#miso
NIPSCO's Microsoft contract filing pairs 478 MW of gas with Atlas battery
NIPSCO and NiSource Generation Company (GenCo) asked the Indiana Utility Regulatory Commission on November 25, 2026 (Cause No. 46504) to approve a special contract to serve a Microsoft data center in LaPorte, ramping up to 788 MW by 2031. Testimony names 478 MW of simple-cycle gas units and the 600 MW, 2,400 MWh Atlas battery toll as GenCo's additions for the load; GenCo has committed to separate filings before building generation.

FERC backs MISO's penalty-free queue exit a month after the window closed
FERC on November 20, 2026 accepted MISO's DPP-2022 queue changes, effective October 19: a full M2 refund for projects leaving by Decision Point 2, a 50% (and $15,000/MW) upgrade-cost threshold, up from 35%, for penalty-free exit afterward, and a cap of one Phase III restudy for this and later cycles. MISO's queue now lists 218 DPP-2022 requests in Phase 3, against the 386 MISO counted in September.

Wisconsin forecasts peak demand up about 40% by 2032, mostly data centers
The Public Service Commission of Wisconsin approved its 2026-2032 Strategic Energy Assessment in final form, announcing it on November 20, 2026. It forecasts statewide peak demand rising from about 14.2 GW in 2026 to 20 GW in 2032, with about 71% of the increase tied to three data center developments, and utilities planning about 14,400 MW of new capacity, led by 5,835 MW of solar and 5,230 MW of natural gas.

MISO and NYISO propose $100 and $200/MWh cutoffs for non-firm large loads
MISO and NYISO filed large-load rules at FERC on November 16, 2026, answering its June 18 show-cause orders. MISO's proposed GRITS service would interrupt non-firm load when local prices exceed $100/MWh; NYISO's Non-Firm Withdrawal Service carries a $200/MWh bid cap. MISO proposes a study of about five months, a $250,000 application fee and security equal to upgrade costs; NYISO's study cycle runs about 18 months to two years, and New York's utilities would recover a large load's upgrade costs over 15 years.

Exelon asks FERC for a prompt PJM capacity auction; PJM pushes back
Exelon filed a FERC complaint on November 3, 2026 (EL27-11) asking that PJM replace its three-year-forward capacity auction with a prompt auction two months before delivery, starting with 2030/2031, and sought an order by January 31, 2027. PJM opposed fast-track processing on November 4 and asked until December 21 to answer; Invenergy filed a separate complaint (EL27-12) seeking MISO capacity accreditation for merchant HVDC lines.

Entergy seeks approval for 350 MW of Google-backed batteries in Arkansas
Entergy Arkansas asked the Arkansas Public Service Commission on October 29, 2026 to approve the 250 MW Driver and 100 MW Jones Mill batteries, estimated at $550.6 million and scheduled for service June 1, 2028, saying Google's amended contract will cover their revenue requirement. The commission is separately questioning that contract, with Entergy's answers due November 9.

MISO picks Iowa 765 kV builders; Texas and Illinois approve new lines
MISO on October 21, 2026 picked an Ameren, GridLiance and Dairyland team and ITC to build the last two competitive projects of its 765 kV Tranche 2.1 portfolio, both in Iowa. Texas approved Oncor's 32-mile Deaf Smith County line the same day, ComEd said Illinois approved its underground GRIT lines near O'Hare, and North Plains Connector's GRIP award is final at about $695 million.
NiSource tolls a 600 MW, 2,400 MWh battery alongside Microsoft deal
NiSource's GenCo signed a tolling agreement on October 15, 2026 for a 600 MW / 2,400 MWh stand-alone MISO battery that AGP Group will build and own, with payments expected to total about $2.2 billion over roughly 20.5 years. A day later NiSource announced a 20-year agreement to serve Microsoft's northwest Indiana campus from 2028 that grows GenCo's pool by about 1,100 MW; the battery is the only resource it has named.