Roundup

Kashiwazaki-Kariwa 7 work slips; Tianwan 8 gets its fuel; Kaiga 1 restarts

TEPCO's contractor says unit 7's antiterrorism facility needs more than a year of schedule revision, Rosatom puts Tianwan 8's startup in the first quarter of 2027, and the NRC opened scoping for General Matter's Paducah plant.

Four nuclear schedules moved between November 22 and 27, 2026, and only one went backward. Tokyo Electric Power cannot yet say when Kashiwazaki-Kariwa unit 7 will restart; Tianwan 8 in China finished hot tests and received its fuel; India's Kaiga 1 went critical again after a 600-day refurbishment; and the NRC opened environmental scoping for General Matter's planned enrichment plant in Kentucky.

TEPCO cannot yet say when Kashiwazaki-Kariwa 7 restarts

Tokyo Electric Power Company Holdings (TEPCO) is revising the construction schedule for unit 7's antiterrorism facility at Kashiwazaki-Kariwa and cannot yet give the reactor a restart date, plant head Takeyuki Inagaki said at his monthly press conference on November 26, 2026. In February 2025 TEPCO had given around August 2029 for the facility's completion, with the schedule still under review. In early November the contractor building its main structures reported that, given its record so far, site conditions and the workers it can secure, the parallel work it had planned could not be done and that the expected gains from experience were not coming, and formally advised that the schedule needed more than a year of revision, according to Inagaki's prepared remarks. Separately, part of a main structure of the unit 7 facility has an uneven concrete finish from a construction problem; TEPCO is working out how to repair it and expects folding that into the schedule to take time.

The facility decides whether a reactor may run. Unit 7's was originally due by October 2025, and after TEPCO moved it to August 2029 the company brought unit 6 back first, The Japan Times reports; unit 6 restarted in January and cannot keep operating unless its own facility is finished by April 2031. Inagaki said the first aim now is unit 6's April 2031 deadline. The February 2025 schedule had pencilled unit 6's facility in for September 2031, five months after it. Some coverage reported April 2031 as a new target for unit 7; Inagaki's remarks attach the date to unit 6.

On November 20, when the delay first surfaced in the press, TEPCO said the reports were not its announcement and that it would consider revising the construction schedule as needed. All construction at the plant is now stopped until its safety is confirmed, Inagaki said, after a contractor's worker died on November 22, trapped under glass at the site of a new office building.

Tianwan 8 finishes hot tests and receives its fuel

Tianwan unit 8, a VVER-1200 in Jiangsu province, completed hot functional tests on November 25, 2026, according to China National Nuclear Power's statement as carried by China Energy News. The tests verified the primary and secondary circuit systems through heat-up, hot and cool-down conditions; post-test disassembly and in-service inspection come next as preparation for fuel loading. Rosatom says the tests ran above 260 °C and covered overpressure protection for both circuits, the main circulation pumps and the power supply systems, and puts the unit's physical startup in the first quarter of 2027. Alexei Bannik of Rosatom's Atomstroyexport said the regulator's permission to load fuel will follow a review of the circuits' main and auxiliary equipment.

The fuel is already supplied. Rosatom says it has delivered unit 8's first core load plus reserve fuel assemblies, made at the Novosibirsk Chemical Concentrates Plant. TVEL's Anton Ivanov said three VVER-1200 cores have been delivered since late 2025, for Tianwan 7 and 8 and Xudapu 3, and Xudapu 4's first load is due to be made and accepted by the customer by the end of 2026. Once unit 8 is in service, Rosatom says, Tianwan will be the world's largest nuclear power plant, and it will enter the world's ten largest power stations, behind only the biggest hydro plants of China and South America. Six of the site's eight units are Russian designs.

China National Nuclear Power puts the finished eight-unit site above 9 GW and 70 TWh a year, and expects unit 7, which reached the grid on October 8, to enter commercial operation within 2026.

Kaiga 1 is critical again after 600 days

Kaiga unit 1, a 220 MWe pressurised heavy water reactor in Karnataka, reached criticality early on November 22, 2026, NPCIL said, 600 days after it shut down on April 1, 2025 for major refurbishment of its coolant channels and feeders. NPCIL says the unit "has set a new fleet-wide benchmark as the first NPCIL reactor to reach criticality in such a short span." The work included defuelling the reactor, draining its heavy water and replacing the coolant channels, then reloading, leak testing, heavy-water filling, hydrotesting and hot conditioning before the approach to criticality, World Nuclear News reports.

The reactor went critical at around 1:45 am after clearance from the Atomic Energy Regulatory Board, the Deccan Herald reports, and NPCIL officials told the paper it will be connected to the southern grid after mandatory tests, with its power then raised gradually. The unit entered commercial operation on November 16, 2000, per NPCIL. Three days before its return, the same regulator cleared a new 700 MWe heavy water unit, RAPP-8, for its first approach to criticality.

NRC opens scoping for General Matter's Paducah enrichment plant

The NRC will prepare an environmental impact statement on General Matter's application to build and operate a uranium enrichment plant in McCracken County, Kentucky, and is taking comments on its scope until December 28, 2026, under a notice published November 27. There will be no public scoping meeting; comments go in writing, through docket NRC-2026-5446 on regulations.gov or by mail. The plant would sit on about 107 acres leased from the Department of Energy's Paducah Site, which includes the former Paducah Gaseous Diffusion Plant, and the requested license would cover building it and then running it for up to 40 years.

The NRC issued its acceptance letter on October 29, and that letter estimated an environmental impact statement for public comment by August 2027.