TotalEnergies venture pulls $16 billion H2 Magallanes from Chile review
Its developer told Chile's environmental agency on November 12, 2026 that demand for green molecules had not developed enough and equipment costs had not fallen as forecast; the review had been on hold since 2025.
TotalEnergies' H2 Magallanes, a $16 billion plan to turn Patagonian wind into green ammonia for export, is out of Chile's environmental review. Its developer, TEC H2 MAG SpA, asked the Environmental Assessment Service (SEA) to withdraw the project's environmental impact study in a letter dated November 12, 2026, and the SEA's Magallanes office declared the study withdrawn on November 13, ending the evaluation. The project record now reads "Desistido."
The developer's filings list contacts at TE H2, which TotalEnergies has described as a joint venture between TotalEnergies and the EREN Group. When the study went in, in May 2025, Chile's foreign investment agency InvestChile called H2 Magallanes "the largest green hydrogen and green ammonia initiative submitted in Chile, far surpassing the other projects announced to date."
Demand and equipment costs, not the permit
The letter's reasons are commercial. "After incurring significant development costs and devoting considerable effort, we have unfortunately concluded that market conditions and demand for green molecules have not evolved sufficiently to secure long-term purchase contracts on economically viable terms," wrote Antoine Liane, the company's legal representative (our translation from the Spanish). Equipment costs, he added, have not fallen as forecast, which has left production costs uncompetitive and made an investment the size of H2 Magallanes economically unviable.
That is a buyer problem and a hardware problem in one paragraph. The letter does not say how much the developer spent getting this far.
The scale explains the price tag. According to the project summary on the SEA record, H2 Magallanes would have built a 5 GW wind farm of 616 turbines rated at 8 MW each, seven electrolysis centres totalling 3.85 GW that together make 1,750 tonnes of hydrogen a day, a desalination plant drawing 1,300 litres a second, an ammonia plant of up to 10,800 tonnes a day, and a marine terminal to ship it. The record lists the investment as 16,000 million dollars.
The pitch around the filing was bigger. On May 6, 2025, InvestChile described 10 GW of wind capacity from about 608 turbines of 16.5 MW each, built in three phases: 1.5 GW of wind and a 1 GW electrolysis plant first, then 5 GW of wind, then the full 10 GW. Start-up was estimated for 2030. The record's summary describes 5 GW, the size InvestChile gave for the second phase.
A review that stopped in 2025
The review stalled within months of starting. The SEA admitted the study on May 12, 2025 and issued its consolidated request for clarifications on August 7, 2025, setting September 23, 2025 as the date for the developer's answers, according to the SEA's September 2025 resolution on the schedule.
Instead of answering, the developer asked for more time. On September 16, 2025 it asked to extend the suspension of the time remaining in the evaluation until March 31, 2027, citing a technical review of the project's design, additional field campaigns (archaeology, marine ecosystems, flora and vegetation, terrestrial vertebrate fauna and soil), processing and analysis of information, and citizen participation and the consolidation of responses. The SEA agreed to extend the suspension only to December 7, 2026, a date it considered enough to answer the clarification request, while leaving the developer the right to ask for a second extension.
The answers never arrived. The developer's next filing after its September 2025 request was the withdrawal letter, sent 25 days before the suspension was due to end.
Next door, the review keeps moving
The same SEA office has other green ammonia megaprojects on its books. The HNH Energy project, an integrated green ammonia export project put at $11 billion, received its environmental approval (RCA) on September 10, 2026, two months before H2 Magallanes left. Proyecto Acuario, a $4.7 billion plan for 4,100 tonnes of green ammonia a day from 173 wind turbines totalling 1.73 GW in the San Gregorio municipality, was admitted on July 22, 2026 and is still under evaluation.
An approval settles the environmental question, which H2 Magallanes' letter did not raise. What it gave up on, by its own account, was signing long-term buyers on viable terms while equipment stayed expensive.
That is a familiar complaint this year. Air Products booked about $3.2 billion of charges in its fiscal 2026, mostly for exiting clean energy projects led by a Louisiana hydrogen and ammonia complex and a green hydrogen plant in Arizona. It had made firm offtake agreements a condition of a final investment decision on the Louisiana complex, and concluded that its expected returns would not meet the company's criteria. In the Netherlands, four of the seven electrolyser projects subsidised in the second wave of the EU's IPCEI Hydrogen programme have stopped, and the Dutch climate minister told parliament that when those applications were assessed, the consensus was that electrolysis would compete with fossil alternatives under the EU carbon market within ten years. H2 Magallanes' letter makes a similar point about its own forecast: the equipment did not get cheap on schedule.
Sources
Primary
- Carta de desistimiento del EIA Proyecto H2 Magallanes · TEC H2 MAG SpA (filed on Chile's e-SEIA)
Supporting
- Renewables & Green Hydrogen: TE H2, CIP, and A.P. Møller Capital Partner for a Large-Scale Project in the Kingdom of Morocco · TotalEnergies
- TotalEnergies drives LATAM's largest green hydrogen project · InvestChile
- Resolución que extiende suspensión de plazo, H2 Magallanes EIA · Servicio de Evaluación Ambiental, Región de Magallanes y de la Antártica Chilena
- Resolución de Desistimiento N° 20261200146, H2 Magallanes EIA · Servicio de Evaluación Ambiental, Región de Magallanes y de la Antártica Chilena
- Ficha del Proyecto: Proyecto de Producción de Hidrógeno y Amoniaco Verde - H2 Magallanes · Servicio de Evaluación Ambiental (e-SEIA)
- Ficha del Proyecto: Proyecto integral para la producción y exportación de amoniaco verde - HNH ENERGY · Servicio de Evaluación Ambiental (e-SEIA)
- Ficha del Proyecto: PROYECTO ACUARIO - PRODUCCION DE AMONIACO VERDE · Servicio de Evaluación Ambiental (e-SEIA)
Copies of cited sources are retained where available. If a link no longer resolves, request a copy at contact@theduckcurve.com.