#microreactors
NASA opens bidding to design a 20 kW reactor for the Moon
NASA's Glenn Research Center posted the SPARC request for proposals on November 20, 2026, seeking designs for Lunar Reactor-1, a fission system delivering at least 20 kWe at the lunar south pole for five years, with launch readiness targeted for December 2030. Proposals are due December 21; NASA expects to award contracts on April 15, 2027.

NRC sets path for DOE-tested reactors; India clears RAPP-8 to go critical
The NRC's DANU-ISG-2026-02, scheduled for Federal Register publication on November 23, 2026, maps how reactor applicants can reuse DOE or Department of War authorizations, and NRC staff found no significant impact from Radiant's Oak Ridge fuel facility. India's AERB cleared RAPP-8 for first approach to criticality on November 19, and Helical Fusion says a METI program selected it for up to JPY 19.2 billion.
France plans fusion to 2035, Sila signs Panasonic, Tesla unveils Powercore
France's research ministry presented a 2026-2035 fusion strategy on November 16, 2026 that makes magnetic confinement its reference path toward a European pilot plant. Sila agreed a multi-year anode offtake with Panasonic Energy, part of a relationship Sila says has the potential for over $1 billion of offtake over time, Tesla introduced its 7.4 MW Powercore solid-state transformer for 2027, and Radiant is expanding its El Segundo and Oak Ridge sites for Kaleidos production.
Oklo test reactor cleared, NSTX-U magnet lowered in, Omega raises $80M
DOE cleared Oklo's Groves-1 test reactor in Texas for its research phase, Oklo said on November 11, 2026, and PPPL lowered NSTX-U's central magnet into the machine on October 27, with operations expected later in 2027. Standard Nuclear reported total contract backlog of $577.2 million, Project Omega raised an $80 million Series A for used-fuel recycling, and a US-funded Holtec SMR-300 simulator opened in Almaty.

Last Energy asks NRC to start foundation work for a Texas PWR-20 reactor
Last Energy filed part one of a two-part phased NRC construction permit application on October 20, 2026, seeking a limited work authorization for reactor-foundation work on its PWR-20 at a site in Caldwell County, Texas. The NRC noticed receipt on November 5 and has not yet accepted the application for docketing.
NRC final rule puts contested hearings on three tracks with fixed clocks
The US Nuclear Regulatory Commission finalized a rule on October 30, 2026 that sorts contested licensing hearings into Standard, Focused and Expedited tracks with fixed deadlines, designed to finish most cases in about a year and the simplest in roughly six months. It takes effect 30 days after Federal Register publication, scheduled for November 3, 2026.

DOE approves Radiant's Kaleidos safety analysis for full-power testing
Radiant says DOE approved the documented safety analysis for its Kaleidos microreactor test at Idaho National Laboratory, covering operation at power as well as criticality; a DOE readiness review comes before fueling.
Antares signs BWXT for TRISO fuel, its second fabrication deal
Antares Nuclear has signed BWX Technologies to make HALEU TRISO fuel for its microreactors on BWXT's Lynchburg, Virginia, line, starting with an initial allocation of one metric ton of uranium. Antares says the deal runs through the end of the decade; BWXT calls it multi-year, with quantities set by future task orders.
DARPA backs a Kilopower test, Taiwan's NTHU signs with NuCube
Space Nuclear Power Corporation said on October 21, 2026 that DARPA awarded it an agreement for a Kilopower ground test with active control rods, a step past the passively controlled 2018 KRUSTY test. Taiwan's National Tsing Hua University signed a microreactor feasibility agreement with NuCube on October 19, NANO Nuclear hired IMPSA for a KRONOS design review expected to include a check against ASME Section III, and Stiesdal said on October 22 that its 6.5 MW electrolyser is in commercial operation at Måde, Denmark.
Antares clears a DOE gate, Finland licenses Onkalo, QuantumScape and Saft
DOE approved the Nuclear Safety Design Agreement for Antares' electricity-producing Mark-1 reactor, the company said October 23, 2026. QuantumScape plans a 100 MWh cell line with Muehlbauer, targeted for 2028, as PowerCo pauses milestone payments, Saft opened solid-state lines in Bordeaux without a capacity figure, and Finland's government granted Posiva what the company calls the first operating licence for spent-fuel final disposal on October 22.
Advisers back Long Mott permit, Navy picks Radiant for Crane microreactor
The NRC's Advisory Committee on Reactor Safeguards said on October 16, 2026 that its review supports a construction permit for Long Mott, a four-unit Xe-100 plant at Dow's Texas site, while listing fuel and source-term work for the operating license. The Navy picked Radiant on October 20 for a prototype microreactor at Naval Weapons Station Crane, Deep Fission signed a Kansas purchase agreement with no minimum purchase, Westinghouse announced an approximately $1 billion LEU+ fuel factory, and an IAEA mission found the UAE's response to a May drone strike at Barakah effective.
NRC lets reactor applicants use DOE and Department of War test results
The Nuclear Regulatory Commission finalized a rule, dated October 22, 2026, letting commercial reactor applicants cite relevant information from reactors the Department of Energy or Department of War previously authorized and tested. Applicants must show how that record meets NRC rules and account for any differences in design, hazards or siting, and the NRC still conducts an independent review.

EU picks 77 net-zero projects, Alaska backs NuCube, ITM's record year
The European Commission selected 77 projects for €3.4 billion of Innovation Fund support on October 19, 2026, among them €20.2 million for Minesto's tidal kite array and a heat-only small modular reactor. The same day, Alaska's AIDEA agreed to invest $25 million in microreactor developer NuCube, and ITM Power reported revenue up 68% to £43.6 million for the year to April 2026.
Last Energy says DOE approved its Texas pilot reactor's safety analysis
Last Energy said on October 7, 2026 that the Department of Energy approved the Documented Safety Analysis for its pilot reactor at Texas A&M-RELLIS, which it calls the final safety analysis in DOE's authorization process. A DOE readiness review is the last step before startup authorization for criticality, the company says; its release gives no date. Oklo's Groves reactor went critical five weeks after its own approval was announced.

Advanced reactors in the US: SMRs and microreactors
As of November 28, 2026, three advanced reactor plants hold NRC construction permits issued this year, none an operating license; DOE's August 6 count put five advanced reactors critical under its authorization, and Oklo has Centrus HALEU deliveries scheduled from 2029.
DOE clears MARVEL microreactor's final safety analysis for dry criticality
DOE's Idaho Operations Office approved the final documented safety analysis for MARVEL, the test microreactor Idaho National Laboratory leads for DOE, authorizing a dry, near-zero-power criticality configuration INL anticipates reaching in December 2026, INL said on October 6, 2026. The reactor's primary coolant system arrived at INL's Transient Reactor Test Facility in mid-September; INL's own project page still dates initial criticality to 2027.

Westinghouse eVinci reaches zero-power criticality at 663°C
Westinghouse said on September 15, 2026 that its eVinci microreactor test reached zero-power criticality at 663°C on September 3 at the National Criticality Experiments Research Center in Nevada, and that researchers made a subcritical reactivity measurement at a peak core temperature of 1,011°C, which the company calls a record high temperature for a reactivity measurement at NCERC. The run follows the August 24 zero-power criticality at the same facility.
Department of War plans shore-based Navy microreactor at Crane by 2028
The Department of War announced on September 9, 2026 the planned installation of an advanced nuclear Micro Modular Reactor at Naval Weapons Station Crane, Indiana, no later than September 2028, executed through the Army's Janus Program with the Navy and the State of Indiana. The release describes the reactor as commercially owned and operated and as the first power-producing reactor installed in Indiana, and names no vendor, design, output, or cost; an Army official's quote cites the Army's "regulatory authorities" without saying who licenses the unit.

Centrus signs HALEU supply contract for Radiant's Kaleidos microreactors
Centrus Energy said in a Form 8-K filed September 9, 2026 that it has signed a definitive multi-year contract to supply high-assay low-enriched uranium for multiple of Radiant Industries' Kaleidos microreactors, with deliveries scheduled to begin before the end of the decade and Radiant prepayments supporting Centrus's domestic commercial enrichment capacity program. The release gives no quantity or value. The same day Centrus priced a $500 million public offering of shares and warrants, its second enrichment contract with customer prepayments in five weeks after X-energy's on August 6.

Standard Nuclear to supply Antares up to eight tons of TRISO fuel
Standard Nuclear announced a binding TRISO fuel supply agreement with Antares Nuclear on August 27, 2026: a minimum of one metric ton of uranium as a firm commitment, plus customer options for up to seven more, with the release describing deliveries through 2035. It is the second definitive TRISO supply agreement the company has announced in August 2026, after an August 20 deal with Radiant Industries.
Five US microreactor designs went critical in the summer of 2026
Five US microreactor designs completed first zero-power criticality tests between June and August 2026, all under DOE authorization rather than NRC licenses: Antares Nuclear's Mark-0, Valar Atomics' Ward 250, Deployable Energy's Unity, Aalo Atomics' Critical Test Reactor, and Westinghouse's eVinci. Four went critical at DOE-complex sites and Valar's at the Utah San Rafael Energy Lab, with the Valar details per POWER magazine's account. Radiant shipped its 1 MWe Kaleidos to Idaho National Laboratory's DOME test bed in August 2026 for the field's first full-power test campaign, targeted for completion in the third quarter of 2026, per Radiant's announcement, and BWXT plans formal testing of the Army's Project Pele prototype as early as 2027. Deployment money so far is federal: the Army's Janus program totals up to $2.2 billion across five vendors, with a first reactor targeted to operate by September 30, 2028; no nuclear microreactor supplies power to a US commercial grid today, per AP.

US Army awards up to $2.2 billion for microreactors at five bases
The US Army selected five vendors on August 26, 2026 under its Janus Program: Antares Nuclear at Fort Bragg, BWXT at Fort Campbell, General Atomics at Fort Hood, Radiant Industries at Fort Benning, and Westinghouse Government Services at Fort Drum, with up to a combined $2.2 billion in milestone-based funding across fiscal 2027 through 2031. The Army expects more than 20 microreactors across installations and targets a first reactor operating by September 30, 2028; the reactors will be licensed by the Army rather than the Nuclear Regulatory Commission, per AP.
