PJM files ride-through rules for data centers, existing ones included
The November 16 FERC filing gives existing large computational loads until at least January 16, 2028 to comply, at its requested dates, and puts the voltage and frequency envelope in PJM's manuals, not its tariff.
PJM Interconnection filed tariff revisions at FERC on November 16, 2026 that would require the transmission customers serving data centers and other Large Computational Loads to meet minimum voltage and frequency ride-through requirements, and the rule reaches the approximately 10 GW of computational load already in PJM's footprint as well as what comes next. A Large Computational Load is a Large Load (a cumulative peak of 50 MW or more at one site) with 25 MW or more of maximum load served through power electronic conversion equipment. PJM asks for an effective date of January 16, 2027 and a FERC order by January 15, 2027, in the new docket ER27-522.
The filing settles the question our September coverage left open. PJM's September 8 deck had reproduced ERCOT's exemptions for loads operating or approved before November 14, 2025 without saying whether PJM would copy them. It will not. PJM principal engineer Byoungkon Choi says in his declaration that "unlike ERCOT and MISO, exempting existing facilities is not appropriate in PJM because the magnitude of existing computational load and its demonstrated operational impacts warrant consistent application of the requirements to both existing and new facilities."
Who has to comply, and by when
The proposed tariff sorts these loads into three groups: new loads, whose customers enter the study process on or after the effective date; existing sites that cross the 50 MW line or are otherwise materially modified on or after it; and transitional loads, any Large Computational Load whose customer, before the effective date, has formally initiated or completed an interconnection study with the transmission owner, executed an agreement authorizing interconnection, commenced construction, or achieved commercial operation. Transitional loads must comply by one year after the effective date or within one year of commercial operation, whichever is later; at the requested date, that is January 16, 2028 at the earliest.
The obligation sits on the Eligible Customer taking transmission service on the load's behalf, which under PJM's tariff can be, among others, a utility, a power marketer or a retail customer taking unbundled transmission service, and it applies whether that customer uses network service or one of the new large-load services PJM proposed the same day. Each customer or transmission owner sets its own requirements, no less stringent than PJM's minimum and stricter where the transmission owner finds that necessary, applied without undue discrimination to similarly situated loads.
The envelope lives in the manuals
What FERC is asked to approve is the obligation, not the numbers. The tariff says PJM "shall establish minimum voltage ride-through and frequency ride-through requirements," which "shall be set forth in the PJM Manuals." The voltage and frequency tables PJM showed stakeholders, including the 58.8 to 61.2 Hz continuous band on its October 28 slide to the Markets and Reliability Committee, are not in the tariff; PJM's letter says the manual language is "in an advanced stage of development." Two items the slide listed under "M14B Attachment D-2 & OATT Changes" are absent from the filed tariff text and the transmittal letter: that PJM may accelerate compliance to 90 days for reliability-risk loads, and that limited exceptions would be considered where requirements cannot be met.
PJM wants it that way. Choi's declaration argues PJM should be able to adjust the parameters "in a timely manner, without having to rely on a lengthy stakeholder process and subsequent FERC approval, which could delay implementation of necessary reliability improvements by months." It also reports: "Dominion's event analysis indicates that most LCL tripping during the July 22, 2026 event occurred within PJM's proposed voltage ride-through envelope." By Choi's reading, the envelope would likely have mitigated a significant portion of that morning's load transfers.
The filing counts three events: about 1.5 GW on July 10, 2024, about 1.8 GW on February 17, 2025, and about 3.9 GW on July 22, 2026. PJM's August event review, as we reported, had put both earlier events at about 1,500 MW.
The definition turns on power electronics rather than end use. PJM concluded that what matters is "the presence of large quantities of power electronic conversion equipment," testifies David Egan, PJM's senior manager for generation modeling and dynamic studies, a test broad enough to take in data centers "while also remaining applicable to other emerging load types that rely heavily on power-electronic conversion technologies, such as certain hydrogen production facilities and other future industrial processes."
The rest of the package
The tariff also adds placeholders for requirements PJM has not written yet: ramp rates, electromagnetic transient performance, auxiliary equipment and protection systems, maintenance outage timing, remote disconnection, control technology and telemetry, and data and communications. Each will be set in the manuals after stakeholder engagement PJM plans to start in early 2027, and PJM consents to FERC severing the ride-through rule from the rest to speed acceptance. The filing answers FERC's June 18 show-cause order, which faulted PJM's tariff for specifying no ramp-rate or ride-through requirements; filing by November 16 suspends PJM's obligation to respond to it.
The ride-through filing was one of several. In a companion filing, docket ER27-531, PJM proposes a Fast Energization Process that studies generation requests and large-load transmission requests together "in a single, 12-month process," plus three new transmission services (interim network service and firm and non-firm Contract Demand service); it asks for March 16, 2027 as the effective date for the new services and some related changes, and for a 60-day comment period. PJM's transmission owners filed their own section 205 package, docket ER27-520, setting rates, cost allocation and cost recovery for large and co-located loads, including a pro forma Cost Recovery Agreement that requires a minimum contribution toward transmission owners' revenue requirements.
PJM's own summary says it forecasts additions of up to 30 GW of these loads by 2030. A national rule is further off: NERC's first computational-load standards leave minimum ride-through requirements to later work.
Outlook
Comments are likely to be fought over where the numbers live rather than whether loads should ride through. A tariff that defers the envelope to the manuals would leave PJM free to revise it, and to add the 90-day acceleration and exceptions it described in October, without a new FERC filing, the flexibility Choi asks for. Owners of the existing 10 GW, who get no exemption and a compliance deadline no earlier than January 16, 2028, have the most reason to ask FERC to pin the parameters down.
⚠ The Outlook extrapolates from PJM's November 16, 2026 filing in ER27-522 (its tariff text deferring the ride-through envelope to the PJM Manuals, its transitional compliance deadline, and Byoungkon Choi's declaration asking for flexibility to adjust parameters without FERC approval) and from the 90-day acceleration and limited exceptions on PJM's October 28, 2026 Markets and Reliability Committee slide.
Sources
Primary
- PJM Interconnection, L.L.C., Operational Requirements for Large Computational Load and Annual Reporting, Docket No. ER27-522-000 · PJM Interconnection (filed with the Federal Energy Regulatory Commission)
Supporting
- Large Load Show Cause Response (Markets and Reliability Committee, October 28, 2026) · PJM Interconnection
- PJM Interconnection, L.L.C., Proposed Tariff Revisions for Large Loads and Additional Compliance with Co-Location Order and Request for Extended 60-Day Comment Period, Docket No. ER27-531-000 · PJM Interconnection (filed with the Federal Energy Regulatory Commission)
- PJM Transmission Owners, Tariff Revisions for Service to Co-Located Loads and Large Loads, Docket No. ER27-520-000 (submitted by PECO Energy Company) · PJM Transmission Owners (filed with the Federal Energy Regulatory Commission)