Advanced reactors in the US: SMRs and microreactors

The standing record of US small modular reactors and microreactors: what has gone critical under DOE, what the NRC has permitted, and the rules, military buyers and fuel supply that decide what comes next.

Where things stand

As of November 19, 2026, three advanced reactor plants have NRC construction permits issued this year, and a summer's worth of test reactors went critical under DOE authority. None yet holds an NRC operating license.

DOE moved first. Its August 6 count put five advanced reactors critical under its authorization between June 4 and August 5: Antares Nuclear's Mark-0, Deployable Energy's Unity and Aalo Atomics' Critical Test Reactor at Idaho National Laboratory, Valar Atomics' Ward 250 in Utah and Oklo's Groves test reactor in Texas. Westinghouse's eVinci completed zero-power criticality testing in Nevada on August 24. Next up: INL's MARVEL, whose dry criticality INL anticipates in December; Last Energy's Texas A&M-RELLIS pilot, which the company says cleared its final DOE safety analysis; and Radiant's Kaleidos, past its third-quarter full-power target and, Radiant says, in DOE's readiness review.

The NRC track is slower and bigger. TerraPower's 345 MWe Kemmerer Unit 1 in Wyoming got its permit decision March 9. TVA's 300 MWe BWRX-300 SMR at Clinch River, Tennessee followed September 28. Long Mott Energy's four-module, 320 MWe Xe-100 plant at Dow's Seadrift site in Texas got the third on November 9 and awaits Dow's final decision to build. Under review, among others: part one of a phased application for two SMR-300 units at Palisades, Michigan, and the University of Illinois' KRONOS research microreactor. Awaiting acceptance: Palisades' part two and first parts for Blue Energy's BWRX-300 in Victoria, Texas and Last Energy's PWR-20 in Caldwell County, Texas. Kairos Power holds permits for its Hermes and Hermes 2 test facilities, Abilene Christian University for Natura Resources' MSR-1, and NuScale's 462 MWe US460 design won standard design approval in May 2025.

On October 22 the NRC finalized its rule letting commercial applicants cite information from reactors DOE or the Department of War authorized and tested, and on October 30 one designed to finish most contested hearings in about a year. Its tracker puts two others past Executive Order 14300's November 23, 2026 final-rule deadline: a new Part 57 for "rapid licensing" of microreactors and reactors with comparable risk profiles, and a broad reactor package whose comments closed November 9. The technology-inclusive Part 53 took effect April 29.

The first customer wears a uniform. The Army's Janus Program picked five vendors on August 26 for vendor-owned microreactors at five bases, for up to a combined $2.2 billion over fiscal 2027 to 2031. The Navy picked Radiant for the Crane, Indiana unit the Pentagon plans by September 2028, and Executive Order 14299 wants an Army-regulated reactor operating on a base by September 30, 2028.

Fuel gates all of it. DOE says HALEU "is not currently available from domestic suppliers." Centrus expects its first new enrichment capacity by 2029, when Oklo's HALEU deliveries are scheduled to begin, and Radiant's before the end of the decade; Antares has TRISO fuel agreements with Standard Nuclear and BWXT.

Timeline

202420252026Nov 19, 2026Nov 18, 2026Nov 17, 2026Nov 12, 2026Nov 12, 2026Nov 12, 2026Nov 11, 2026Nov 10, 2026Nov 9, 2026Nov 9, 2026Nov 6, 2026Oct 30, 2026Oct 30, 2026Oct 30, 2026Oct 29, 2026Oct 29, 2026Oct 27, 2026Oct 26, 2026Oct 23, 2026Oct 22, 2026Oct 20, 2026Oct 20, 2026Oct 20, 2026Oct 19, 2026Oct 19, 2026Oct 19, 2026Oct 16, 2026Oct 14, 2026Oct 13, 2026Oct 13, 2026Oct 8, 2026Oct 7, 2026Oct 7, 2026Oct 6, 2026Oct 1, 2026Sep 30, 2026Sep 28, 2026Sep 24, 2026Sep 21, 2026Sep 18, 2026Sep 15, 2026Sep 11, 2026Sep 9, 2026Sep 9, 2026Sep 8, 2026Sep 3, 2026Sep 3, 2026Aug 28, 2026Aug 27, 2026Aug 26, 2026Aug 24, 2026Aug 24, 2026Aug 20, 2026Aug 13, 2026Aug 6, 2026Aug 5, 2026Jul 23, 2026Jul 4, 2026Jul 1, 2026Jun 30, 2026Jun 18, 2026Jun 4, 2026May 1, 2026Apr 2, 2026Mar 31, 2026Mar 30, 2026Mar 9, 2026Dec 31, 2025Dec 2, 2025Aug 12, 2025May 23, 2025Mar 31, 2025Nov 21, 2024Sep 16, 2024Dec 14, 2023
75 dated events, 2023 to 2026. Jump to 2026, 2025, 2024, 2023.
  1. 2026
  2. Radiant said its first commercial deliveries begin in 2028 and that the NRC targets January 2027 for its fuel license; the NRC's schedule says by December 18 (Radiant; coverage).

  3. New York's Department of Public Service staff recommended a 5 GW target for new advanced nuclear, procured by competitive open-book negotiation, not a request for proposals (white paper); NYSERDA and the department issued a 30-point master plan (plan; coverage).

  4. The NRC cut the Advisory Committee on Reactor Safeguards to the minimum its statutory duties require by direct final rule, effective February 1, 2027 absent significant adverse comments by December 17 (rule).

  5. The New York Power Authority qualified 10 of 21 respondents as potential partners for at least 1 GW of advanced nuclear upstate, four for SMRs only (NYPA; coverage).

  6. Oklo said it signed definitive HALEU contracts with Centrus for enough fuel for up to five Aurora powerhouses for multiple years, with deliveries from Centrus's Ohio plant scheduled to begin in 2029 (Oklo; coverage).

  7. Standard Nuclear said it sent DOE its new Oak Ridge TRISO plant's final safety analysis November 6, Idaho's to follow, and targets authorization for both in February 2027; August's release said fourth-quarter 2026 (8-K; August; coverage).

  8. Oklo said DOE cleared its Groves-1 isotope test reactor in Texas for unrestricted operations (Oklo).

  9. Ontario's OPG said its first Darlington BWRX-300, the design TVA plans at Clinch River, is no longer expected to meet its October 2030 commercial operation target or C$7.7 billion estimate, which includes systems and services common to all its planned SMRs, citing GE Vernova Hitachi's ongoing engineering; it expects its assessment substantially complete by mid-2027 (OPG; coverage).

  10. The NRC announced Long Mott's construction permit for four Xe-100 reactors, which it calls the first for a high-temperature gas-cooled reactor in nearly 60 years (NRC). Dow said the permit is not a final decision to build (Dow; coverage).

  11. NEI said the reactor package's reporting and recordkeeping cuts fall "far short" of what Executive Order 14300 requires (NEI); nine state attorneys general urged withdrawing its "problematic portions" (states; coverage).

  12. The Commission denied San Antonio Bay Estuarine Waterkeeper's petition for review of the licensing board rulings that rejected or dismissed all its Long Mott contentions (CLI-26-15).

  13. NRC staff issued Long Mott's final safety evaluation, recommending the Commission make the safety findings for a construction permit, with two proposed conditions on foundation geology and flood protection (NRC; letter; coverage).

  14. The NRC finalized a rule overhauling contested licensing hearings: three tracks, with schedules designed to finish most cases in about a year (NRC; rule; coverage).

  15. The NRC had dropped its October 31 target for the Palisades draft EIS; final safety evaluation and EIS targets stay March 31, 2027 (NRC).

  16. The NRC accepted General Matter's Paducah, Kentucky uranium enrichment plant application as of October 28, estimating completion in April 2028 (NRC); the company intends a 2027 amendment to produce HALEU (release; coverage).

  17. Radiant said DOE approved its Kaleidos documented safety analysis, covering initial criticality and operation at power; a DOE readiness review comes before fueling, with no date for either (Radiant; coverage).

  18. Antares signed a TRISO fuel fabrication agreement with BWXT, its second after Standard Nuclear's: HALEU fuel from Lynchburg, Virginia, starting with one metric ton of uranium (Antares; BWXT; coverage).

  19. Elementl signed a preliminary agreement for an up-to-$750 million partnership, intended to partly fund pre-construction work on up to three projects, with a DS Investment Partners-led consortium, Samsung C&T a potential strategic investor (Elementl; coverage).

  20. Antares said DOE approved the Nuclear Safety Design Agreement for Mark-1, its first electricity-producing reactor, designed to run at full electrical power at INL in 2027 (Antares; coverage).

  21. The NRC finalized 10 CFR 50.43(f) and a revised 53.440(a)(1), letting commercial applicants cite relevant information from a DOE- or War-authorized reactor that "has been tested and has demonstrated the ability to function safely"; published October 26, it takes effect November 25 (rule). The NRC calls it the first major change to its reactor regulations finalized under Executive Order 14300 (NRC; coverage).

  22. Last Energy filed part one of a two-part phased construction permit application for its PWR-20 in Caldwell County, Texas, with a limited work authorization request; the NRC noticed receipt November 5 (notice; coverage).

  23. The Navy selected Radiant for a prototype Kaleidos microreactor power plant at Crane, procured through Janus and, the Navy says, "accounted for within" the Army's August 26 award (Navy; Radiant; coverage).

  24. Deep Fission signed what it calls a binding 25-year master energy purchase agreement with the Great Plains Development Authority for a commercial project at its Parsons, Kansas pilot site: an initial phase anticipated at 150 MW, targeting commercial operation September 30, 2028, with "no minimum purchase obligation" for the authority (release).

  25. Alaska's state-backed AIDEA agreed to put $25 million into microreactor developer NuCube Energy, NuCube said, counting toward the $75 million minimum cash condition for closing its merger with SPAC Launch Two (NuCube); the two extended the outside date that day to January 7, 2027 (8-K; coverage).

  26. AtkinsRéalis, the State of Indiana and Hoosier Energy signed an MOU to explore up to eight CANDU reactors, up to 6.0 GW, naming no site, cost or schedule (AtkinsRéalis). The NRC lists the 700 MWe-class Enhanced CANDU 6 in pre-application aimed at design certification (NRC), though AtkinsRéalis's June 26 engagement plan points to a construction permit application once a customer is identified (plan; coverage).

  27. AEP and X-energy agreed to study a 960 MW plant of twelve 80 MW Xe-100 units, evaluating the former Breed coal plant site in Sullivan County, Indiana; Amazon is funding development and intends to buy the power long term (AEP). X-energy and Amazon call it their second project, after Washington's Cascade facility, toward more than 5 GW of new US nuclear by 2039 (X-energy; Amazon; coverage).

  28. The ACRS said its review "supports issuance of the construction permit" for Long Mott, listing fuel performance and mechanistic source term among work still needed for an operating license (ACRS).

  29. The Molten Chloride Reactor Experiment is expected to reach first criticality as early as 2027 after DOE approved cost-shared Advanced Reactor Demonstration Program funding for an accelerated final stage, Southern said (Southern). DOE said on December 3, 2025 it anticipated a roughly six-month run in 2028 in INL's LOTUS test bed (DOE; coverage).

  30. Oklo said it will advance Groves 2 Forge, an isotope production and processing pilot facility focusing first on lutetium-177, as part of DOE's Nuclear Energy Launch Pad (Oklo; coverage).

  31. Bluecore Energy said it bought uranium hexafluoride enriched to 4.95% uranium-235 from WMC, held at a US fuel facility outside California (Bluecore). The NRC describes a 45 MWt pressurized water reactor on a barge, with the Port of Long Beach, California as its reference operating location (NRC; coverage).

  32. Terrestrial Energy said it submitted a Thermal and Electric Facility topical report asking the NRC to confirm that building the IMSR plant's generator, turbine and steam supply facility "is not nuclear construction under 10 CFR 50.10(a)(1)"; if approved, it says, the facility could be built and operated ahead of nuclear licensing (Terrestrial; coverage).

  33. Last Energy said DOE approved the Documented Safety Analysis for its pilot reactor at Texas A&M-RELLIS, moving it into DOE's readiness review, the final step before startup authorization (release; coverage).

  34. The ACRS was scheduled to hear Long Mott's construction permit review (notice).

  35. INL said DOE's Idaho Operations Office approved MARVEL's final documented safety analysis, authorizing a dry, near-zero-power criticality configuration, and that criticality is "anticipated to occur in December" (INL; coverage).

  36. The NRC began four weekly notices of receipt for part one of Holtec's phased application for Pioneer Units 1 and 2 at Palisades (notice).

  37. Holtec's Palisades SMR filed part two of its phased application, a preliminary safety analysis report; the NRC noticed receipt November 10 (notice).

  38. The NRC issued Construction Permit CPAR-2 to TVA for Clinch River Nuclear Unit 1, a BWRX-300, setting construction completion between October 1, 2031 and September 30, 2032 (permit). Its September 29 release says the permit clears the way for "the nation's first commercial small modular reactor" (NRC; coverage).

  39. The NRC's proposed reactor licensing, decommissioning and operational oversight rule was published, with comments due November 9 (rule; coverage).

  40. Kairos Power said Samsung C&T agreed to provide up to $100 million in direct investment and in-kind engineering, subject to regulatory approvals, for the Hermes 2 demonstration plant in Oak Ridge (Kairos; coverage).

  41. Natura Resources received FLiBE salt from Oak Ridge National Laboratory, via INL, for the MSR-1 being built at Abilene Christian University (Natura; coverage).

  42. Blue Energy filed part one of a phased construction permit application, with a limited work authorization request and two exemption requests, for one BWRX-300 in Victoria, Texas; the NRC noticed receipt October 8 (notice). The NRC lists a 10 CFR 50.10(a)(1) exemption request under acceptance review and an approved construction-resequencing topical report (NRC).

  43. The NRC announced a proposed "broad overhaul" of its reactor licensing and oversight rules under Executive Order 14300 (NRC; coverage).

  44. The Department of War announced a commercially owned and operated Micro Modular Reactor at Naval Weapons Station Crane, Indiana, no later than September 2028, executed through the Army's Janus Program (release; coverage).

  45. Centrus announced a definitive multi-year contract to supply HALEU for multiple Radiant Kaleidos microreactors, with deliveries to begin before the end of the decade (8-K; coverage).

  46. A University of Colorado Boulder preprint argued that operating and fuel costs, not investment costs, make SMRs at advertised costs uneconomical in US power markets (arXiv; coverage).

  47. Westinghouse's eVinci test reached zero-power criticality at 663°C at the National Criticality Experiments Research Center in Nevada (Westinghouse; coverage).

  48. Deep Fission lowered a 20-foot, non-nuclear prototype reactor canister to 100 feet in a 34-inch borehole and retrieved it (release; coverage).

  49. The NRC granted Palisades SMR, LLC an exemption allowing construction of permanent support-of-excavation walls for Pioneer Units 1 and 2 before a limited work authorization (notice).

  50. Standard Nuclear announced a binding agreement to supply Antares a minimum of one and up to eight metric tons of uranium in TRISO fuel through 2035 (8-K; coverage).

  51. The Army's Janus Program selected Antares, BWXT, General Atomics, Radiant and Westinghouse for microreactors at five bases, up to a combined $2.2 billion over fiscal 2027 to 2031 (Army; coverage).

  52. DOE's National Reactor Innovation Center announced 13 new Nuclear Energy Launch Pad projects from 12 developers, including Antares, Valar, Oklo and Deployable Energy (INL).

  53. Westinghouse completed zero-power criticality testing of its eVinci design in Nevada (Westinghouse; coverage).

  54. The NRC noticed the mandatory (uncontested) hearing on Long Mott's permit application for September 22 in Port Lavaca, Texas (notice).

  55. Radiant said its 1 MWe Kaleidos had left El Segundo, California for INL's DOME test bed, with a minimum 150-hour continuous full-power run targeted for the third quarter of 2026 (Radiant).

  56. Deep Fission said DOE approved the Nuclear Safety Design Agreement for its Gravity reactor under the Reactor Pilot Program (release).

  57. Oklo's Groves Isotope Test Reactor reached criticality in Lockhart, Texas, the fifth DOE-authorized advanced reactor critical that summer (DOE).

  58. DOE made a conditional commitment of HALEU for Radiant's planned microreactor at Buckley Space Force Base, saying HALEU "is not currently available from domestic suppliers" (DOE).

  59. Aalo Atomics' Critical Test Reactor reached criticality (Aalo).

  60. Centrus finalized a $900 million DOE task order for large-scale HALEU production capacity; it expects the first new capacity online by 2029 (Centrus).

  61. Deployable Energy's Unity reached criticality at INL under DOE's Nuclear Energy Launch Pad, the third DOE-authorized advanced reactor to do so (DOE).

  62. Valar Atomics' Ward 250 completed a zero-power criticality demonstration in Emery County, Utah, which DOE calls the first DOE-authorized reactor built outside a national laboratory (DOE).

  63. Antares Nuclear's Mark-0 completed a zero-power criticality demonstration at INL, the first under DOE's Reactor Pilot Program (DOE).

  64. The NRC proposed a new Part 57 for licensing microreactors and other reactors with comparable risk profiles; comments closed June 15 (rule).

  65. The NRC proposed letting commercial applicants leverage prior DOE or Department of War authorizations of demonstration reactors; comments closed May 4 (rule).

  66. The University of Illinois applied for a construction permit for its KRONOS research microreactor, based on NANO Nuclear technology; the NRC docketed it May 18 (NRC).

  67. The NRC published Part 53, its risk-informed, technology-inclusive licensing framework, effective April 29 (rule).

  68. The NRC recorded its construction permit decision for TerraPower's 345 MWe Kemmerer Unit 1 in Wyoming (NRC), after the Commission authorized staff on March 4 to issue it (release).

  69. 2025
  70. Palisades SMR, LLC submitted part one of a phased construction permit application, with a limited work authorization request, for two SMR-300 units at Palisades (NRC).

  71. DOE selected TVA and Holtec for $400 million each toward first SMR plants at Clinch River and Palisades (DOE), and BWXT said a full core of TRISO fuel for the Project Pele microreactor arrived at INL, with formal system testing planned as early as 2027 (BWXT).

  72. DOE selected 11 advanced reactor projects for its Reactor Pilot Program (DOE).

  73. Executive Order 14299 set a September 30, 2028 deadline for an Army-regulated reactor on a military base (order), and Executive Order 14300 ordered the NRC's "wholesale revision" of its regulations (order).

  74. Long Mott Energy applied for a construction permit for a four-module Xe-100 plant in Calhoun County, Texas (NRC).

  75. 2024
  76. The NRC issued Kairos Power construction permits for the Hermes 2 test reactor facility (NRC).

  77. The NRC issued Abilene Christian University a construction permit for its Molten Salt Research Reactor (NRC).

  78. 2023
  79. The NRC issued Kairos Power a construction permit for the Hermes test reactor in Oak Ridge (NRC).

Next milestone

  • 2026-11-23: Executive Order 14300's 18-month deadline for NRC final rules.
  • 2026-11-25: DOE- and War-authorized design rule takes effect.
  • 2026-12-03: Contested hearing rule takes effect (rule).
  • 2026-12-18: NRC's scheduled Radiant fuel license decision.
  • 2027-01-07: Outside date for NuCube's merger with SPAC Launch Two.
  • 2027-01-26: NRC tracker's estimated final Part 57 microreactor rule.
  • 2027-02-01: ACRS rule takes effect absent significant adverse comments.
  • 2027-03-31: Palisades final safety evaluation and EIS targets.
  • 2027-06-29: NRC tracker's estimated final reactor licensing rule, moved from March 31.
  • 2028-09-30: Executive Order 14299's deadline for an Army-regulated reactor on a base.
  • 2028-09-30: Deep Fission's first Parsons, Kansas phase targets commercial operation.

Long Mott's next decision is Dow's: a preliminary investment decision Dow is expected to consider in 2027, per X-energy.

This is a maintained page: it is revised as the record changes, and every revision is reviewed before it goes live. Dates in the text are the dates the facts hold for, not the date you are reading it.