News

Wisconsin forecasts peak demand up about 40% by 2032, mostly data centers

Utilities plan about 14,400 MW of new capacity, led by solar and gas; We Energies, which plans most of the gas, has no 2032 emissions figure in the state's Strategic Energy Assessment.

Oak Creek Power Plant on the Lake Michigan shore at Oak Creek, Wisconsin, seen across the water from Bender Park, with a tall stack venting a white plume beside a shorter stack, with breakwater rocks in the foreground and a jet skier on the water
Michael Barera / Wikimedia Commons (Oak Creek Power Plant, photographed May 25, 2026)

Wisconsin's peak electricity demand is forecast to climb from about 14.2 GW in 2026 to 20 GW in 2032, and about 71% of that increase comes from three data center developments, according to the 2026-2032 Strategic Energy Assessment the Public Service Commission of Wisconsin approved in final form, the commission announced on November 20, 2026. The commission calls it an increase of nearly 5.8 GW, "or over 40 percent, in a six-year period."

The three projects account for approximately 4.12 GW of the growth and sit in the service territories of two utilities, Wisconsin Power and Light (Alliant Energy) and Wisconsin Electric Power Company (We Energies), per the assessment. WPR identifies them as the data center projects in Mount Pleasant, Port Washington and Beaver Dam. Port Washington is the Vantage Data Centers campus whose 1.3 GW of demand forecast through 2030 is the load behind Oracle's Point Beach subscription with We Energies. Utilities told the commission that developers are considering more data centers across the state that are not in the forecast.

The year-by-year table is a touch smaller than the headline: 14,234 MW in 2026 to 19,883 MW in 2032, a rise of 5,649 MW, or just under 40% by our arithmetic. The shape matters more than the rounding. Peak demand fell in 2024 and 2025, edges up 0.77% in 2026 and 3.69% in 2027, then jumps 15.76% in 2028, 8.62% in 2029 and 6.12% in 2030 before nearly flattening at 0.81% in 2031 and 0.16% in 2032. By our arithmetic, 2028 through 2030 carry about 87% of the six-year increase.

What the utilities plan to build

Wisconsin providers reported plans to add about 14,400 MW of nameplate capacity by 2032: 5,835 MW of solar, 5,230 MW of new natural gas capacity or upgrades to existing gas plants, nearly 1,420 MW of wind and about 1,900 MW of storage, about 1,200 MW of which is expected to be paired with existing solar.

We Energies accounts for most of it. The utility reported plans for 4,079 MW of solar, 694 MW of wind, 4,593 MW of natural gas and 1,200 MW of storage, which by our arithmetic is about 88% of the statewide gas figure. Alliant's Wisconsin Power and Light, which WPR says will serve the Beaver Dam project, reported 100 MW of solar, 570 MW of wind, 356 MW of upgraded gas capacity at three existing sites and 110 MW of storage.

Most of the coal fleet is changing fuel rather than closing. Providers plan to retire about 1,100 MW of generation of all fuels between 2025 and 2032, including the last 640 MW or so of coal at Oak Creek, whose full retirement We Energies pushed back in April 2026 to the end of 2027, with gas combustion turbines replacing it. They also plan to retrofit about 3,400 MW of coal units at Elm Road, Columbia, Edgewater and Weston to burn natural gas by 2032, which would leave two coal generating sites in the state. If everything happens as planned, coal falls from 31% of Wisconsin's generation in 2024 to 2% in 2032, while gas rises from 36% to 50%, wind from 11% to 17% and solar from 5% to 16%.

The emissions column with a gap

The utilities that provided 2032 emissions forecasts project a 61% cut in carbon dioxide from 2005 levels, according to the assessment. That group leaves out Wisconsin Electric and Madison Gas and Electric, whose 2032 entries read "N/A." Wisconsin Electric's owned generation is projected at 17.9 million metric tons in 2026, about half of the 34.72 million metric tons for all providers that year by our arithmetic. The utility adding nearly 4.6 GW of gas is one of the two whose 2032 line reads N/A, and the assessment notes that We Energies and Wisconsin Public Service "have announced they are reconsidering their near-term emissions reductions goals."

The commission staff's own modeling lands in a similar place, until emissions count. Its base case, which does not account for emissions goals, "predominately selected natural gas resources." In a scenario built around net zero by 2050, the models picked a significant amount of gas first, "only to be replaced by new nuclear capacity in later years," with "clean flex" resources (dispatchable, zero-carbon, high fuel cost) selected during the transition.

A report, not a plan

The commission will review that build-out one application at a time, deciding generation projects case by case as utilities or developers file them, as commission Chairperson Summer Strand described the process to WPR. Wisconsin has no integrated resource planning process, and the commission "does not prescribe the type of generation resource power providers retire or seek approval to build," per the document. The legislature eliminated the state's previous planning process, the "Advanced Plan," in 1998 and replaced it with the assessment, the commission said in its release, adding that Gov. Tony Evers proposed requiring utilities to file resource plans in previous budgets, provisions the Republican-led legislature removed.

"Under the current legislative framework, the Commission cannot seek a comprehensive, timely, and accurate resource-planning roadmap from the utilities it regulates," Strand said in the release. She was blunter with WPR: "The SEA has no teeth."

The release also concedes that, because of statutory reporting timelines, some parts of the assessment "may be outdated by the time it's published." Utilities submitted their data in November 2025 and updated it in fall 2026; the draft was open for public comment from August 20 to September 28, 2026.

The money and the region are moving too. Forecast load growth, predominantly from data centers, has utilities planning significant investment, one of two trends the assessment says is shaping their revenue requirements, which rose 4.16% a year from 2015 to 2024 for the largest providers. Responses to a 2025 survey of the Organization of MISO States and MISO indicated capacity across the region could be at risk of falling below the local reserve margin requirement in future years; some of MISO's scenarios showed shortfalls and others did not. MISO has meanwhile filed its own large-load rules at FERC, and NERC has asked FERC to approve reliability standards for computational loads such as data centers.

Sources

Primary

Supporting

Copies of cited sources are retained where available. If a link no longer resolves, request a copy at contact@theduckcurve.com.