NERC files data center reliability standards at FERC, asks for speed
NERC has asked the Federal Energy Regulatory Commission to approve a new family of reliability standards for data centers, AI compute clusters and crypto miners about six weeks before FERC's deadline, and to move quickly on them. The petition, dated November 16, 2026 and filed November 17 in docket RD27-3-000, seeks approval of CLO-001-1 (interconnection, studies and modeling data), CLO-002-1 (operational data and communications) and CLO-003-1 (protection coordination and disturbance monitoring), plus FAC-001-5 and FAC-002-5, which exclude computational load sites from the existing interconnection standards to avoid duplicative requirements.
FERC's July 16 order in docket RD26-7-000 gave NERC until December 31, 2026 to file. NERC says its board adopted the package on October 26, "nearly two months earlier than originally targeted," after the final ballot in October. The petition asks for expedited action, including an expedited public comment period, because the reliability challenges of integrating large computational loads "are pressing, urgent, and real." FERC's notice of the filing sets the comment date at 5 pm Eastern on December 17, 2026. Public Citizen and Constellation Energy Generation have moved to intervene.
The case for urgency is load that took itself off the grid. The petition points to a 2024 Eastern Interconnection event in which a 230 kV line fault led to the loss of about 1,500 MW of voltage-sensitive load, all of it data center-type, and a July 2026 incident whose preliminary estimate is about 3,900 MW of load reduction from computational loads. NERC's petition does not name that event; the July 22 northern Virginia event that PJM described came to about 3,800 MW by PJM's count.
The standards would take effect on the first day of the first calendar quarter after FERC's approval order takes effect, with phased compliance: sites already in service by then get 36 months to meet CLO-003-1's disturbance monitoring requirements. Ride-through performance requirements are left to NERC's separate Project 2026-03, which focuses on voltage and frequency ride-through and post-fault active power recovery, though NERC calls CLO-003-1, with its protection-coordination requirements, "an important initial step toward addressing the confirmed risks associated with disturbance performance ride-through."
Sources
Primary
- Petition of the North American Electric Reliability Corporation for Approval of Reliability Standards to Support the Integration of Computational Load and Request for Expedited Action, Docket No. RD27-3-000 · North American Electric Reliability Corporation (filed with the Federal Energy Regulatory Commission)
Supporting
- Combined Notice of Filings #1, November 17, 2026, including Docket No. RD27-3-000 · Federal Energy Regulatory Commission
- Motion to Intervene of Public Citizen, Inc under RD27-3 · Public Citizen, Inc. (filed at FERC)
- Motion to Intervene of Constellation Energy Generation, LLC under RD27-3 · Constellation Energy Generation, LLC (filed at FERC)
Copies of cited sources are retained where available. If a link no longer resolves, request a copy at contact@theduckcurve.com.