Roundup

Lydian's 600 MWh Utah battery is online; NYSERDA opens second storage round

Terra-Gen cuts the ribbon on a Lockhart complex finished in July, the EBRD funds what it calls Tunisia's first utility-scale battery, and Calibrant closes $145 million of debt for a portfolio including a 120 MWh data center battery.

Grid batteries announced between November 10 and 13, 2026 ranged from a 600 MWh system in Utah that had run for nearly eight weeks before its owner said so, to a 20 MWh battery that the EBRD calls Tunisia's first at utility scale. New York opened the second round of its bulk storage program, and two of the US batteries are tied to data centers.

Lydian's 600 MWh Faraday battery is running in Utah for PacifiCorp

Lydian Energy's Faraday battery in Utah County, Utah, a standalone 150 MW / 600 MWh lithium iron phosphate system, has reached commercial operation, Lydian said on November 10. It began operating on September 18, 2026, and delivers its 600 MWh of contracted capacity to PacifiCorp under a long-term energy storage agreement, through a Schedule 34 contract in support of Meta's Eagle Mountain data center operations. Meta's Amanda Yang says in the release that Meta's investments in new energy resources "are helping projects like Faraday BESS reach the grid."

The battery sits on about eight acres beside the 525 MW Faraday solar facility and shares that plant's substation and grid interconnection, which let Lydian add storage using existing infrastructure, the company says. It went from mobilization to commercial operation in about 10 months. Lydian is also developing Faraday BESS 2 at the site, which would add up to 375 MW / 1,500 MWh with a targeted in-service date in the fourth quarter of 2028.

Terra-Gen cuts the ribbon on Lockhart, finished in July

Terra-Gen held a ribbon-cutting at Hinkley, California for its $950 million Lockhart Solar and Storage complex in San Bernardino County: 365 MW of solar and 173.7 MW of battery storage in 248 battery enclosures, per its November 10 release. The headline celebrates commercial operation, which the last of Lockhart's four phases reached months earlier: Terra-Gen said on July 14 that with the 80 MW Lockhart IV online, all four phases were operational.

Masdar, which co-owns Terra-Gen with Igneo Infrastructure Partners, issued its own version on November 13. The output goes to corporate buyers and California load-serving entities, Terra-Gen says. None of the three releases gives the batteries' energy capacity in megawatt-hours, so their duration is anyone's guess (kW vs kWh).

NYSERDA opens the second round of its bulk storage program

NYSERDA issued ISCRFP26-1, the second bulk storage solicitation, on November 12, seeking long-term contracts to buy Index Storage Credits from grid-connected projects of at least 5 MWac. A project creates one credit for each megawatt-hour that is operational and available for discharge on a given day. NYSERDA pays the gap when a project's bid strike price exceeds a reference price built from wholesale energy and capacity prices, and the developer pays NYSERDA when the reference is higher. Contracts run up to 15 years for lithium-ion projects and up to 25 years for other technologies.

Step One eligibility applications are due December 15, 2026, price bids on March 17, 2027, and provisional awards are expected by the end of the second quarter of 2027. Each project needs a development plan showing it can be operating by December 31, 2030. Two-hour batteries are capped at 10% of the 3 GW of planned bulk procurements, NYSERDA targets eight hours or longer for 20% of each round's awardees, and across all three rounds it wants at least 35% of capacity in NYISO Zones G through K, with a minimum 30% in Zone J. New this time: sites at existing barge-mounted or overwater locations that include fossil fuel generating facilities are eligible, if proposers first meet two state agencies on whether a permitting path exists.

The first round, issued July 28, 2025, drew bids for 46 eligible projects of roughly 6 GW and 30 GWh and ended with eight contracted projects totaling 950 MW, according to NYSERDA's solicitations page. Its results were announced on September 23, 2026, about 14 months after it opened.

The EBRD finances what it calls Tunisia's first utility-scale battery

The European Bank for Reconstruction and Development (EBRD) has signed a €50 million package with STEG, Tunisia's national electricity and gas utility, for a 50 MWac solar plant at Beni Mhira in the southern governorate of Tataouine, integrated with a 10 MW / 20 MWh battery, the bank said on November 12. The EBRD lends €30 million with a sovereign guarantee; the other €20 million is a concessional loan from the Climate Investment Funds' Clean Technology Fund under its Global Energy Storage Program. The project includes a 1.2 km high-voltage line to the national grid and is part of a STEG programme of 380 MWac of solar and 100 MWh of storage.

Firsts start small. Ten days earlier the EBRD said it was lending €30 million toward a 246 MW / 512.5 MWh battery in Bulgaria, a country where the bank puts battery storage capacity above 6.2 GW / 19 GWh (our roundup). In Tunisia the point is practice: the bank and STEG both say the battery will build the know-how to run storage on the national grid.

Calibrant closes $145 million for a portfolio with a 120 MWh data center battery

Calibrant Energy has closed a $145 million debt facility led by Investec, with Citi, Liberty Bank and Siemens Financial Services participating, for solar and battery projects across multiple US power markets, the company said on November 10. It recapitalizes operating assets and funds new construction; the portfolio includes a 120 MWh battery serving a hyperscale data center customer in PJM, which the release does not name.

Calibrant pitches on-site batteries as giving data centers control over how and when they draw power, which it says supports faster interconnection and reduces grid upgrades whose cost would otherwise pass to other ratepayers, while PJM and federal regulators work through how large loads connect (FERC's ruling on PJM's large-load rules). Its more than 5.9 GWh of batteries in operation, in construction or under exclusive development agreements include more sites for the same customer.