Reference

Fusion energy: milestones, money and rules

The standing record of fusion's path from experiment to power plant: public machines, milestone programs, private money, the rules, and the first plant sites and power deals.

Where things stand

As of November 22, 2026, fusion has a laboratory ignition record, an international machine whose core components have all arrived, and power plant sites, none with a finished plant.

Public machines anchor the science. Lawrence Livermore's National Ignition Facility first got more fusion energy out than its lasers put in on December 5, 2022, and set its 8.6 MJ record on April 7, 2025. ITER's 2024 baseline puts deuterium-tritium operation in 2039.

Governments now also pay for results. DOE's Milestone-Based Fusion Development Program picked eight companies in 2023. Former DOE program staff count about $200 million appropriated through fiscal 2026 and $36.5 million paid as of September 10. Germany's SPRIND opened a milestone program on October 7 with €500 million to 2029, its early money meant to flow mainly as equity. The UK is investing over £2.5 billion in fusion over five years, including STEP, a prototype plant at West Burton targeting first operations in 2040. In Japan, Helical Fusion says a trade ministry program has formally selected it for up to about JPY 19.2 billion, though the administrator still lists it and three others as conditionally selected; the subsidy covers up to two-thirds of costs, with end-of-program milestones deciding who continues.

The private checks are bigger. The Fusion Industry Association counted $4.48 billion raised in the 12 months to July 2026. Among this year's rounds: Inertia's $450 million, Helion's Series G, Proxima Fusion's €411 million, $1 billion for Commonwealth Fusion Systems (CFS) and Type One Energy's $200 million. TAE Technologies is going public through a merger with Trump Media that has not closed.

In the US, fusion machines are headed for materials licensing, not reactor licensing, with the NRC's final regulations due by December 31, 2027 under existing law; fission is on our advanced reactors page. The NRC chose its byproduct material framework in April 2023, and its proposed rule of February 26, 2026 would add a fusion machine definition and revise its particle accelerator definition to include fusion machines. Thirty-eight Agreement States would oversee machines within their borders. Tennessee issued its first fusion-specific license, to Type One, on August 31. H.R. 10574, which its sponsor says would provide $10 billion, has sat in committee since September 24. Britain's Energy Act 2023 exempts fusion facilities from nuclear site licensing.

The first plants have sites and buyers. CFS plans its roughly 400 MW ARC in Chesterfield County, Virginia, for the early 2030s, with Google and Eni signed for power; Google's agreement is anchored in CFS's SPARC machine reaching net fusion energy, which CFS says will happen in 2027. Helion is building Orion in Malaga, Washington, to supply Microsoft. TVA issued Type One a letter of intent for Infinity Two at Bull Run, Tennessee, now rated 400 MWe. Pacific Fusion's Albuquerque machine is a demonstration, not a power plant.

Timeline

2023202420252026Nov 20, 2026Nov 18, 2026Nov 17, 2026Nov 16, 2026Nov 12, 2026Nov 11, 2026Nov 10, 2026Nov 5, 2026Nov 5, 2026Nov 4, 2026Nov 3, 2026Nov 2, 2026Oct 29, 2026Oct 28, 2026Oct 22, 2026Oct 13, 2026Oct 12, 2026Oct 8, 2026Oct 8, 2026Oct 7, 2026Oct 6, 2026Oct 6, 2026Oct 2, 2026Oct 2, 2026Sep 30, 2026Sep 30, 2026Sep 30, 2026Sep 30, 2026Sep 24, 2026Sep 21, 2026Sep 15, 2026Sep 15, 2026Sep 14, 2026Sep 10, 2026Sep 9, 2026Sep 2, 2026Aug 31, 2026Aug 31, 2026Aug 27, 2026Aug 25, 2026Jul 30, 2026Jul 16, 2026Jul 10, 2026Jul 7, 2026Jun 16, 2026Jun 9, 2026Jun 8, 2026Jun 4, 2026May 27, 2026Apr 28, 2026Feb 26, 2026Feb 11, 2026Jan 13, 2026Dec 18, 2025Oct 1, 2025Sep 22, 2025Sep 19, 2025Jul 30, 2025Jul 22, 2025Jun 30, 2025Jun 12, 2025Apr 7, 2025Dec 17, 2024Jul 9, 2024Jul 3, 2024May 31, 2023May 10, 2023Apr 13, 2023Dec 5, 2022
69 dated events, 2022 to 2026. Jump to 2026, 2025, 2024, 2023, 2022.
  1. 2026
  2. Pacific Fusion said New Mexico had approved its radioactive materials license, letting it possess and use tritium at its Albuquerque campus; the Albuquerque Journal reports the license was granted in August; see New Mexico licenses Pacific Fusion to use tritium in Albuquerque.

  3. Helical Fusion said it had been formally selected for a METI grant of up to about JPY 19.2 billion (USD 126 million) through February 2029, for its HARUKA demonstration device, KANATA plant design and core technologies; the administrator still lists it as conditional; see NRC sets path for DOE-tested reactors; India clears RAPP-8 to go critical.

  4. TAE said it is upgrading Norm and aims to reach 100 million degrees Celsius at fusion-relevant density and confinement in 2027, subject to installation and testing; Norm is the proving ground for Da Vinci, a 50 MW plant targeted to demonstrate fusion energy by 2031 (PR Newswire); see TAE upgrades Norm, Wisconsin backs Realta, Nuclea closes Moltex purchase.

  5. France's research minister presented a fusion strategy for 2026 to 2035 at the CEA's WEST tokamak (ITER); magnetic confinement is its main path, and from 2031 it plans to prepare the design and begin building a pilot plant in a European framework (strategy); see France plans fusion to 2035, Sila signs Panasonic, Tesla unveils Powercore.

  6. The IAEA's fourth World Fusion Outlook counts 174 fusion facilities operating, under construction or planned, 63 privately funded. FusionX's section puts private committed capital at $21.9 billion, not directly comparable with Fusion Industry Association totals, the report says, and estimates a further $80 billion could be needed over 20 years to reach commercialization (report); see IAEA's World Fusion Outlook 2026 counts 174 fusion facilities worldwide.

  7. UK Fusion Energy tendered five STEP system partner lots, estimated at £115 million excluding VAT (tender notice); see UK Fusion Energy opens £115m tender for five STEP system partners.

  8. PPPL said NSTX-U's central magnet assembly was lowered into the machine on October 27, with centering scheduled for November, final assembly expected by early 2027 and operations later that year; see Oklo test reactor cleared, NSTX-U magnet lowered in, Omega raises $80M.

  9. Kyoto Fusioneering agreed to supply 170 GHz, 1 MW-class gyrotron systems for plasma heating on Infinity One, Type One's stellarator prototype at Bull Run, with deliveries to be completed in 2029; see Gyrotrons for Type One, PPPL's INFUSE trio and a Thea coil test at MIT.

  10. The SEC declared Trump Media's S-4 for the TAE merger effective, and Trump Media filed the definitive proxy statement/prospectus for the December 14 shareholder vote (Form 425).

  11. Thea Energy said it will test a full-field, full-force encircling coil for its Eos stellarator at MIT's Plasma Science and Fusion Center; see Gyrotrons for Type One, PPPL's INFUSE trio and a Thea coil test at MIT.

  12. UKAEA lowered a 12-tonne double beam box into position for MAST Upgrade, its spherical tokamak at Culham; the two neutral beam injectors it will house will double the machine's neutral beam heating power from 4.4 MW to 8.8 MW, with all major hardware expected to be manufactured and fitted inside the box by the end of autumn 2027 and experiments due in 2028 (GOV.UK); see MAST Upgrade gets a 12-tonne beam box to double its neutral beam heating.

  13. DOE's Office of Science selected 28 INFUSE projects for $8.5 million in fiscal 2026 funding, pairing 22 companies with national laboratories and universities; selection for award negotiations, DOE says, is not a commitment to fund. Its fiscal 2027 call adds a review topic for fusion pilot plant preconceptual designs (DOE); see DOE selects 28 INFUSE fusion projects for $8.5M at labs and universities.

  14. Trump Media's amended S-4 set a December 14 shareholder vote on the TAE merger, expected to close before the December 18 end date, and said TAE had drawn the full $100 million second tranche of its convertible note, funded October 7 (Form S-4/A).

  15. Proxima Fusion and Kyoto Fusioneering signed an MoU to expand joint work on plasma-heating gyrotrons and fuel cycle technologies. Kyoto Fusioneering also signed one with Focused Energy, to explore laser fusion cooperation, and Proxima one with Fujikura on plans for HTS tape manufacturing in Germany; see Kyoto Fusioneering signs fusion MoUs with Proxima and Focused Energy.

  16. Commerce signed CHIPS letters of intent for up to $389 million in R&D awards to four companies, including up to $175 million for Helion, for high-voltage power semiconductors and power modules for pulsed-power fusion, and up to $85 million for CFS, for semiconductors for radio-frequency plasma heating, power electronics, embedded electronics for fusion diagnostics and radiation-hardened electronics; as a condition, Commerce will take a minority, non-voting equity stake in each company; see Helion and CFS sign CHIPS letters of intent for fusion chip R&D.

  17. UK Fusion Energy's 2025/26 annual report says it met 16 of its 21 corporate performance measures, partly met one and missed four, and spent £118.8 million (outturn, within 1% of budget); the UKAEA Board approved a £167.5 million budget for 2026/27. It contracted the ILIOS consortium as construction partner on April 2, 2026 and decided not to appoint an engineering partner for now; UKAEA took ownership of half the West Burton site from EDF on March 23, 2026 (annual report); see UK Fusion Energy missed four of 21 targets in 2025/26, spent £118.8m.

  18. Fermilab said it is launching MAGNES, a superconducting cable test platform for fusion and particle accelerator magnets, funded jointly by DOE's offices of Fusion, High Energy Physics and Nuclear Physics; a Berkeley Lab 15-tesla dipole will supply its background field, test cables will carry up to 100,000 amps, and the first cable tests are expected in summer 2028; see Fermilab's fusion cable tester, Oklo's Groves 2 Forge, Bluecore's uranium.

  19. DOE selected a project led by CFS to build an AI-enabled digital twin of SPARC among 12 Genesis Mission Phase II projects totaling $159 million; partner lab PPPL says the twin will predict a full plasma pulse in less than 20 minutes, with its NSTX-U experiment as the test bed (PPPL). Neither DOE's release nor its selection list gives a per-project amount; the list says selection is not a commitment to fund; see CFS to lead DOE Genesis Mission project on an AI digital twin of SPARC.

  20. General Fusion said its LM26 machine heated plasma electrons to 1,090 ± 40 eV, measured by Thomson scattering with UKAEA, and to 1,180 ± 65 eV by X-ray diodes, in two papers submitted for peer review (General Fusion, Thomson scattering paper, compression paper); see General Fusion says LM26 hit 1.1 keV electrons in paper under peer review.

  21. SPRIND launched a milestone-based fusion program for Germany's research ministry, with €500 million to be made available by 2029 and total public funding to rise to as much as €2.5 billion; see Germany's SPRIND opens fusion milestone program with up to €500M to 2029.

  22. Type One Energy closed a $200 million Series B co-led by Breakthrough Energy Ventures and Clutterbuck Capital, for its stellarator program and Project Infinity; see Type One Energy raises $200M Series B for its Tennessee fusion plant.

  23. Xcimer Energy finalized up to $30.5 million for the second budget period of DOE's milestone program, bringing its potential milestone payments to $39.5 million; see Xcimer Energy finalizes up to $30.5M more from DOE fusion milestone program.

  24. Trump Media filed a delaying amendment to its S-4 for the TAE merger, holding the registration's effective date until a further amendment or an SEC determination (delaying amendment).

  25. ITER took delivery of vacuum vessel sector #2 from Europe, which it calls the last of its core tokamak components; see ITER's ninth and final vacuum vessel sector arrives from Europe.

  26. CFS agreed to buy more than 10,000 km of high-temperature superconducting tape from Fujikura for its ARC plants, starting with Fall Line, in what it called the largest agreement of its kind for HTS tape.

  27. Trump Media filed the S-4 registration statement for its all-stock merger with TAE (Form 8-K).

  28. The S-4 says TAE's recurring losses, negative operating cash flows and continuing capital needs raise substantial doubt about its ability to continue as a going concern (Form S-4); the same day the two companies amended and restated the $200 million convertible note Trump Media funded in December 2025, letting TAE draw up to $100 million more until November 29, 2026, or until the merger agreement terminates, if earlier (Form 8-K); see Helion closes at $500M, Hyundai joins CFS, Trump Media files for TAE.

  29. California enacted SB 925, which requires the California Energy Commission to deliver a fusion strategic plan by December 31, 2029 (SB 925); see Newsom signs SB 925 fusion strategic plan and AB 2647 nuclear assessment.

  30. H.R. 10574, the American Leadership in Fusion Act, was introduced and referred to the House Committee on Science, Space, and Technology (GovInfo); see Lofgren fusion bill would appropriate $10 billion for commercialization.

  31. nT-Tao and Orion Nuclear Energy signed an MoU making Orion the US project development partner for nT-Tao's compact fusion system, designed for up to 20 MW (GlobeNewswire); see nT-Tao and Orion sign MoU on US deployment of up-to-20 MW fusion system.

  32. At an IAEA General Conference side event, CNNC released an HL-3 tokamak joint experimental plan, and China Fusion Energy Co. signed a memorandum of cooperation with the ITER Organization (CNNC); see CNNC proposes fusion engineering platform, unit signs ITER memorandum.

  33. UK Fusion Energy, STEP's delivery body, became a Tier 1 member of the Manufacturing Technology Centre and expects to spend up to £10 million through it; see UK Fusion Energy joins MTC as Tier 1 member, to spend up to £10m on R&D.

  34. The UK and US closed the Global Fusion Policy Summit in London with a joint statement that fusion safety standards should be distinct from fission safety standards (GOV.UK); see UK Fusion Week: a UK-US statement, a supercomputer link and up to £3m.

  35. Hyundai Motor Group became an investor in CFS's $1 billion round; CFS gave no amount (CFS).

  36. Thea Energy said 16 peer-reviewed papers on its Helios stellarator power plant had been published as a special issue of Fusion Engineering and Design; see Thea Energy's Helios stellarator design lands in 16 peer-reviewed papers.

  37. Realta Fusion and Madison Gas and Electric agreed to explore a 200 MWe fusion plant in Wisconsin, with MGE's parent taking an equity stake in Realta; see MGE Energy buys into Realta Fusion to explore 200-MWe Wisconsin plant.

  38. The administrator of Japan's fusion power demonstration subsidy listed four conditionally selected proposals, pending formal selection: EX-Fusion (laser), Helical Fusion, LINEA Innovation (beam-assisted FRC) and Starlight Engine (HTS tokamak).

  39. Tennessee issued Type One Energy the state's first fusion-specific byproduct material license, for Project Infinity at TVA's Bull Run site (TDEC); see Tennessee issues Type One Energy a fusion-specific license.

  40. Marathon Fusion said its plasma centrifuge had enriched hydrogen and lithium isotopes; see Marathon Fusion says its plasma centrifuge enriched lithium and hydrogen.

  41. Pacific Fusion announced it had broken ground, in a release datelined August 24, on a $1 billion campus in Albuquerque for a machine designed to reach net facility gain by 2030, and NNSA signed an MoU with the company (NNSA); see Pacific Fusion breaks ground on a $1 billion fusion campus in Albuquerque.

  42. CFS announced $1 billion of new capital, which it called the largest single fusion funding round since its own $1.8 billion round in 2021, for $4 billion raised in total.

  43. Lawrence Livermore reported more than 3,000 full-power shots on the Sirius pulsed-power prototype in a campaign with Pacific Fusion under a cooperative research agreement (LLNL); see LLNL and Pacific Fusion push Sirius pulser past 3,000 shots.

  44. General Fusion completed its business combination with Spring Valley Acquisition Corp. III, and its shares trade on Nasdaq as GFUZ (shell company report); its later prospectus says it received net proceeds of about $123.4 million at closing (prospectus).

  45. Proxima Fusion announced a €411 million round led by XTX Ventures and East X Ventures, backing Alpha, its net-energy stellarator demonstrator near Munich.

  46. Helion said the Washington Department of Health had granted it two licenses for its Orion fusion power plant.

  47. Tennessee's fusion machine rules, Chapter 0400-20-14, took effect (TDEC).

  48. DESNZ opened consultation on EN-8, the draft National Policy Statement for fusion energy, which closed August 17 and is being analysed (GOV.UK).

  49. Helion announced a $465 million Series G led by Thrive Capital, later updating the page to say it closed at $500 million in September.

  50. Thea Energy raised a $100 million Series B led by Thomas Tull's US Innovative Technology Fund.

  51. CFS applied to connect its first ARC plant to PJM Interconnection and named the Chesterfield County site the Fall Line Fusion Power Station.

  52. The NRC published its proposed rule "Regulatory Framework for Fusion Machines," with comments due May 27 (Federal Register).

  53. Inertia announced a $450 million Series A led by Bessemer Venture Partners (GlobeNewswire).

  54. Thea Energy said DOE had certified its Helios preconceptual pilot plant design, the first awardee in the milestone program to receive that certification.

  55. 2025
  56. Trump Media & Technology Group and TAE Technologies agreed an all-stock merger, with either side able to terminate if it has not closed by December 18, 2026 (Form 8-K).

  57. The Hefei Institutes of Physical Science installed the Dewar base of BEST, a compact tokamak under construction in Hefei scheduled for completion by the end of 2027 (HFIPS).

  58. Eni signed a power offtake agreement worth more than $1 billion for electricity from CFS's ARC plant (CFS).

  59. TVA issued Type One Energy a letter of intent on potential deployment of its fusion plant at the former Bull Run Fossil Plant (TVA, via Type One Energy).

  60. Helion began work on the site of Orion, its first fusion power plant, in Malaga, Washington.

  61. CNNC inaugurated China Fusion Energy Co. in Shanghai.

  62. Google signed a power purchase agreement for 200 MW from CFS's first ARC plant (CFS).

  63. The UK government announced a record £2.5 billion for fusion, including support for STEP, the prototype plant at West Burton that targets first operations in 2040 (GOV.UK).

  64. The National Ignition Facility set its yield record, 8.6 MJ from 2.08 MJ of laser energy, a target gain of 4.13 (LLNL).

  65. 2024
  66. CFS said it would build its first ARC plant, about 400 MW, in Chesterfield County, Virginia.

  67. The ADVANCE Act became law, adding a "fusion machine" definition to the Atomic Energy Act and requiring an NRC report on licensing frameworks for mass-manufactured fusion machines (Public Law 118-67).

  68. ITER presented its 2024 baseline: start of research operation in 2034, full magnetic energy in 2036 and deuterium-tritium operation in 2039.

  69. 2023
  70. DOE announced $46 million for eight companies in its Milestone-Based Fusion Development Program.

  71. Helion agreed to supply Microsoft electricity from its first fusion plant, expected online by 2028.

  72. The NRC Commission approved licensing and regulating fusion energy systems under its byproduct material framework in 10 C.F.R. Part 30 (NRC).

  73. 2022
  74. The National Ignition Facility produced 3.15 MJ of fusion energy from 2.05 MJ of laser energy, which DOE called the first controlled fusion experiment to reach that milestone (DOE).

Next milestone

  • 2026-12-13: Applications close for DOE's fiscal 2027 INFUSE call.
  • 2026-12-14: Trump Media shareholders vote on the TAE merger.
  • 2026-12-18: TAE merger end date, after which either side may terminate.
  • 2026-12-31: Type One intends to break ground at Bull Run in 2026.
  • 2027-01-13: Applications close for SPRIND's fusion milestone program.
  • 2027-01-29: STEP system partner tenders due.
  • 2027-04-06: STEP system partner award decision expected.
  • 2027-12-31: Statutory deadline for the NRC's fusion machine regulations (NRC tracker).
  • 2028-12-31: General Fusion's target for all three LM26 milestones.
  • 2029-12-31: Kyoto Fusioneering's gyrotron deliveries for Type One's Infinity One due.
  • 2029-12-31: California's fusion strategic plan is due to the Legislature.

ITER aims to move the sector #9 module into the tokamak pit in early December (ITER) and expects the last module there by mid-2027. General Fusion's three LM26 milestones are 1 keV, 10 keV and the Lawson criterion; it says upgrades for the 10 keV attempt are under way but gives no date. UK Fusion Energy plans the next formal stage of consultation on STEP's Development Consent Order in early 2027; the rest of the West Burton site is to transfer in 2028, when EDF completes its coal plant decommissioning (UK Fusion Energy). The National Academies study will assess DOE's milestone approach, and SPRIND's call says it will decide in principle in 2029 which demonstrators to back. Type One's January release put Infinity Two construction as early as 2028 under TVA's letter of intent (Type One Energy).

This is a maintained page: it is revised as the record changes, and every revision is reviewed before it goes live. Dates in the text are the dates the facts hold for, not the date you are reading it.