services planned as bidirectional hardware, interconnection rules and utility program designs evolve. Zaptec said on November 9 that one million of its chargers are installed, and Nevoya said on November 12 that Meta will buy environmental attribute certificates supporting 25 battery-electric trucks on I-10, which it expects to begin operating in 2027.
Iron flow battery developer ESS Tech files for Chapter 7, ceases operations
ESS Tech, the Oregon developer of iron flow and sodium-ion battery systems, ceased operations and filed a Chapter 7 petition in Delaware bankruptcy court on November 13, 2026. A trustee will liquidate its assets, and the company says common stockholders are unlikely to receive any payment.
Hyd'Occ opens, Oman's Duqm awards, Brazil's first H2 basic-grid access
Qair inaugurated Hyd'Occ, a 20 MW electrolysis plant it calls France's largest renewable hydrogen plant, on November 13, 2026. GE Vernova reported a 50% hydrogen blend validation and a 100% hydrogen test on two aeroderivative turbines; Oman's Hydrom awarded two Duqm projects targeting about 121,000 tonnes of green hydrogen a year by 2032; and Brazil's ANEEL authorized its first green hydrogen project to access the basic grid.
Southwest hydropower hit a record low as Lake Powell and Lake Mead fell
Hydropower generation in EIA's Southwest region (Arizona, New Mexico and parts of Nevada and California) from April through August 2026 was 19% below 2025 and 28% below the 10-year average, EIA reported on November 13, 2026, as Lake Powell and Lake Mead hit what EIA calls record lows. EIA expects 6.13 billion kWh of Southwest hydropower in 2026.
NYPA qualifies 10 developers for its 1 GW upstate nuclear project
The New York Power Authority said on November 12, 2026 that it has qualified 10 of the 21 respondents to its nuclear request for qualifications as potential partners for at least 1 GW of advanced nuclear in upstate New York: six for large reactors or SMRs, four for SMRs only. Its next step is selecting a host community, technology and development partner, and state regulators' staff owe a Nuclear Reliability Backbone white paper by November 18.

ISO New England's large-load filing ties firm service to new capacity
ISO New England and the region's transmission owners filed large-load rules with FERC on November 13, 2026 (ER27-484): firm service for loads of 50 MW or more that bring new capacity, and interim or non-firm service re-dispatched above $250/MWh. Applications would open June 1, 2027.
