#data centers
Wisconsin forecasts peak demand up about 40% by 2032, mostly data centers
The Public Service Commission of Wisconsin approved its 2026-2032 Strategic Energy Assessment in final form, announcing it on November 20, 2026. It forecasts statewide peak demand rising from about 14.2 GW in 2026 to 20 GW in 2032, with about 71% of the increase tied to three data center developments, and utilities planning about 14,400 MW of new capacity, led by 5,835 MW of solar and 5,230 MW of natural gas.

NERC files data center reliability standards at FERC, asks for speed
NERC filed CLO-001-1, CLO-002-1 and CLO-003-1, a new family of reliability standards for computational loads such as data centers and crypto miners, at FERC on November 17, 2026, with revised FAC-001-5 and FAC-002-5, and asked for expedited action. Comments are due December 17.
SPP files $25/MWh bid cap for flexible loads in FERC large-load package
Southwest Power Pool filed a Price Adaptive Load Service at FERC on November 19, 2026 (ER27-578): non-firm service for flexible, price-sensitive loads whose energy bids are capped at $25/MWh, against MISO's $100, NYISO's $200 and ISO New England's $250/MWh triggers, with implementation targeted for the second quarter of 2028. A companion filing (ER27-577) directly assigns delivery-point upgrade costs above the lesser of $25 million or $500,000 per MW to the requesting customer.

Senate passes BAAJA permitting bill 62-33, sending it to the House
The Senate passed H.R. 2347, the vehicle for the Bipartisan American Affordability and Jobs Act, 62-33 on November 19, 2026, with the Capito substitute's permitting, transmission and data center cost provisions. The House, which passed H.R. 2347 as an unrelated tax bill in April, must now act on the Senate's version.

PJM transmission owners ask FERC for 10-year minimum data center contracts
The PJM Transmission Owners asked FERC on November 16, 2026 for a pro forma cost recovery agreement under which data centers commit for at least ten years to 80 to 100 percent of their firm transmission charges, backed by collateral sized to the full projected bill. PG&E and Southern California Edison proposed 15-year minimum revenue obligations backed by five years of security.

MISO and NYISO propose $100 and $200/MWh cutoffs for non-firm large loads
MISO and NYISO filed large-load rules at FERC on November 16, 2026, answering its June 18 show-cause orders. MISO's proposed GRITS service would interrupt non-firm load when local prices exceed $100/MWh; NYISO's Non-Firm Withdrawal Service carries a $200/MWh bid cap. MISO proposes a study of about five months, a $250,000 application fee and security equal to upgrade costs; NYISO's study cycle runs about 18 months to two years, and New York's utilities would recover a large load's upgrade costs over 15 years.

US storage passes 200 GWh installed as Q3 additions slip 1% on the year
The US installed 14.3 GWh of energy storage in Q3 2026, 1% less than in Q3 2025, and has passed 200 GWh installed to date, according to SEIA and Benchmark Mineral Intelligence. Installations through September reached 48.3 GWh, up 20% year over year.

PJM asks FERC to study generators and large loads in one 12-month pass
PJM Interconnection filed its Fast Energization Process at FERC on November 16, 2026 (ER27-531), studying generator interconnection and Large Load transmission service requests together in one 12-month cluster that PJM says takes half the time of its current cycle. PJM asks for an order within 120 days and expects the first application window in late November 2027.

Google signs 50 MW superhot geothermal PPA with Quaise in Oregon
Google signed a power purchase agreement for 50 MW from Quaise Energy's Project Obsidian in Central Oregon, Quaise announced November 17, 2026, with deliveries as early as 2030 to support Google's data center operations in The Dalles. The first phase uses conventional drilling; Quaise's millimeter wave drill is slated for the second, and OPB reports a 10-mile line to La Pine is needed.

PJM files ride-through rules for data centers, existing ones included
PJM filed tariff revisions at FERC on November 16, 2026 (ER27-522) requiring transmission customers serving Large Computational Loads, 50 MW sites with 25 MW or more on power electronics, to meet minimum ride-through requirements set in PJM's manuals. Existing loads get no exemption; at the requested effective date they have until at least January 16, 2028 to comply.

Lydian's 600 MWh Utah battery is online; NYSERDA opens second storage round
Lydian Energy said on November 10, 2026 that its 150 MW / 600 MWh Faraday battery in Utah, contracted to PacifiCorp in support of Meta's Eagle Mountain data center, began operating on September 18. NYSERDA issued ISCRFP26-1, its second bulk storage solicitation, on November 12; the EBRD signed €50 million for a Tunisian solar plant with a 10 MW / 20 MWh battery, and Calibrant closed a $145 million debt facility.
Hyd'Occ opens, Oman's Duqm awards, Brazil's first H2 basic-grid access
Qair inaugurated Hyd'Occ, a 20 MW electrolysis plant it calls France's largest renewable hydrogen plant, on November 13, 2026. GE Vernova reported a 50% hydrogen blend validation and a 100% hydrogen test on two aeroderivative turbines; Oman's Hydrom awarded two Duqm projects targeting about 121,000 tonnes of green hydrogen a year by 2032; and Brazil's ANEEL authorized its first green hydrogen project to access the basic grid.
ISO New England's large-load filing ties firm service to new capacity
ISO New England and the region's transmission owners filed large-load rules with FERC on November 13, 2026 (ER27-484): firm service for loads of 50 MW or more that bring new capacity, and interim or non-firm service re-dispatched above $250/MWh. Applications would open June 1, 2027.

Oklo signs HALEU contracts with Centrus for Aurora reactors in Ohio
Oklo and Centrus Energy said on November 12, 2026 that Oklo signed definitive, multi-year contracts for enough HALEU to fuel up to five Aurora powerhouses for multiple years, with deliveries from Centrus's Pike County, Ohio plant scheduled to begin in 2029. Meta's prepayment for Oklo power supports the purchase; Oklo's 10-Q dates a supply agreement to September 30.

Cornell study: data centers shift grid costs onto rural, low-income homes
A Cornell study published in Nature Energy on November 9, 2026 finds that cumulative wholesale price increases attributable to data centers exceed 10% in the most exposed US hubs by 2025 and that regulated tariffs allocate residential customers a median 47% of costs despite their contributing far less to demand growth. Rural burden increases run 76% larger than urban ones, the lowest-income households face extra energy burdens of up to 28 percentage points, and local economic returns barely scale with incentive spending (spending elasticity 0.16).

Senate permitting bill gets substitute text two days before cloture vote
Senators Lee, Capito, Heinrich and Whitehouse released a substitute amendment to the Bipartisan American Affordability and Jobs Act on November 7, 2026, ahead of a November 9 cloture vote on the motion to proceed to H.R. 2347, its House-passed vehicle. Heatmap News reports the text makes transmission developers go to states for a year before seeking FERC's siting backstop; the text itself caps the behind-the-meter facilities its market-access rule covers at 5 MW.

PJM expects enough winter supply for a record peak near 147,500 MW
PJM Interconnection's winter outlook, published November 5, 2026, expects 182,426 MW of operational capacity against a forecast peak of about 147,500 MW, a would-be winter record, plus about 3,200 MW of exports, and says supply is sufficient under expected conditions. Its higher-stress scenarios reach 152,200 MW and rely on demand response; in the 2025–26 winter, generator outages ran above PJM's seasonal projection.

Brattle puts US distributed energy savings at $614 billion through 2050
A Brattle Group study for The Pew Charitable Trusts, released November 5, 2026, estimates that removing barriers to distributed solar, batteries and flexible demand would avoid $614 billion in US power system costs through 2050 (2026 dollars, undiscounted). It models distributed capacity growing from 113 GW to 524 GW and average household bills $122 a year lower by 2050, about half the projected rise above inflation.

Florida PSC denies Duke's large-load tariff, tells it to file a rate
The Florida Public Service Commission on November 3, 2026 denied Duke Energy Florida's large-load tariff as filed in the first case under Section 366.043, F.S., and directed Duke to file provisions covering all customers of 50 MW or more with a cost-supported large-load rate schedule. It suspended the large-load filings of Tampa Electric, FPL and Florida Public Utilities for review.

Synchronized battery software linked to a one-minute grid frequency wobble
A Nature Energy paper published October 30, 2026 links a one-minute oscillation in grid frequency, seen in 12 grids, to clock-synchronized control software in uninterruptible power supplies and battery storage. Also: DOE's BattMan consortium, Enphase's 13.8 kV solid-state transformer demo, First Solar's license to CubicPV's US perovskite patents, and Draslovka's deal for ex-Natron sodium-ion IP.
Entergy seeks approval for 350 MW of Google-backed batteries in Arkansas
Entergy Arkansas asked the Arkansas Public Service Commission on October 29, 2026 to approve the 250 MW Driver and 100 MW Jones Mill batteries, estimated at $550.6 million and scheduled for service June 1, 2028, saying Google's amended contract will cover their revenue requirement. The commission is separately questioning that contract, with Entergy's answers due November 9.

PJM refiles its backstop procurement for March 2027 with lower collateral
PJM Interconnection filed an amended Reliability Backstop Procurement at FERC on October 29, 2026, in docket ER27-330-000, rewriting the cost allocation, load-serving-entity collateral and exit rules that FERC's September 29 order sent to a paper hearing. PJM now plans to open the procurement on March 1, 2027, post results on May 10, and asks FERC for an order by January 29, 2027.

CAISO board approves 50 MW large-load rules for its FERC filing
CAISO's Board of Governors voted 5-0 on October 28, 2026 to approve its answer to FERC's June large-load show-cause order: a 50 MW large-load definition, curtailable interim interconnection until network upgrades are built, and public postings of large-load upgrade costs, to be filed by November 16. The CPUC's Public Advocates Office and SCE argued CAISO leaves cost-shift protection too much to transmission owners.

Antares clears a DOE gate, Finland licenses Onkalo, QuantumScape and Saft
DOE approved the Nuclear Safety Design Agreement for Antares' electricity-producing Mark-1 reactor, the company said October 23, 2026. QuantumScape plans a 100 MWh cell line with Muehlbauer, targeted for 2028, as PowerCo pauses milestone payments, Saft opened solid-state lines in Bordeaux without a capacity figure, and Finland's government granted Posiva what the company calls the first operating licence for spent-fuel final disposal on October 22.
Google expands its Voltus virtual power plant in PJM to 1 GW
Google and Voltus said on October 22, 2026 they will build a 1 GW virtual power plant in PJM, adding 1,070 MW of distributed capacity to a 100 MW agreement signed in June, with Voltus paying businesses and homes to cut demand when the grid is strained. The contract is voluntary: FERC rejected PJM's rules for new large loads to bring their own new capacity on October 9.

Peak Energy raises $108M as GM Ventures leads its sodium-ion storage round
Peak Energy said on October 21, 2026 it closed an oversubscribed Series B led by General Motors Ventures, with $108 million in new financing to scale US manufacturing of its passively cooled sodium-ion grid storage, fulfill over $1 billion in customer orders and launch its product to the data center market.
Indiana, Hoosier Energy and AtkinsRéalis to study up to 6 GW of CANDU units
AtkinsRéalis, the State of Indiana and Hoosier Energy have signed an MOU to explore a campus of up to eight CANDU reactors, up to 6.0 GW, with no site, cost estimate or schedule named. AtkinsRéalis's Enhanced CANDU 6 design is in NRC pre-application activities, and its plan says the company intends to submit a construction permit application once a customer is identified.

Entergy's Google expansion includes a solar deal Arkansas regulators denied
Entergy Arkansas said on October 19, 2026 that Google will pay for about $600 million of grid investment and a 440 MWac solar power purchase agreement for a second phase of its West Memphis data center, with at least $500 million in customer savings over 20 years starting in 2028. Arkansas regulators denied that solar contract, Big Island, on September 16, and staff and the attorney general oppose Entergy's rehearing request.

AEP, X-energy and Amazon study 960 MW Xe-100 plant at Indiana coal site
American Electric Power and X-energy signed a joint development agreement, announced October 19, 2026, to study a 960 MW plant of 12 Xe-100 reactors at the former Breed Generating Station coal site in Sullivan County, Indiana. Amazon is funding development and, if the plant is built, intends to buy its power under a long-term contract covering the facility's costs; none of the companies gave a cost estimate or schedule for the plant.

DOE puts up to $50M of Defense Production Act money into Virginia lines
The US Department of Energy said on October 16, 2026 it intends to give up to $50 million in Defense Production Act funding to a Virginia Energy project that would reconductor and add dynamic line rating to Appalachian Power lines for an estimated 290 MW of transmission capacity. Appalachian Power, which takes $40 million, calls it a SPARK award.
