#ferc
FERC backs MISO's penalty-free queue exit a month after the window closed
FERC on November 20, 2026 accepted MISO's DPP-2022 queue changes, effective October 19: a full M2 refund for projects leaving by Decision Point 2, a 50% (and $15,000/MW) upgrade-cost threshold, up from 35%, for penalty-free exit afterward, and a cap of one Phase III restudy for this and later cycles. MISO's queue now lists 218 DPP-2022 requests in Phase 3, against the 386 MISO counted in September.

NERC files data center reliability standards at FERC, asks for speed
NERC filed CLO-001-1, CLO-002-1 and CLO-003-1, a new family of reliability standards for computational loads such as data centers and crypto miners, at FERC on November 17, 2026, with revised FAC-001-5 and FAC-002-5, and asked for expedited action. Comments are due December 17.
SPP files $25/MWh bid cap for flexible loads in FERC large-load package
Southwest Power Pool filed a Price Adaptive Load Service at FERC on November 19, 2026 (ER27-578): non-firm service for flexible, price-sensitive loads whose energy bids are capped at $25/MWh, against MISO's $100, NYISO's $200 and ISO New England's $250/MWh triggers, with implementation targeted for the second quarter of 2028. A companion filing (ER27-577) directly assigns delivery-point upgrade costs above the lesser of $25 million or $500,000 per MW to the requesting customer.

Senate passes BAAJA permitting bill 62-33, sending it to the House
The Senate passed H.R. 2347, the vehicle for the Bipartisan American Affordability and Jobs Act, 62-33 on November 19, 2026, with the Capito substitute's permitting, transmission and data center cost provisions. The House, which passed H.R. 2347 as an unrelated tax bill in April, must now act on the Senate's version.

PJM transmission owners ask FERC for 10-year minimum data center contracts
The PJM Transmission Owners asked FERC on November 16, 2026 for a pro forma cost recovery agreement under which data centers commit for at least ten years to 80 to 100 percent of their firm transmission charges, backed by collateral sized to the full projected bill. PG&E and Southern California Edison proposed 15-year minimum revenue obligations backed by five years of security.

MISO and NYISO propose $100 and $200/MWh cutoffs for non-firm large loads
MISO and NYISO filed large-load rules at FERC on November 16, 2026, answering its June 18 show-cause orders. MISO's proposed GRITS service would interrupt non-firm load when local prices exceed $100/MWh; NYISO's Non-Firm Withdrawal Service carries a $200/MWh bid cap. MISO proposes a study of about five months, a $250,000 application fee and security equal to upgrade costs; NYISO's study cycle runs about 18 months to two years, and New York's utilities would recover a large load's upgrade costs over 15 years.

PJM asks FERC to study generators and large loads in one 12-month pass
PJM Interconnection filed its Fast Energization Process at FERC on November 16, 2026 (ER27-531), studying generator interconnection and Large Load transmission service requests together in one 12-month cluster that PJM says takes half the time of its current cycle. PJM asks for an order within 120 days and expects the first application window in late November 2027.

PJM files ride-through rules for data centers, existing ones included
PJM filed tariff revisions at FERC on November 16, 2026 (ER27-522) requiring transmission customers serving Large Computational Loads, 50 MW sites with 25 MW or more on power electronics, to meet minimum ride-through requirements set in PJM's manuals. Existing loads get no exemption; at the requested effective date they have until at least January 16, 2028 to comply.

ISO New England's large-load filing ties firm service to new capacity
ISO New England and the region's transmission owners filed large-load rules with FERC on November 13, 2026 (ER27-484): firm service for loads of 50 MW or more that bring new capacity, and interim or non-firm service re-dispatched above $250/MWh. Applications would open June 1, 2027.

Senate permitting bill gets substitute text two days before cloture vote
Senators Lee, Capito, Heinrich and Whitehouse released a substitute amendment to the Bipartisan American Affordability and Jobs Act on November 7, 2026, ahead of a November 9 cloture vote on the motion to proceed to H.R. 2347, its House-passed vehicle. Heatmap News reports the text makes transmission developers go to states for a year before seeking FERC's siting backstop; the text itself caps the behind-the-meter facilities its market-access rule covers at 5 MW.

Exelon asks FERC for a prompt PJM capacity auction; PJM pushes back
Exelon filed a FERC complaint on November 3, 2026 (EL27-11) asking that PJM replace its three-year-forward capacity auction with a prompt auction two months before delivery, starting with 2030/2031, and sought an order by January 31, 2027. PJM opposed fast-track processing on November 4 and asked until December 21 to answer; Invenergy filed a separate complaint (EL27-12) seeking MISO capacity accreditation for merchant HVDC lines.

ISO New England opens its markets to distributed energy aggregations
ISO New England began letting aggregators register pooled distributed energy resources, such as solar, storage, demand response and EVs with controllable charging, on November 1, 2026 under FERC Order No. 2222, with a 100 kW minimum. Energy and ancillary-service rules took effect that day. FERC's 2023 order had set November 1, 2022 for capacity-market rules aimed at the FCA 18 auction; ISO-NE's refresher now lists its capacity-market changes as effective for 2028-29.

PJM refiles its backstop procurement for March 2027 with lower collateral
PJM Interconnection filed an amended Reliability Backstop Procurement at FERC on October 29, 2026, in docket ER27-330-000, rewriting the cost allocation, load-serving-entity collateral and exit rules that FERC's September 29 order sent to a paper hearing. PJM now plans to open the procurement on March 1, 2027, post results on May 10, and asks FERC for an order by January 29, 2027.

CAISO board approves 50 MW large-load rules for its FERC filing
CAISO's Board of Governors voted 5-0 on October 28, 2026 to approve its answer to FERC's June large-load show-cause order: a 50 MW large-load definition, curtailable interim interconnection until network upgrades are built, and public postings of large-load upgrade costs, to be filed by November 16. The CPUC's Public Advocates Office and SCE argued CAISO leaves cost-shift protection too much to transmission owners.

FERC denies battery waiver; four Massachusetts projects leave ISO-NE queue
FERC on October 16, 2026 denied five Massachusetts battery developers' request to pause ISO New England's interconnection deadlines while it weighs their complaint against the Transitional Cluster Study. Four Massachusetts battery projects totaling 1,105 MW, including River Mill Storage's 500 MW project, left the queue on October 19 and 20.

FERC approves ISO-NE review of utilities' asset condition projects
FERC on October 16, 2026 accepted ISO New England as the region's Asset Condition Reviewer from January 1, 2027, an advisory role reviewing the need, cost-effectiveness and alternatives for transmission owners' larger projects to replace aging equipment.
NERC data center standards pass final ballot as Google, Meta, AWS vote no
NERC's three computational-load standards for data center and crypto sites of at least 50 MW at 100 kV or above passed a final ballot that closed October 14, 2026, with weighted segment values of 78.13 to 82.69 despite no votes from Google, Meta and Amazon Web Services. They go to NERC's board, then to FERC under a December 31, 2026 filing deadline.

Voltus raises $225M Series D, expects its platform to reach 20 GW by 2030
Voltus said on October 8, 2026 that it raised $225 million in a Series D led by Generation Investment Management, with Activate Capital and Vitol as co-leads, and expects to grow its platform to 20 GW by 2030 as it executes on its Bring Your Own Capacity program in PJM and MISO; its website lists 8.5 GW of distributed energy resources today. On October 9, FERC rejected PJM's IRAS and BYONC large-load rules, which Voltus had supported in September comments.

FERC rejects PJM's large-load curtailment plan, keeps the load registry
The Federal Energy Regulatory Commission on October 9, 2026 accepted PJM Interconnection's Large Load definition (a cumulative peak of 50 MW or more at one site) and a Large Load Registry, effective October 12, and rejected the rest of PJM's August 13 filing as one package, including the Interim Resource Adequacy Service, which would have curtailed new large loads not offset by new capacity in emergencies, and the Bring Your Own New Capacity rules. FERC said parts appeared to intrude on state retail-rate jurisdiction.

Google backs 890 MW of Constellation nuclear uprates at 11 PJM units
Google and Constellation Energy announced on October 6, 2026 a 20-year power purchase agreement backing uprates at 11 Constellation nuclear units in Illinois, Pennsylvania and New Jersey that Constellation says will add 890 MW to the PJM grid, the first by 2028, plus a 15-year agreement for 2,700 MW from its operating PJM fleet. Constellation calls it a direct response to PJM's bring-your-own-power proposal, which both companies have asked FERC to reject except its registry.

Interconnection queues and costs in the US
As of November 24, 2026, PJM's first reformed cycle has 617 projects in study and its backstop is refiled for a March 1, 2027 start; FERC has capped MISO's Phase III restudies at one from DPP-2022 on; PJM, SPP, CAISO, MISO, NYISO and ISO New England have filed large-load rules.
FERC accepts PJM backstop procurement but suspends it to February 2027
FERC on September 29, 2026 accepted PJM's one-time Reliability Backstop Procurement for filing in docket ER26-3380-000 but suspended it for five months, to February 28, 2027, subject to refund, set a paper hearing on cost allocation, transmission-owner exit rules and load-serving-entity collateral, and opened a section 206 proceeding. It found the core design, from eligibility rules to the $555/MW-day average price cap, just and reasonable and encouraged a new section 205 filing. PJM says the procurement will not begin on September 30 as planned.

FERC denies Oklo complaint; 750-MW project stays out of PJM's Cycle 01
The Federal Energy Regulatory Commission denied Oklo's complaint against PJM Interconnection on September 24, 2026, finding Oklo failed to show PJM violated its tariff when it withdrew Oklo's 750-MW nuclear, gas and fuel-cell project, which Utility Dive places in Virginia, from Cycle 01; the waiver request is moot. It reads section 403(B)(1) as one cure opportunity when PJM timely noticed deficiencies, concedes the five-cycle fault test is not in PJM's guidelines, and notes Oklo can cure the errors and refile for Cycle 02 or use the Expedited Interconnection Track, open to December 31, 2027.

Hydropower Licensing Transparency Act signed; FERC report within 180 days
The White House said the President signed H.R. 3657, the Hydropower Licensing Transparency Act, into law on September 25, 2026; the Library of Congress record dates both 'Signed by President.' and 'Became Public Law No: 119-112.' to September 25, 2026. The act adds a section 37 to the Federal Power Act: within 180 days of enactment and annually after that, FERC reports to Congress on each pending new license, subsequent license for which sections 14 and 15 have been waived, and original license for which a notice of intent was given at least three years earlier, with six inclusions each.
Congress moved four energy bills in three days; one goes to the President
Between September 15 and 17, 2026, the House passed the High-Capacity Grid Act (H.R. 6633) and the Load Forecasting Enhancement Act (H.R. 9332) by voice vote and the Ratepayer Protection Act (H.R. 9340) by 417 to 3, and the Senate passed the Hydropower Licensing Transparency Act (H.R. 3657) by unanimous consent without amendment; the bill status record shows that bill presented to the President on September 17 and the other three received in the Senate. Each orders a report, a rulemaking, study boards, or a state proceeding; none funds or builds anything.
Oklo tells FERC that PJM's fault test is not in PJM's own guidelines
Oklo's September 14, 2026 answer in FERC docket EL26-101-000 says its cure for the 750-MW project (150 MW nuclear, 300 MW gas, 300 MW fuel cells) passed the flat start test for the whole facility and the 9-cycle ride-through test for the inverter-based fuel cells, the only two stability tests it says PJM's guidelines contain, and calls PJM's explanation of the 5-cycle three-phase fault it ran a post hoc rationalization. PJM's answer says the cured model was unstable with all 750 MW in service. No FERC order was on the docket as of September 16.
PJM says Oklo's fix left the 750-MW model unstable, asks FERC to deny
PJM asked FERC on September 4, 2026 to deny Oklo's complaint over the withdrawal of its 750-MW project C01-1735 from Cycle 01. PJM says Oklo's response to a May 15 deficiency notice removed excitation-limiter models from the synchronous units and that the model showed an unstable response when PJM tested the whole facility at 750 MW; it says its tariff allows one cure round, that four other Oklo projects totaling 900 MW advanced, and that reinstatement could delay Phase I, set to start September 28, by as much as two months. It asks FERC to act by September 14 if it grants relief.

PJM proposes ride-through rules for data centers after 3,800 MW drop-off
PJM presented proposed voltage and frequency ride-through requirements for large computational loads, a category PJM says includes data centers and crypto-mining facilities, at its September 8, 2026 Planning Committee, after a July 22 fault in the Dominion zone that PJM's August 6 Operating Committee deck says sent approximately 3,800 MW of load onto backup power. PJM plans to file at FERC in November 2026 in docket EL26-67-000, where FERC faulted the tariff in June for specifying no ramp-rate or ride-through requirements and on August 14 paused the proceeding until November 16.

Virtual power plants in the US
As of November 19, 2026, US VPPs grow through state programs like New Jersey's PowerUp NJ and deals like Google's 1 GW Voltus VPP while Order 2222 market access arrives operator by operator and a Senate-passed bill would mandate it for qualifying behind-the-meter aggregations.
Oklo asks FERC to reinstate its 750-MW project in PJM's queue
Oklo filed an emergency complaint at FERC on August 28, 2026 (docket EL26-101-000) asking the commission to order PJM to reinstate a 750-MW mixed-technology generation project, combining advanced nuclear, natural gas, and fuel cells, that PJM withdrew from the first cycle of its reformed interconnection study. Oklo says the withdrawal was unlawful and would delay the project by at least 14 months; it wants PJM to answer by September 4, 2026.
