CIP closes about $990M of debt for Mexico's La Alegría solar and battery

La Alegría pairs 864 MWdc of solar with a 313 MW / 1,501 MWh battery in Campeche; with its sibling La Esperanza, CIP puts the cluster's investment at about $1.5 billion.

Aerial view of long rows of solar panels on pale sandy ground, cut by dirt access roads, with an equipment skid on a cleared pad among the rows.
Copenhagen Infrastructure Partners (CIP's Greasewood solar farm in Pecos County, Texas, not La Alegría)

Copenhagen Infrastructure Partners (CIP) has reached financial close on La Alegría Solar in Campeche, on Mexico's Yucatán Peninsula: 864 MWdc of solar panels paired with a 313 MW / 1,501 MWh battery, financed with approximately $990 million of debt from five banks, the Danish fund manager said on November 30, 2026. Construction is underway, and CIP expects commercial operation in 2028.

The lenders are BNP Paribas, JPMorgan Chase Bank, Natixis CIB, Santander and Scotiabank, the same five that financed La Esperanza Solar, CIP's other Campeche project, when it closed on August 6, 2026. Equity comes from CIP's Growth Markets Fund II, with an expected co-investment from Mexican retirement fund administrator Profuturo. Each project is backed by a long-term power purchase agreement with CFE Calificados, the large-client commercial arm of state utility Comisión Federal de Electricidad (CFE), and both are recognised as priority projects by the Ministry of Energy (SENER) under Mexico's binding planning framework, per CIP.

CIP calls La Alegría the largest battery energy storage development in Mexico. In August, the same company described La Esperanza's battery as "one of the largest in Mexico." Between August and November, the superlative moved next door.

Two plants, one cluster

Together, CIP says, the two projects will be "Mexico's largest solar and battery storage cluster", with approximately 1.3 GWdc of solar and 463 MW / 2,315 MWh of storage. The solar and battery megawatts add up: 420 MWdc plus 864 MWdc, and 150 MW plus 313 MW.

The megawatt-hours do not. CIP's 2,315 MWh cluster figure is 64 MWh more than its two project releases add up to, by our arithmetic: La Esperanza's August release sized its battery at "150 MW/5-hour (750 MWh)", and 750 plus 1,501 is 2,251 MWh. The 2,315 MWh total is exactly 463 MW times five hours, while La Alegría's own battery works out to about 4.8 hours of storage at full output. Neither release reconciles the two.

The money has a similar shape. La Esperanza closed on approximately $510 million of debt; add La Alegría's approximately $990 million and the debt alone comes to about $1.5 billion by our arithmetic, which is also the figure CIP gives for the two projects' total investment. Neither release puts a dollar figure on the equity.

The battery rule

Under SENER's second call for priority generation permits, a new renewable plant has to come with a battery. The call, aligned with the binding plan and published in the Diario Oficial de la Federación on May 11, 2026, asks for a storage system sized at "at least 30%" of the plant's capacity, with a duration of at least three hours, that meets the call's technical and operating requirements for battery storage, and for commercial operation between 2027 and the first half of 2030. The second call followed a first one, published on October 17, 2025.

La Alegría clears that bar with room to spare on duration: about 4.8 hours against three. On size, its 313 MW of batteries is about 36% of the 864 MWdc solar rating, by our arithmetic; the rule measures against the plant's capacity, and CIP gives only the panels' DC figure. The release does not say which call, if either, the project's permits came through, so the rule is a yardstick here, not a compliance finding. The distinction between the battery's power and its energy, the two numbers in every storage headline, is the one in kW vs kWh.

CIP pitches the cluster as a grid asset for the peninsula: the projects will "strengthen the reliability, resilience and flexibility of the electricity system in the Yucatán Peninsula," the company said, and in August it described the region as one "where rising electricity demand has increased the need for new power generation and storage capacity."

The fund manager also signalled that two Campeche plants are not the end of it. "Mexico remains a priority market for CIP," said Ole Kjems Sørensen, a partner at the firm. "We see significant potential for further investment, driven by the country's growing energy needs, market fundamentals and opportunities to develop critical infrastructure."