Interconnection queues and costs in the US
Who gets into the queue, who pays for the grid upgrades and how data centers get connected: the standing record of US interconnection reform, cost fights and large-load rules.
Where things stand
As of November 21, 2026, the reformed US interconnection queues are moving; the arguments are over who gets cut, who pays for upgrades and how data-center load gets in. Only 13% of the capacity that applied from 2000 to 2020 had reached commercial operation by the end of 2025, per Lawrence Berkeley National Laboratory's Queued Up 2026 edition, when about 8,200 projects sought interconnection: 1,312 GW of generation and roughly 749 GW of storage, a 10% drop in active volume from a year earlier.
The rulebook, FERC's Order No. 2023 (effective November 6, 2023), swapped serial queues for first-ready, first-served cluster studies, penalizing developers who withdraw and providers who study late.
PJM says no backlog remains from its old queues. Phase I of Cycle 01, its first reformed cycle, began September 28, 2026 with 617 projects and nearly 169 GW: storage leads the count with 265 projects, natural gas the capacity with 81.1 GW. FERC has upheld two of PJM's Cycle 01 removals, Oklo's 750-MW project on September 24 (one chance to cure) and Advantage Capital Renewables' storage project on October 1. Neither developer has sought rehearing, and complaints by Agilitas Energy, RWE Americas and Lanyard Power remain pending. PJM's Expedited Interconnection Track accepted its first projects on September 30: two ENGIE batteries and a gas upgrade.
East Point Energy pulled its 125-MW Tewksbury battery from ISO New England's queue after the transitional cluster study put $65.3 million of upgrades on its position (our coverage); the Siting Board cancelled its October 27 hearing but has not ruled on the withdrawal motion. Since November 1, Massachusetts has replaced last-customer-pays charges for small solar and battery systems with a $225 pooled fee.
PJM has no load interconnection queue; utilities submit large-load adjustments to its forecast. MISO asked FERC on October 2 to study pairing loads of at least 200 MW with new generation. ISO New England filed large-load rules November 13. On November 16 PJM proposed a 12-month joint study of large-load service and generation, plus ride-through rules; CAISO, NYISO and MISO filed too. SPP followed November 18 and 19. NERC filed its computational-load standards at FERC November 17.
PJM refiled its Reliability Backstop Procurement on October 29, aiming to start it March 1, 2027. FERC's September 29 order accepted the procurement but suspended it to February 28, 2027, and said PJM should use up-to-date forecasts to set the target, which PJM filed at up to 6,831 MW. The Market Monitor, per the order's summary, puts the 2028/2029 shortfall at 3,055 MW after 4,017 MW of data-center load was cancelled or delayed (our coverage).
FERC rejected PJM's Interim Resource Adequacy Service (IRAS) on October 9, finding parts of it appeared to intrude on retail rate regulation; it would have curtailed new large loads in real-time shortages unless new backstop or bring-your-own capacity offset them. It accepted a 50 MW Large Load definition and the Large Load Registry Google and Constellation backed (our coverage), effective October 12.
Timeline
- 2026
-
SPP's filings suspended its show-cause response.
-
SPP made section 205 filings answering FERC's June 18 large-load order: transmission service changes for High Impact Large Loads (ER27-559), filed November 18; a Load Safe Harbor Limit (ER27-577) making customers pay and secure delivery-point upgrade costs above a threshold; and Price Adaptive Load Service (ER27-578), non-firm service with energy bids capped at $25/MWh, targeted for 2028's second quarter.
-
NERC filed its computational-load standards (RD27-3), asking FERC for expedited action.
-
PJM answered FERC's June 18 large-load order with section 205 filings and asked FERC to close its section 206 side. Fast Energization (ER27-531) would study generation and large-load transmission service in one 12-month process, half the current cycle's time, from late November 2027 into 2029 by PJM's estimate; interim and contract-demand services would take effect March 16, 2027. Ride-through rules would take effect January 16, 2027; the transmission owners filed cost allocation and rates, including ten-year-minimum cost recovery agreements.
-
CAISO filed its large-load tariff amendment (ER27-532), asking that most of it take effect February 16, 2027 and that FERC close its show-cause proceeding; permanent flexible service awaits a stakeholder initiative expected in 2027. PG&E and SCE filed 15-year minimum revenue obligations, and New York's transmission owners filed cost recovery agreements; NYISO and MISO filed large-load rules.
-
Hillman asked the Siting Board to defer ruling on its withdrawal motion, saying a company is evaluating whether to continue developing the Tewksbury battery; it will update the Board by December 18.
-
ISO New England, NEPOOL and the transmission owners filed large-load rules (ER27-484) answering FERC's June 18 show-cause order: loads of 50 MW or more above 60 kV get firm service once they bring their own new capacity and their upgrades are in service, otherwise non-firm service, all or part re-dispatched when local prices top $250/MWh. Applications would open June 1, 2027, service June 1, 2028.
-
PJM moved to withdraw ER27-330 in favor of ER27-454, citing a clerical filing-code error.
-
PJM filed the Large Load tariff language FERC's October 9 order required and refiled its backstop as ER27-454, which it calls substantively identical to ER27-330. Ohio's Consumers' Counsel sought rehearing of the October 9 order.
-
PJM materials said it would make several section 205 filings on or about November 16.
-
Florida regulators denied Duke Energy Florida's large-load tariff as filed, the first case under the state's 50 MW law: it covered only firm load, and Duke had not shown it reasonably ensures each customer bears its own full cost of service. Duke must refile covering all such customers, with a cost-supported rate schedule (vote sheet). Tampa Electric's, FPUC's and FPL's proposed tariff changes were suspended for review.
-
PJM refiled its backstop (ER27-330), aiming to start it March 1, 2027 and asking FERC to rule by January 29, 2027. It keeps the October 22 deck's cost allocation, collateral and opt-out terms and adds a bidding week so Cycle 01 developers can see Phase I results, scheduled by March 26, 2027 (filing).
-
CAISO's board voted 5-0 to approve its large-load show-cause response (EL26-71): a 50 MW definition, flexible interim service until upgrades are complete, and public large-load upgrade cost estimates (motion; memo).
-
FERC moved the backstop paper hearing's initial and reply briefs (EL26-108) from November 13 and December 3 to January 11 and 26, 2027.
-
PJM's refiling deck proposed costs allocated by firm large-load growth, collateral of 40% of discounted total obligations and no co-op and municipal opt-out (deck).
-
Missouri regulators approved Ameren Missouri's 250 MW Millcreek battery (order); its application says the site can use MISO's Expedited Resource Addition Study for an interconnection agreement in as little as three to four months (application).
-
Pennsylvania Gov. Josh Shapiro petitioned to intervene in the state consumer advocate's October 2 complaint against PPL Electric Utilities, which seeks, among other things, a data-center rate class, tariff provisions making data centers pay the network upgrade costs they cause, and interconnection and load-shed rules protecting existing customers (complaint).
-
NERC's computational-load reliability standards passed final ballots (notice); they cover sites with at least 50 MW of total connected load supplied through equipment connected at 100 kV or above (CLO-001-1). They set no industry-wide minimum voltage and frequency ride-through requirements, work NERC says is progressing in its Large Loads Working Group (FAQ).
-
PJM asked FERC to pause the backstop paper hearing (ER26-3380, EL26-108) pending a refiling (motion).
-
PJM could call on backup generation, which DOE says it sought at data centers and other large sites, as a last resort before declaring or during an EEA 3, October 13 to 16, after DOE authorized it at PJM's request. The order says backup run under it "shall not be considered a capacity resource."
-
FERC accepted Duke Energy Carolinas' revised pro forma network integration transmission service agreement, effective August 1 (ER26-2691): a network customer adding 100 MW or more of new or transferred load commits to pay for at least 75% of its scheduled MW for 15 years after the network upgrades serving it enter service, paying any shortfall, and network upgrade costs roll into Duke's transmission rates by default. Commissioner Rosner, concurring, wrote Duke's existing tariff "includes zero protections safeguarding residential consumers and small businesses from bearing the costs of transmission for new large loads such as data centers"; Commissioner Chang dissented, finding Duke had not shown the commitment adequately protects existing customers given the lack of meaningful security and an unexplained 75% threshold (order).
-
FERC accepted PJM's definition of Large Load, a cumulative peak of 50 MW, and its Large Load Registry, effective October 12, and rejected the rest of the ER26-3515 filing, including IRAS and the Bring Your Own New Capacity rules, as an integrated package; it found parts of the proposal appear to present an impermissible intrusion on retail rate regulation, directed a 30-day compliance filing dropping New Large Load, and gave guidance should PJM refile. Commissioner Rosner, concurring, wrote a refiled proposal must justify curtailing IRAS load on a mandatory basis before load voluntarily enrolled in demand response (order).
-
PJM announced the first three projects accepted into its Expedited Interconnection Track, over 2,100 MW of nameplate capacity slated to come online in mid-2029: ENGIE IR Holdings' Wayne 345 kV (860 MW) and Galion 345 kV (800 MW) storage projects, and Hunterstown 500 kV, a 455 MW upgrade to an existing gas facility (PJM). The track sunsets at the end of 2027.
-
DOE intervened in PJM's backstop docket (ER26-3380) in support of FERC's September 29 order, saying PJM should adopt the cost allocation and other reforms FERC identified so the costs of serving new data centers and other large loads are not unfairly shifted to existing ratepayers.
-
PJM staff brought the Planning Committee revised ride-through rules for large computational loads, covering facilities of 50 MW or more with at least 25 MW served through power electronics (deck).
-
Google and Constellation Energy announced a 20-year agreement that Constellation says will add 890 MW of uprates at 11 of its nuclear units in Illinois, Pennsylvania and New Jersey, plus a 15-year agreement for an additional 2,700 MW from its operating PJM fleet; the release calls the deal "a direct response to PJM's 'Bring Your Own Power' proposal" (Constellation).
-
MISO filed its Large Load Addition Resource Study (LARS) at FERC (ER27-25): a study of about 120 days for a load of at least 200 MW and new generation in the same local resource zone, ten applications per study period and three periods a year, with the pair bound for at least 15 years and an entry milestone of $30,000 per MW. MISO asked for an order by December 2 to start the first study period in the first quarter of 2027, and says LARS also responds to FERC's June 18 show-cause order on its large-load rules (transmittal letter).
-
ISO New England published a capacity heatmap and a queue map and said developers can submit requests for its first full cluster study between October 5 and November 19; battery storage, it says, forms the bulk of the current queue.
-
FERC denied Advantage Capital Renewables' complaint over PJM's withdrawal of its Freshwater Dune storage project from Cycle 01 (EL26-99). The order finds the cure submission left eight deficiencies unresolved and that PJM's Dynamic Model Development Guidelines are implementation details that need not be in the tariff; the developer can still try to cure the errors and submit the project to Cycle 02.
-
FERC accepted PJM's Reliability Backstop Procurement for filing and suspended it to February 28, 2027, sending cost allocation, transmission-owner exit rules and buyer collateral to a paper hearing (order).
-
Twelve utilities presented large-load adjustments, primarily data centers, to PJM's Load Analysis Subcommittee for the 2027 load forecast. PJM now requires contract status to tell firm commitments from the rest, has hired Charles River Associates to assess data-center demand, and will publish the forecast in January.
-
Constellation told FERC PJM's large-load proposal in ER26-3515 exceeds the Commission's jurisdiction and discriminates based on load size, load date and resource vintage, and asked it to "reject PJM's Proposal (other than the proposal to create the Large Load Registry)"; Google's September 3 protest likewise asked FERC to accept the registry, "the only legally defensible part of PJM's proposal," and reject IRAS (answer; protest).
-
Phase I of PJM's Cycle 01 began with 617 projects and 168.6 GW of nameplate capacity; PJM says 49 GW of generation already holds signed agreements, many of those projects not being built or slowed by permitting and supply chain backlogs.
-
FERC denied Oklo's complaint over its 750-MW project (EL26-101), reading PJM's tariff as one opportunity to cure after a timely deficiency notice (order).
-
FERC dismissed the requests for rehearing and clarification of its June 18 PJM large-load order (EL26-67), finding the show-cause order was not final.
-
Oklo told FERC the five-cycle fault test PJM ran is not in PJM's own modeling guidelines (answer).
-
Current Hydro withdrew, without prejudice, its September 1 complaint against PJM in docket EL26-102.
-
PJM first proposed ride-through requirements for large computational loads: return to more than 90% of pre-disturbance consumption within 2 seconds after voltage recovers, and a continuous range of 58.8 to 61.2 Hz (deck).
-
PJM asked FERC to deny Oklo's complaint, saying the cured model was unstable when the whole facility was tested at 750 MW and that reinstatement could delay Cycle 01's Phase I by as much as two months (answer).
-
Hillman Energy Center, East Point Energy's project company, moved to withdraw its Siting Board petition for a 125 MW / 500 MWh battery in Tewksbury, Massachusetts, saying it had also pulled the project from the queue because cluster study upgrade costs "greatly exceeded previous estimates, making this project economically unviable" (motion; docket).
-
Oklo filed an emergency complaint asking FERC to reinstate its 750-MW project of 150 MW advanced nuclear, 300 MW fuel cells and 300 MW natural gas, which PJM withdrew from Cycle 01 on August 3 (complaint).
-
FERC held its PJM large-load show-cause proceeding (EL26-67) in abeyance for 90 days, making responses due November 16 and answers December 16; a section 205 filing on the order's findings by then suspended a response.
-
PJM asked FERC (ER26-3515) to approve a Large Load Registry, a large-load database, and an Interim Resource Adequacy Service (IRAS), used only in real-time shortages to prioritize load reduction in zones where new large loads had neither brought their own new capacity nor been covered by the backstop procurement.
-
The Massachusetts Department of Public Utilities stamp-approved a non-refundable $225 Common System Modification Fee for listed inverter-based solar and battery systems of 25 kW or less, which pays up to $10,000 of upgrades for Eversource and National Grid customers and up to $1,450 for Unitil customers, effective November 1 (D.P.U. 26-57).
-
ISO New England's final Transitional Cluster Study report covered 23 projects totaling 4,826.5 MW of summer capacity; its estimates run from $672,500 to $540.6 million for the 18 positions that carry them, including $65.3 million for the Tewksbury position.
-
PJM accepted 715 projects, 201.5 GW, into Cycle 01 from 811 applications.
-
PJM opened its Expedited Interconnection Track for large generation projects backed by a primary siting authority that can start operating within three years, up to 10 requests per calendar year in 2026 and 2027.
-
A fault on one 230 kV line in the Dominion zone sent approximately 3,800 MW of northern Virginia data center load to backup power, the largest such transfer in PJM's history (deck; PJM review).
-
FERC directed NERC to file reliability standards and glossary definitions addressing the risks of integrating computational loads by December 31, and expects Rules of Procedure revisions with registry criteria by then (RD26-7).
-
Massachusetts Energy and Environmental Affairs Secretary Rebecca Tepper wrote to ISO New England that its cluster study identified "more than $3 billion in total interconnection costs"; ISO New England replied on June 29 the transmission investment in the interim report "is driven by the volume and location of proposals in the TCS" (letters).
-
FERC opened a section 206 proceeding on PJM's large-load transmission service, noting "the Tariff does not specify ramp rate or ride-through requirements with which the transmission customer taking transmission service on behalf of the large load must comply" (order); it issued a show-cause order on MISO's large-load rules the same day, per MISO's LARS filing.
-
PJM finished Phase II of its last transition cycle, 270 projects of about 30 GW, and said system network upgrade costs fell $8.7 billion from Phase I, mostly because of transmission its board approved in February and partly because 180 projects withdrew.
- 2023
-
FERC's Order No. 2023 took effect, requiring cluster studies, readiness deposits, site control and withdrawal penalties, and replacing the reasonable-efforts standard with penalties of $1,000 to $2,500 per business day on late studies.
Next milestone
- 2026-11-30: Comments due on PJM's refiled backstop (ER27-454).
- 2026-12-02: MISO's requested FERC ruling date on LARS.
- 2026-12-04: Comments due on ISO New England's large-load rules (ER27-484).
- 2026-12-07: Comments due on PG&E, SCE, New York owners and PJM ride-through filings.
- 2026-12-14: Comments due on NYISO's large-load rules (ER27-517).
- 2026-12-16: Comments due on MISO's ER27-526 and CAISO's ER27-532.
- 2026-12-17: Comments due on NERC's standards (RD27-3).
- 2026-12-18: Hillman's Tewksbury update to the Siting Board due.
- 2027-01-11: Initial briefs due in PJM's backstop paper hearing, unless paused.
- 2027-01-15: Comments due on Fast Energization and PJM owners' filing.
PJM asked for a Fast Energization order within 120 days.
This is a maintained page: it is revised as the record changes, and every revision is reviewed before it goes live. Dates in the text are the dates the facts hold for, not the date you are reading it.
Sources
Primary
- Letter order granting abeyance, Southwest Power Pool, Inc. et al., Docket No. EL26-68-000 (196 FERC ¶ 61,128) · Federal Energy Regulatory Commission
- Combined Notice of Filings #1 (November 10, 2026), including Docket No. ER27-454-000 · Federal Energy Regulatory Commission
- Motion to Withdraw Filing and Terminate Proceeding in Deference to New Docket No. ER27-454-000, PJM Interconnection, L.L.C., Docket Nos. ER27-330-000 and ER27-330-001 · PJM Interconnection, L.L.C. (filed with the Federal Energy Regulatory Commission)
- FERC, Combined Notice of Filings #2, November 13, 2026 · Federal Energy Regulatory Commission
- California Independent System Operator Corporation, Large Loads Tariff Amendment, Response to Order to Show Cause, Docket No. ER27-532-000 · California ISO (filed with the Federal Energy Regulatory Commission)
- Hillman Energy Center, EFSB 26-02: Letter Request to Defer Ruling on Motion to Withdraw · Hillman Energy Center LLC (filed with the Massachusetts Energy Facilities Siting Board)
- PJM Interconnection, L.L.C., Proposed Tariff Revisions for Large Loads and Additional Compliance with Co-Location Order and Request for Extended 60-Day Comment Period, Docket No. ER27-531-000 · PJM Interconnection (filed with the Federal Energy Regulatory Commission)
- PJM Interconnection, L.L.C., Operational Requirements for Large Computational Load and Annual Reporting, Docket No. ER27-522-000 · PJM Interconnection (filed with the Federal Energy Regulatory Commission)
- FERC, Combined Notice of Filings #1, November 16, 2026 · Federal Energy Regulatory Commission
- New York Independent System Operator, Inc., Proposed Tariff Revisions to Establish New Large Load Integration Procedures and Related Market Participation Provisions, Docket No. ER27-517-000 · NYISO (filed with the Federal Energy Regulatory Commission)
- New York Transmission Owners, Section 205 Filing in Response to the Large Load Show Cause Order, Docket No. ER27-529-000 · New York Transmission Owners (filed by NYISO with the Federal Energy Regulatory Commission)
- Combined Notice of Filings #1, November 17, 2026, including Docket No. RD27-3-000 · Federal Energy Regulatory Commission
- Errata Notice Extending Comment Period, New York Independent System Operator, Inc., Docket No. ER27-517-000 · Federal Energy Regulatory Commission
- Errata Notice Extending Comment Period, PECO Energy Company, Docket No. ER27-520-000 · Federal Energy Regulatory Commission
- Southwest Power Pool, Inc., Submission of Tariff Revisions to Enhance Transmission Service Provisions for High Impact Large Loads and Clarify Interconnection and Market Registration Requirements for Non-Transmission Facilities in Response to Show Cause Order, Docket No. ER27-559-000 · Southwest Power Pool (filed with the Federal Energy Regulatory Commission)
- FERC, Combined Notice of Filings #1, November 18, 2026 · Federal Energy Regulatory Commission
- Southwest Power Pool, Inc., Submission of Tariff Revisions to Establish Load Safe Harbor Limit for Delivery Point Costs, Docket No. ER27-577-000 · Southwest Power Pool (filed with the Federal Energy Regulatory Commission)
- Southwest Power Pool, Inc., Submission of Tariff Revisions to Add the Price Adaptive Load Service, Docket No. ER27-578-000 · Southwest Power Pool (filed with the Federal Energy Regulatory Commission)
Supporting
- Improvements to Generator Interconnection Procedures and Agreements (Order No. 2023), 88 FR 61014 · Federal Energy Regulatory Commission (Federal Register)
- Application (Public), Case No. EA-2026-0183 · Ameren Missouri (Union Electric Company)
- Proactive Planning Lowers Connection Costs by $8.7 Billion, Paves Way for More Generation · PJM Interconnection (Inside Lines)
- Order Instituting Proceeding Under Section 206, PJM Interconnection, L.L.C., Docket No. EL26-67-000 (195 FERC ¶ 61,211) · Federal Energy Regulatory Commission (PJM-hosted copy)
- Letters between Massachusetts EEA Secretary Rebecca Tepper (June 25, 2026) and ISO New England CEO Vamsi Chadalavada (June 29, 2026) · ISO New England (combined letters PDF)
- EFSB 26-02 docket (Hillman Energy Center certificate petition) · Massachusetts DPU/EFSB fileroom
- Order Directing the North American Electric Reliability Corporation to File Reliability Standard(s) Pertaining to Computational Load Integration, Docket No. RD26-7-000, 196 FERC ¶ 61,031 · Federal Energy Regulatory Commission
- PJM Begins Accepting Expedited Interconnection Track Requests · PJM Interconnection (Inside Lines)
- Over 700 New Generation Projects Accepted Into First Cycle of Reformed Interconnection Process · PJM Interconnection (Inside Lines)
- July 22, 2026 Dominion Load Transfer Event (Operating Committee, August 6, 2026) · PJM Interconnection / Dominion Energy
- Transitional Cluster Study - Final Report (ISO-NE PUBLIC), August 6, 2026 · ISO New England Inc. (copy hosted by WBUR)
- PJM, Dominion Review Large Load Transfer Event · PJM Interconnection (Inside Lines)
- D.P.U. 26-57: Common System Modification Fee tariffs (stamp-approved August 12, 2026) · Massachusetts Department of Public Utilities
- Proposal of PJM Interconnection, L.L.C. to Establish Interim Resource Adequacy Service and a Large Load Registry to Address System Reliability, Docket No. ER26-3515-000 · PJM Interconnection, via FERC eLibrary
- Letter order granting abeyance, PJM Interconnection, L.L.C., Docket No. EL26-67-000 (196 FERC ¶ 61,129) · Federal Energy Regulatory Commission
- Emergency Complaint of Oklo Inc. v. PJM Interconnection, L.L.C. (Docket No. EL26-101-000) · US Federal Energy Regulatory Commission (eLibrary)
- Motion of Hillman Energy Center to Withdraw (EFSB 26-02) · Massachusetts Energy Facilities Siting Board
- Protest of Google LLC, Docket No. ER26-3515-000 · Google LLC, via FERC eLibrary
- Answer of PJM Interconnection, L.L.C. (Docket No. EL26-101-000) · US Federal Energy Regulatory Commission (eLibrary)
- PJM LCL Ride-through Requirements: PJM Interconnection Proposal (Planning Committee, September 8, 2026) · PJM Interconnection
- Notice of Withdrawal of Complaint, Current Hydro LLC v. PJM Interconnection, L.L.C., Docket No. EL26-102-000 · US Federal Energy Regulatory Commission (eLibrary)
- Motion for Leave to Answer and Answer of Oklo Inc. (Docket No. EL26-101-000) · US Federal Energy Regulatory Commission (eLibrary)
- Order Dismissing Requests for Rehearing and Clarification, PJM Interconnection, L.L.C., Docket No. EL26-67-001 (196 FERC ¶ 61,214) · Federal Energy Regulatory Commission
- Order Denying Complaint, Oklo Inc. v. PJM Interconnection, L.L.C., Docket No. EL26-101-000, 196 FERC ¶ 61,231 · US Federal Energy Regulatory Commission (eLibrary)
- PJM Kicks Off Annual Process of Vetting Large Load Requests · PJM Interconnection (Inside Lines)
- Motion for Leave to Answer and Answer of Constellation Energy Generation, LLC, Docket No. ER26-3515-000 · Constellation Energy Generation, LLC, via FERC eLibrary
- Order Accepting Reliability Backstop Procurement and Establishing Further Procedures, 196 FERC ¶ 61,245, Docket Nos. ER26-3380-000 and EL26-108-000 · Federal Energy Regulatory Commission
- Over 600 Projects Enter Phase I of PJM's New Interconnection Process · PJM Interconnection (Inside Lines)
- Order Denying Complaint, Advantage Capital Renewables, LLC v. PJM Interconnection, L.L.C., Docket No. EL26-99-000, 197 FERC ¶ 61,006 · US Federal Energy Regulatory Commission (eLibrary)
- Interactive heatmap provides insights into what areas of the New England grid might best support new capacity · ISO New England (ISO Newswire)
- Midcontinent Independent System Operator, Inc.'s Large Load Addition Resource Study Process (transmittal letter), Docket No. ER27-25-000 · US Federal Energy Regulatory Commission (eLibrary)
- Office of Consumer Advocate Formal Complaint and Public Statement, Pennsylvania Consumer Advocate v. PPL Electric Utilities Corporation · Pennsylvania Office of Consumer Advocate (PA PUC docket C-2026-3065756)
- PJM Large Computational Load (LCL) Ride-Through Requirements: PJM Interconnection Proposal (Planning Committee, October 6, 2026) · PJM Interconnection
- Google and Constellation Announce Landmark Agreement to Bring 890 MW of New Nuclear Capacity to PJM Grid as Part of Long-Term Power Deal · Constellation Energy Corporation
- Notice of Intervention and Statement of Position of the United States Department of Energy, Docket Nos. ER26-3380-000 and EL26-108-000 · US Department of Energy, via FERC eLibrary
- EIT Requests Status · PJM Interconnection
- PJM Accepts First Expedited Interconnection Track Projects · PJM Interconnection (Inside Lines)
- Standards Announcement: Project 2026-02 Computational Loads, Final Ballots Open through October 14, 2026 · North American Electric Reliability Corporation (NERC)
- Order Accepting Tariff Revisions in Part and Rejecting Tariff Revisions in Part, PJM Interconnection, L.L.C., Docket No. ER26-3515-000, 197 FERC ¶ 61,019 · Federal Energy Regulatory Commission
- Order Accepting Proposed Tariff Revisions, Duke Energy Carolinas, LLC, Docket Nos. ER26-2691-000 and ER26-2691-001, 197 FERC ¶ 61,020 · Federal Energy Regulatory Commission
- FAQ: Computational Loads, Registry Criteria and Project 2026-02 Standards (October 2026) · North American Electric Reliability Corporation (NERC)
- CLO-001-1 Computational Load Interconnection, Studies, & Modeling Data (final draft) · North American Electric Reliability Corporation (NERC)
- DOE Order No. 202-26-50 (PJM Interconnection, L.L.C., Regarding Specified and Backup Generation Resources) · U.S. Department of Energy
- Motion for Abeyance of PJM Interconnection, L.L.C., Docket Nos. ER26-3380-000 and EL26-108-000 · PJM Interconnection, L.L.C.
- Petition to Intervene of Governor Josh Shapiro, Pennsylvania Consumer Advocate v. PPL Electric Utilities Corporation, Docket No. C-2026-3065756 · Pennsylvania Public Utility Commission (filed by the Governor's Office of General Counsel)
- NERC's Computational Loads Standards Pass Final Ballot, Advance to Board Adoption · North American Electric Reliability Corporation (NERC)
- Order Approving Stipulation and Agreement and Granting Certificates of Convenience and Necessity, Case No. EA-2026-0183 (with the Non-Unanimous Stipulation and Agreement attached) · Missouri Public Service Commission
- Staff recommendation, Docket No. 20260064-EI, Petition for a limited proceeding to approve large load tariff, by Duke Energy Florida, LLC · Florida Public Service Commission staff
- Decision on Large Load Enhancements - Memo (Response to FERC Large Loads Order to Show Cause) · California ISO
- Tariff, Section 9.2(b) Stakeholder Consultation of Upcoming 205 Filing on Reliability Backstop Procurement (Special MC, October 22, 2026) · PJM Interconnection
- Notice Addressing Motion to Hold Proceeding in Abeyance, PJM Interconnection, L.L.C., Docket Nos. ER26-3380-000 and EL26-108-000 · Federal Energy Regulatory Commission
- EFSB 26-02, Hillman Energy Center: presiding officer correspondence cancelling the October 27, 2026 adjudicatory hearing · Massachusetts Energy Facilities Siting Board
- Decision on Large Load Enhancements - Motion - Oct 28, 2026 · California ISO Board of Governors
- PJM's Response Matrix to the Large Load Show Cause Order Opportunities · PJM Interconnection
- PJM Interconnection, L.L.C., Proposed Amendments to the Reliability Backstop Procurement, Docket No. ER27-330-000 (transmittal letter) · PJM Interconnection (filed with the Federal Energy Regulatory Commission)
- Vote sheet, November 3, 2026 Commission Conference, Item 9, Docket No. 20260146-EI (Tampa Electric large load tariffs) · Florida Public Service Commission
- Vote sheet, November 3, 2026 Commission Conference, Item 10, Docket No. 20260148-EI (Florida Public Utilities large load tariff) · Florida Public Service Commission
- Vote sheet, November 3, 2026 Commission Conference, Item 11, Docket No. 20260149-EI (FPL large load contract service tariff) · Florida Public Service Commission
- Vote sheet, November 3, 2026 Commission Conference, Item 3, Docket No. 20260064-EI (Duke Energy Florida large load tariff) · Florida Public Service Commission
- PJM Interconnection, L.L.C., Thirty-Day Compliance Filing to the Commission's October 9, 2026 Order on PJM's Large Load Definition and Large Load Registry, Docket No. ER26-3515-002 · PJM Interconnection (filed with the Federal Energy Regulatory Commission)
- PJM Interconnection, L.L.C., Proposed Amendments to the Reliability Backstop Procurement, Request for Waiver of Tariff Attachment DD, Sections 16.2 and 16.3, Docket No. ER27-454-000 · PJM Interconnection (filed with the Federal Energy Regulatory Commission)
- Request for Rehearing to Promote Transparency for Ohio Consumers by the Office of the Ohio Consumers' Counsel, Docket No. ER26-3515-000 · Office of the Ohio Consumers' Counsel (filed with the Federal Energy Regulatory Commission)
- ISO New England Inc. et al., Revisions to ISO New England Inc. Transmission, Markets and Services Tariff Related to the Integration of Large Loads to the Transmission System, Docket No. ER27-484-000 (transmittal letter and testimony) · ISO New England Inc., NEPOOL Participants Committee and Participating Transmission Owners (filed with the Federal Energy Regulatory Commission)
- Southern California Edison Company, Large Load Show Cause Order Response, TO Tariff Revisions, Docket No. ER27-508-000 · Southern California Edison (filed with the Federal Energy Regulatory Commission)
- Pacific Gas and Electric Company, Response to Large Load Order to Show Cause in EL26-71-000, TO Tariff Revisions, Docket No. ER27-513-000 · Pacific Gas and Electric Company (filed with the Federal Energy Regulatory Commission)
- Midcontinent Independent System Operator, Inc., Large Load Review, Cost Recovery and Transmission Services Filing, Docket No. ER27-526-000 · MISO (filed with the Federal Energy Regulatory Commission)
- PJM Transmission Owners, Tariff Revisions for Service to Co-Located Loads and Large Loads, Docket No. ER27-520-000 (submitted by PECO Energy Company) · PJM Transmission Owners (filed with the Federal Energy Regulatory Commission)
- Petition of the North American Electric Reliability Corporation for Approval of Reliability Standards to Support the Integration of Computational Load and Request for Expedited Action, Docket No. RD27-3-000 · North American Electric Reliability Corporation (filed with the Federal Energy Regulatory Commission)
- Queued Up: 2026 Edition, Characteristics of Power Plants Seeking Transmission Interconnection As of the End of 2025 · Lawrence Berkeley National Laboratory
Copies of cited sources are retained where available. If a link no longer resolves, request a copy at contact@theduckcurve.com.