PJM asks FERC to study generators and large loads in one 12-month pass
Fast Energization would swap three system impact studies for one and price upgrades for each cycle as a portfolio, but PJM expects its first window in late November 2027 and the first cycle to finish in 2029.
PJM Interconnection wants to study new power plants and the data centers that want their power in the same 12-month study. Its Fast Energization Process, filed at FERC on November 16, 2026 in docket ER27-531, would put generator interconnection requests and transmission service requests for Large Loads (50 MW or more at one site) into a single annual cluster that PJM says "will take half the time of the Cycle process." PJM's Inside Lines announcement puts that as projected timelines falling from two years to one. PJM asks FERC for a 60-day comment period and an order within 120 days.
Fast Energization is PJM's answer to FERC's June 2026 large-load show-cause order and the co-location order issued with it, and PJM asks FERC to close the section 206 side of the show-cause proceeding. Its separate ride-through rules for data centers went in the same day.
Three studies become one
The current cycle runs three System Impact Study phases. Fast Energization swaps them for a screening phase of about four months, two "turns" of analysis that each take less than 60 days and end in a decision point, followed by a single System Impact Study. Each turn gives developers and load customers non-binding estimates of upgrade costs and construction time; at each decision point they choose whether to go on, with Readiness Deposits at risk if they do. Negotiation of service agreements starts when the System Impact Study does.
Speed is bought partly with stricter entry. Developers post Readiness Deposits in full with the application, and a customer seeking service for a Large Load must first sign a Cost Recovery Agreement with its transmission owner. No physical changes to a project or load are allowed after the application; a developer who wants one withdraws and tries again next cycle. Large Loads go on a registry that sets a baseline, and any new or increased service beyond it has to apply and be studied. PJM's 50 MW definition and the registry are the ones FERC accepted in October.
Upgrades are planned for the whole cluster at once. Instead of tying specific network upgrades to specific projects, PJM would identify a portfolio of "Interconnection Reliability Reinforcements" for each cycle, and each developer pays a share of the portfolio. Service agreements would carry schedules of interim injection or withdrawal rights based on the grid as it stands, reassessed every year, so service can begin at a partial level before every upgrade is built.
Applications are a bottleneck of their own: only 5% reach PJM correct and complete on the first try, the filing says, so a 14-week Early Application Engagement period before the deadline has PJM testing applicants' models and giving feedback. PJM also says it has been vetting Tapestry, an AI-powered interconnection platform, and is nearing the point at which it can trust the platform's results without parallel human verification. And it would drop Replacement Generation Interconnection Service, one of the parallel tracks it built alongside the Expedited Interconnection Track, which exists so a new generator can take over a retiring plant's Capacity Interconnection Rights within the one-year transfer limit. With the study itself taking a year, PJM says, the separate track is no longer needed.
PJM's case is that the queue is the one lever it holds. It counts 47 GW of generation with signed agreements, many of those projects not being built or slowed by state permitting and supply chain backlogs, and writes that "The factor that PJM Planning can influence is the interconnection process."
Who pays for the wires
PJM's role is to find the upgrades; the transmission owners hold the filing rights on who pays for them. PJM says it will post the reinforcements, their drivers and their capital costs at the end of each cycle in a searchable format on pjm.com. Inside Lines frames the point for states: transparent access to data-center-driven upgrade costs, "empowering states to bill Large Loads for those costs."
The transmission owners' companion filing, docket ER27-520, makes the bill follow the load. Reinforcement costs would be assigned to the zones containing the Large Loads being studied, recovered through firm transmission rates in the zones where the upgrades sit plus a new Interconnection Reliability Reinforcement Charge assessed by each zone's calculated Large Load impact. For the Large Loads' share, that arrangement runs for 15 years per portfolio, after which remaining costs move to PJM's regional allocation for reliability projects. Generators' proportional share would be billed by PJM as a fee over 15 years and credited back to customers in the zones carrying the costs.
The owners also want their package to stand on its own. They argue its key elements are just and reasonable and should be accepted regardless of how FERC acts on PJM's filing.
A one-year process that finishes in 2029
Fast Energization cannot start until Cycle 01 of PJM's current process is far enough along. PJM would open the first submission window the business day after Cycle 01's Decision Point II, which it expects in late November 2027. Pending Cycle 02 applications would be re-submitted into the new process, with a soft close in early May 2028 and an application deadline in August 2028. "The first Fast Energization Cycle would therefore finish in 2029," the filing says. That puts the first finish line for the one-year process three calendar years after the filing.
Until then, PJM would keep using its Necessary Studies process for load service, as FERC directed in the co-location proceedings. The new transmission services (interim network service and firm and non-firm Contract Demand service) and related changes carry a requested effective date of March 16, 2027, while the Fast Energization provisions are filed with an indefinite effective date. PJM says FERC's full acceptance within 10 months of filing would likely be necessary to implement the process in time for Cycle 02. It plans further stakeholder sessions on at least November 23 and December 15, 2026.
Outlook
The 120-day order PJM requested would land, by our count, on March 16, 2027, the same date it asks for the new transmission services. Its own 10-month mark falls in September 2027, two months before the window it expects to open, so the plan leaves some room for revisions. PJM consents to FERC severing elements of its proposal, and the owners say their cost package can be accepted on its own; if FERC splits the two, the cost rules could be settled before the study process they were written for. A compliance round that runs past the 10-month mark would, on PJM's own reasoning, put the late-November 2027 window at risk.
⚠ The Outlook extrapolates from PJM's ER27-531 filing (its requested 120-day order, its statement that full acceptance within 10 months would likely be needed for Cycle 02, its consent to severance, and its late-November 2027 window estimate) and from the transmission owners' ER27-520 argument that their package can be accepted on its own; the March 16, 2027 date is our arithmetic from November 16, 2026.
Sources
Primary
- PJM Interconnection, L.L.C., Proposed Tariff Revisions for Large Loads and Additional Compliance with Co-Location Order and Request for Extended 60-Day Comment Period, Docket No. ER27-531-000 · PJM Interconnection (filed with the Federal Energy Regulatory Commission)
Supporting
- PJM Transmission Owners, Tariff Revisions for Service to Co-Located Loads and Large Loads, Docket No. ER27-520-000 (submitted by PECO Energy Company) · PJM Transmission Owners (filed with the Federal Energy Regulatory Commission)
- PJM Proposal Would Cut Interconnection Process Time in Half · PJM Interconnection (Inside Lines)
Copies of cited sources are retained where available. If a link no longer resolves, request a copy at contact@theduckcurve.com.