Roundup

Taishan 3 pours first concrete, BWXT trials AP1000 parts, UK presses reform

Westinghouse's purchase orders cover demonstration pieces for steam generators and reactor vessel internals, and UK ministers gave the few nuclear organisations yet to answer a March letter until December 14.

One reactor started construction in China in the week to November 25, 2026, a supplier in Ontario and Pennsylvania took orders for practice parts of another design, and three UK ministers wrote to their nuclear industry about the pace of its rule reform.

Taishan 3 pours its first nuclear-island concrete

Taishan Unit 3 in Guangdong province had the first concrete of its reactor main plant poured on November 25, 2026, which marks the start of full-scale construction, CGN Power told the Hong Kong stock exchange. The unit is an HPR1000, the design also called Hualong One, with an installed capacity of 1,200 MW.

The pour opens the second of three phases at a site planned for six million-kilowatt-class units; the two Phase I units were complete and in operation as of September 7, 2019, Global Times reported, citing Science and Technology Daily. The nuclear-island foundation needs about 8,823 cubic meters of concrete, in a pour expected to take 55 hours of continuous work, and state broadcaster CCTV expects the unit to generate more than 9 billion kWh a year.

China's National Nuclear Safety Administration checked the unit's readiness for the pour from October 13 to 16. Its inspection report, sent to the operator on October 21, logged 28 inspection records and four corrective requirements, which the operator was to complete before the first concrete.

Taishan 3 was the second full-construction start CGN Power announced in November: Cangnan Unit 4, a 1,215 MW HPR1000, poured its first concrete on November 10. With Haiyang 5 on October 31, that is at least three Chinese reactor foundations started in under four weeks.

BWXT gets demonstration orders for AP1000 parts

Westinghouse and BWXT Canada have agreed to qualify BWXT Canada to manufacture key AP1000 components to Westinghouse specifications, BWXT said on November 23, 2026. The qualification runs through Westinghouse purchase orders for demonstration pieces: for steam generators at BWXT's plant in Cambridge, Ontario, and for reactor vessel internals at its plant in York, Pennsylvania.

The orders are for the qualification, and production orders remain to be won. The release names no AP1000 project in either country, pointing instead to "AP1000 projects globally" and the 14 units it counts as under construction worldwide, and its own risk section lists "whether and when prospective projects proceed, and whether BWXT Canada receives additional orders for commercial production."

The Cambridge plant has just grown. BWXT said on November 12 that it had completed an expansion there of approximately C$80 million, adding 55,000 square feet and enlarging what it calls the world's largest commercial nuclear clean room by 40%. Its current projects include 48 new steam generators for the Pickering refurbishment and the reactor pressure vessel for the Darlington SMR.

Westinghouse's Polish suppliers are on a similar footing. In October it placed conditional purchase orders with four Polish companies for modules for Poland's first AP1000, with the full scope to follow NQA-1 certification and pre-production qualification mockups.

UK ministers chase nuclear regulatory reform

Three UK ministers wrote to nuclear chief executives and dutyholders on November 23, 2026, a year after the Nuclear Regulatory Review was published, to reaffirm the government's commitment to implementing it, in a joint letter published on GOV.UK on November 24. Exchequer Secretary Dan Tomlinson, Energy Minister Michael Shanks and Defence Readiness and Industry Minister Luke Pollard say the government is working to implement its response to the review by the end of 2027, through guidance, policy and regulatory changes and legislation including the Nuclear Regulation Bill.

Their progress list includes the lead regulator model, the Office for Nuclear Regulation's completed consultation on revised Safety Assessment Principles, a single point of contact for nuclear export licensing, and an operational DESNZ Post Consent Unit for development consents. A review of the Semi-Urban Population Density Criterion is under way, and the government will consult on updates to the national policy statement for nuclear generation, EN-7.

The pointed paragraph is about who has not answered. The previous Chancellor wrote to leaders across the sector in March 2026 calling for substantial change; the ministers report overwhelming support in the responses, but a "small number of prominent organisations" have yet to reply, and they are asked to do so by December 14. The ministers have tasked their teams and the Nuclear Regulatory Implementation Panel to chase responses and interrogate the plans companies shared.