Hai Long completes construction; some Dogger Bank A turbines need work
Vattenfall and CIP pick Siemens Gamesa for Zeevonk, Brussels clears up to €9.45 billion in fallback Dutch aid, and Britain sets notional £1 auction budgets until it sees the bids.
Between November 17 and November 19, 2026, a Taiwanese wind farm of more than 1 GW celebrated the end of construction, the first phase of Britain's Dogger Bank learned that some of its early turbines need more work, a Dutch project ordered its turbines, Brussels cleared up to €9.45 billion of Dutch support, and London set its offshore wind auction budget at a notional £1. Neither of the last two figures means quite what it says.
Hai Long marks construction completion in Taiwan
Hai Long, three wind farms combined into one project of more than 1 GW in the Taiwan Strait, held its construction completion ceremony on November 17, 2026, with all 73 turbines connected to Taiwan Power Company's grid, the project said. Full operations are expected in 2027, once administrative and permitting procedures are done, the release says.
The ceremony marked news that was a month old. Northland Power, a co-owner, said on October 15 that all 73 turbines were installed and generating power, that final permitting approvals were on track for the first half of 2027, and that overall construction costs were "aligned with original expectations." Northland holds 30.6%, Mitsui & Co. 40% and Gentari 29.4%. The supply chain went local too: by our arithmetic, the 21 nacelles in Hai Long's original localization commitment and the 52 more locally assembled ones it bought add up to 73, the turbine count.
Some early Dogger Bank A turbines need more work
SSE said in its interim results on November 18, 2026 that commissioning continues at Dogger Bank A, with additional work needed on some turbines installed early in the installation campaign so they meet the required quality and reliability standards. The 1.2 GW phase is now expected to be substantially available by the end of the first quarter of 2027, with the remaining capacity available during final commissioning by the end of the third quarter. Across the 3.6 GW project, in which SSE holds 40%, around 150 turbines are installed and around 100 commissioned.
Chief executive Martin Pibworth's prepared remarks for the analyst call were plainer: "The first phase of that project experienced some well-publicised teething problems, and remediation works are well under way to ensure those early turbines meet our required quality and reliability standards." SSE's statement and remarks do not name the turbine maker. On the call, Pibworth said "The issue on Dogger Bank relates to a few dozen turbines, and there's different elements of that," reNEWS reported, describing them as GE Haliade-X 13 MW machines from GE Vernova. Turbine installation on the next phase is running well ahead of the first phase's pace: Dogger Bank B has 52 turbines installed and is expected to be substantially available in the first half of 2027, and Ofgem named a preferred bidder for its offshore transmission assets in a notice published November 5.
Zeevonk picks Siemens Gamesa for its first gigawatt
Vattenfall and Copenhagen Infrastructure Partners chose Siemens Gamesa to supply 69 turbines for Phase I of Zeevonk, off the Dutch North Sea coast, Vattenfall said on November 18. Each SG 15-236 is rated 15 MW, with a power boost of up to 15.5 MW, for "just over 1 GW" in total; a separate agreement covers long-term service and maintenance.
Vattenfall says all key supplier agreements for the construction phase are now in place. The investment decision is not. "With the project's two largest contracts now in place, we are moving decisively towards a final investment decision and bringing Zeevonk into execution," said Felix Pahl, a partner at CIP. Turbine manufacturing is planned for 2028 and installation targeted for 2029; Phase II follows in 2032, adding another 1 GW of wind and 500 MW of system integration capacity.
Brussels clears up to €9.45 billion for IJmuiden Ver Gamma
The European Commission approved a Dutch scheme, TOWOZ, for two North Sea wind farms, IJmuiden Ver Gamma-A and Gamma-B, on November 17, 2026, the Commission said. The farms have a combined capacity of 2 GW and are expected to generate up to 7,441 GWh a year. The scheme's maximum budget is €9.45 billion, paid if necessary for 15 years from operations expected in 2032.
The money is a fallback. The tender first invites bids that pay the state for the site; only if there are none will the government consider bids for a variable premium on top of the market price, with a bid cap and a claw-back. That is a different instrument from the two-way contract for difference worth up to €2.04 billion that the Commission cleared for Belgium on November 10. The two Dutch tenders are to be organised before July 2027; the Commission's background notes that EU electricity rules allow feed-in premiums instead of two-way contracts for difference until July 2027.
The UK sets AR8 budgets at £1 until it sees the bids
The Department for Energy Security and Net Zero published the budget notice for Contracts for Difference Allocation Round 8 on November 19, the day the Scottish Government consented the Muir Mhòr floating wind farm. The round opened to applications on July 20, 2026. The four pots for solar, onshore wind, offshore wind and floating or deepwater offshore wind each get a notional £1, so no project clears and the government reviews anonymised bids before deciding whether to raise them. Budget will be provided only if bid prices are in consumers' interests, with final decisions made with HM Treasury.
Pot 5, which covers technologies from geothermal and tidal stream to energy from waste with CHP, gets £0, and that budget is final. The expected effect "is that no assets will be supported in this pot," the accompanying note says. "This decision reflects AR8's focus on strategic technologies which can deploy at scale and at lower cost in the near term." Administrative strike prices stay at AR7 levels, in 2024 prices: £113/MWh for offshore wind, £271/MWh for floating offshore wind, and £371/MWh for tidal stream, a ceiling with no budget under it.
Sources
Primary
- Hai Long, Asia's Largest Single Offshore Wind Project, Marks Construction Completion · Hai Long Offshore Wind
- Commission approves €9.5 billion Dutch State aid to support offshore wind energy (IP/26/2457) · European Commission
- SSE plc: Interim Results for the six months ended 30 September 2026 · SSE plc
- Vattenfall and Copenhagen Infrastructure Partners choose Siemens Gamesa turbines for Zeevonk offshore wind farm · Vattenfall
- Contract Budget Notice for Allocation Round 8, 2026 · Department for Energy Security and Net Zero
Supporting
- Northland's Hai Long Offshore Wind Project Reaches Major Milestone: All 73 Turbines Installed and Generating Power · Northland Power
- SSE plc half-year results to 30 September 2026: presentation transcript · SSE plc
- Accompanying Note to the Contract Budget Notice for Allocation Round 8 (AR8), 2026 · Department for Energy Security and Net Zero
- 'Dozens' of turbines need work at Dogger Bank · reNEWS
Copies of cited sources are retained where available. If a link no longer resolves, request a copy at contact@theduckcurve.com.