NIPSCO's Microsoft contract filing pairs 478 MW of gas with Atlas battery
NIPSCO asked the IURC on November 25, 2026 to approve its Microsoft contract and GenCo supply deal; GenCo has committed to a separate filing for the gas units, and existing customers would get about $349 million in credits over 20 years.
Northern Indiana Public Service Company (NIPSCO) has asked Indiana regulators to approve its contract to serve a Microsoft data center in LaPorte, and the filing names the power behind it: 478 MW of simple-cycle gas generation alongside the 600 MW Atlas battery. NIPSCO and its generation affiliate, NiSource Generation Company (GenCo), filed a joint petition in Indiana Utility Regulatory Commission (IURC) Cause No. 46504 on November 25, 2026. It seeks approval of the October 14 special contract, under which Microsoft commits to demand ramping up to 788 MW by 2031, and of a November 20 power purchase agreement through which GenCo supplies NIPSCO.
The gas is the part October's announcement left out. NiSource announced the agreement on October 16 with a pool growing by approximately 1,100 MW and one named resource, the battery, as our first report noted. Two 239 MW F-frame combustion turbines for the pool surfaced in NiSource's third-quarter 10-Q, and the Microsoft case now lists gas and battery together: GenCo is adding the Atlas battery tolling agreement, 600 MW and 2,400 MWh, and simple-cycle gas units of 478 MW, per testimony from Karl Stanley, NiSource's vice president of supply and optimization. By our arithmetic, two 239 MW turbines make the 478 MW, and gas plus battery come to 1,078 MW, which fits the release's rounded figure.
Contracts now, plants later
The turbines are meant to come back to Indiana regulators on their own. This case asks the commission to approve the contracts, not the plants: GenCo "is not seeking approval of the generation resources" in this proceeding, Stanley testified, and reaffirmed its commitment to make separate filings before building them. The 10-Q says the turbines will be subject to IURC approval and that NiSource believes they should reach commercial operation by the end of 2029, built under an engineering contract with Quanta whose target price, scope and schedule are subject to change.
Stanley says the battery and the gas units "will cover the first tranches" of Microsoft's load, including accreditation and planning reserve margin. The table showing that ramp, year by year, is redacted, as are the dollar estimates for the transmission and generation investment in the testimony of NIPSCO vice president Erin Whitehead. She testified that those costs will be fully recovered from Microsoft.
Every asset Stanley names in the pool so far is a battery. He lists its current assets as the Nebo energy storage agreement (75 MW, 300 MWh), the Tipton storage agreement (167 MW, 668 MWh), part of GenCo's Mitchell battery project (100 MW, 400 MWh) and market purchases, which he does not size. In the Amazon case, NIPSCO president Vincent Parisi testified that the pool was made up of batteries and capacity from a thermal resource in Indiana, under a 500 MW capacity confirmation running from 2028 through 2040. It also has to cover 400 MW of extra capacity for Amazon, which NIPSCO testified it would serve from the pool under the Amazon contract amendments the IURC approved on November 18. In that case the NIPSCO Industrial Group raised concerns about potential overbuilding of the pool, and the commission declined to impose its restrictions, pointing to its finding in the Alphabet-subsidiary case that such concerns were unfounded. Stanley now calls it "a practical certainty" that GenCo will at times have more capacity than it needs to meet its obligations to NIPSCO, because capacity is procured in tranches; he says GenCo would likely offer the surplus to NIPSCO under an approved capacity transfer agreement or into MISO's capacity auction.
The petitioners proposed a schedule they say is still under discussion with the Office of Utility Consumer Counselor and other stakeholders: intervenor testimony by February 1, 2027, an evidentiary hearing on March 8, 2027, and an order on April 21, 2027. No order had been issued in the cause as of November 30.
A new lane into MISO
The gas units are taking a newer route to the grid. MISO's Expedited Resource Adequacy Study program will sunset at the end of 2027 with all its slots taken, Stanley testified, so the turbines will use MISO's Large Load Addition Resource Study, which studies a load of at least 200 MW together with new generation in the same local resource zone, as our interconnection queue tracker records.
MISO filed the program at FERC, and Stanley expects approval on December 2, 2026, with the program operating by mid-January 2027 and applications subject to a 120-day review. Assuming MISO accepts GenCo's application in that first tranche, he expects the generator interconnection agreement by April or May 2027. The battery's interconnection agreement is the developer's to sign under the toll.
If that first-tranche assumption holds, the turbines would go through a process built for this pairing: a data center and the new generation meant to serve it, studied together.
What existing customers get
Microsoft's payments include an existing system charge that NIPSCO would pass back to its other customers as bill credits. Whitehead puts those credits at about $349 million over the 20-year contract term, or $16.80 a year for each residential customer from 2032, once the load has finished ramping. That is $1.40 a month, by our arithmetic. NIPSCO and GenCo shareholders would add up to $7.4 million for northern Indiana communities through a customer fund.
The headline number is bigger. Counting the two earlier contracts, approved in the Amazon and Alphabet-subsidiary cases, Whitehead puts expected benefits at $1.75 billion over 20 years, about $140 per residential customer a year from 2032. That is the figure NiSource's October release led with; the Microsoft contract's own piece is the $16.80.
Microsoft can terminate at specified milestones but still owes defined costs if it does, and it must provide a guaranty, or a letter of credit if it loses its investment-grade status, per testimony from Alan Schroeder of NiSource Corporate Services. The power purchase agreement matches the contract's term, so NIPSCO has no continuing payments to GenCo once Microsoft's contract ends, and gives NIPSCO termination rights substantially similar to Microsoft's. Once the IURC has approved it, the agreement is to be filed at FERC.
Sources
Primary
- Verified Joint Petition of NIPSCO and NiSource Generation Company LLC, Cause No. 46504 (Microsoft special contract) · Indiana Utility Regulatory Commission (filed by NIPSCO and GenCo)
Supporting
- NiSource announces long-term agreement with Microsoft expected to increase customer savings and support Indiana's economic growth · NiSource
- NiSource Inc. Form 10-Q for the quarter ended September 30, 2026 · NiSource Inc. (SEC EDGAR)
- IURC Order, Cause No. 46442 (Amazon special contract amendments and NIPSCO-GenCo PPA amendment), approved November 18, 2026 · Indiana Utility Regulatory Commission
- Verified Direct Testimony of Erin E. Whitehead (Joint Petitioners' Exhibit 1, redacted), Cause No. 46504 · Indiana Utility Regulatory Commission (filed by NIPSCO and GenCo)
- Verified Direct Testimony of Alan Schroeder (Joint Petitioners' Exhibit 2, redacted), Cause No. 46504 · Indiana Utility Regulatory Commission (filed by NIPSCO and GenCo)
- Verified Direct Testimony of Karl E. Stanley (Joint Petitioners' Exhibit 4, redacted), Cause No. 46504 · Indiana Utility Regulatory Commission (filed by NIPSCO and GenCo)
- FERC deficiency letter to MISO on the Large Load Addition Resource Study filing, Docket No. ER27-25-000 · Federal Energy Regulatory Commission (Office of Energy Market Regulation)
Copies of cited sources are retained where available. If a link no longer resolves, request a copy at contact@theduckcurve.com.