Brief

Rooppur 1 starts 350 MW trial supply, Bangladesh's first nuclear power

Bangladesh's first nuclear power plant is on the grid, briefly and on purpose. Unit 1 of the Rooppur Nuclear Power Plant, the 1,200 MW Russian-built reactor in Pabna, began supplying 350 MW to the national grid on a trial basis at 3:16 p.m. on November 17, 2026, in the presence of Science and Technology Minister Fakir Mahbub Anam, the project said on its official Facebook page. It is the first power from the unit to reach the grid, after the reactor reached criticality on October 11.

The connection is a test, and a short one. The project's plan has the unit supplying the grid for about 8 to 10 hours while the turbine, generator and grid-coordinated operation are checked for stability, then disconnecting for further technical tests. After a break of about 28 hours it reconnects for another 4 to 6 hours. If the results are satisfactory, the next stage of trial operation needs approval from the Bangladesh Atomic Energy Regulatory Authority (BAERA). Under the contract with the Russian contractor, commercial supply at full capacity comes after a 10-month trial operation.

Customers get the electrons, but not a promise. Power generated during testing goes to consumers, though the plant cannot guarantee an uninterrupted, stable baseload supply while tests continue, according to the press release reported by The Business Standard, which adds that the grid operator will act to hold the grid stable as the unit's output fluctuates.

Officials did not agree on whether this was a first try. On November 16, Md Anwar Hossain, secretary of the Ministry of Science and Technology, told The Business Standard of the synchronisation, "This is the first time we are attempting it." An official at Power Grid Bangladesh PLC told the paper that several previous attempts to synchronise the plant with the grid had been unsuccessful.

The power also arrived ahead of both calendars in circulation in October: Rosatom's director general put Unit 1's power start-up in the 20s of November, and plant sources told Prothom Alo the first supply, about 300 MW, could come in December. It came in at 350 MW.