SPP files $25/MWh bid cap for flexible loads in FERC large-load package
A companion filing would make customers pay and secure delivery-point upgrade costs above the lesser of $25 million or $500,000 per MW; the non-firm service itself targets the second quarter of 2028.
The Southwest Power Pool wants its most flexible loads to run on cheap power only. Under a Price Adaptive Load Service that SPP filed at the Federal Energy Regulatory Commission on November 19, 2026 (ER27-578), a flexible commercial or industrial load would bid for energy under a uniform $25/MWh cap, and whenever the price at its settlement location exceeds $25 it is dispatched to zero. That is a quarter of MISO's $100/MWh interruption price (GRITS filing), an eighth of NYISO's $200/MWh bid cap (NYISO filing) and a tenth of ISO New England's $250/MWh re-dispatch price (ISO-NE filing), by our arithmetic.
The bid cap is one piece of a three-filing package SPP made on November 18 and 19 in answer to FERC's June 18 large-load show-cause order, after ISO New England, PJM, MISO, NYISO and the California ISO had filed theirs (our interconnection queues page tracks them). A second filing (ER27-577) makes the transmission customer requesting a new or enlarged delivery point pay for, and secure, network upgrade costs above the lesser of $25 million or $500,000 per MW. A third (ER27-559) requires every study of a High Impact Large Load to evaluate grid-enhancing technologies.
Cheap hours, billed by the hour
PALS is non-firm, as-available service for terms of one to ten years. It needs no supporting generation, will not cause network upgrades to be built (the customer pays for any facilities needed to connect it) and carries no resource adequacy obligation. In a constraint or emergency it ranks behind all firm service and behind CHILLS, SPP's bridge service for large loads waiting on firm service, and level with hourly non-firm point-to-point service. It is also open to loads below SPP's large-load thresholds, though not to critical loads.
The bill follows the usage. A PALS customer pays the hourly non-firm point-to-point rate on the kilowatts it actually takes, capped each month at the monthly rate times its highest hourly use. SPP says that is where it parts from the Non-Firm Contract Demand service FERC required of PJM, which is reserved by the megawatt: a PALS customer will "only pay when it withdraws, instead of paying for the reservation."
The $25 figure came out of a simulation. SPP modeled ten 200 MW price-adaptive loads at locations with historically low prices over 42 days of historical market data, a week (the 10th through the 16th) of every other month beginning in February 2025 to capture seasonal and weekday-weekend swings, testing caps from $20 to $35. Moving the cap from $20 to $25 raised the loads' real-time load factor from 45% to 60%, the largest gain of any step, while average real-time prices rose $0.20/MWh; the next step to $30 added $0.80/MWh. Extra wind dispatch stopped growing above $25. SPP also cites stakeholders' preference for "an initially conservative bid cap" and promises to review it at least annually.
Curtailment earns nothing. SPP draws a line between PALS and demand response, whose participants hold firm service and give up part of it: "compensating PALs for reducing withdrawals that they have no firm right to take would pay them for forgoing service they never purchased."
The software comes last. SPP asks FERC for an order by February 17, 2027, but leaves the effective date open and targets implementation for the second quarter of 2028.
A ceiling on shared upgrade costs
The second filing caps what everyone else pays to hook up a load. SPP's tariff sets no limit on the network upgrade costs that can be spread across other customers' rates for a delivery point request, SPP says, "regardless of the costs relative to the load requested or whether the load materializes." Under the Load Safe Harbor Limit, costs above the lesser of $25 million or $500,000 per MW are directly assigned to the requesting customer, recovered through the transmission owner's revenue requirement for up to 40 years before any remainder reverts to shared funding, and backed by financial security that shrinks as the upgrades depreciate. The limit applies to requests submitted on or after its effective date, which SPP asks to be February 17, 2027.
The $500,000 per MW sits between the 75th percentile (about $378,000) and 95th percentile (about $1.018 million) of past delivery point studies that needed upgrades, against a median of about $177,000. The $25 million is 50 MW times $500,000, matching the 50 MW threshold for a large load connected above 69 kV, so for any request that size or bigger the dollar cap is the one that binds. By our arithmetic, a 1,000 MW campus whose studies found $100 million of upgrades would pay $75 million itself; without the aggregate cap, SPP notes, a 1,000 MW request could qualify for $500 million of regional funding.
The limit reached FERC without the approval of SPP's tariff working group or its Markets and Operations Policy Committee. The tariff working group did not approve it in an October 12 vote, and the committee "failed to pass any motion related to the LSHL." Two other groups recommended versions of it: the Cost Allocation Working Group, which reports to the state regulators, voted six in favor, four against and five abstentions for a $21.25 million limit on loads of 50 MW or larger, and SPP's cost-allocation review team (the CARE Team) voted 14 in favor with two abstentions for one with direct assignment capped at 20 years. State regulators carried it: the Regional State Committee, which SPP's bylaws give primary responsibility for deciding whether participant funding is used, approved it 14 to 1 with one abstention on November 16, and SPP's board approved the filing.
Grid-enhancing technologies first
Large-load studies would have to weigh grid-enhancing technologies every time, without waiting for a customer to ask. The third filing, which SPP asks to take effect February 16, 2027, makes each High Impact Large Load study report explain the result of that evaluation, writes the existing operating requirements for those loads into the standard service agreements, and puts the upgrades and costs for those delivery points into SPP's transmission expansion plan in a searchable, filterable format. It also replaces the tariff's undefined "non-jurisdictional" label with a defined Non-Transmission Facility, to settle when behind-the-meter and co-located generation gets studied and who answers when it fails to register in the market.
Outlook
FERC set comment dates of December 9 for ER27-559 and December 10 for ER27-577 in its November 19 combined notice. SPP says its separate response in the show-cause docket, EL26-68, covers, among other things, transmission and ancillary service rates for co-located load; FERC's August 14 abeyance order set November 20 for responses and December 21 for answers. If FERC accepts PALS as filed and SPP holds its target, the service could start in the second quarter of 2028, around the June 1, 2028 date NYISO requested for its large-load market rules, and ahead of January 1, 2029, the earliest MISO says it can run GRITS, at the lowest trigger price of the four. Our earlier coverage of the MISO and NYISO filings and ISO New England's has the other designs.
⚠ The Outlook extrapolates from the comment dates in FERC's November 19, 2026 combined notice, the response and answer dates in FERC's August 14, 2026 abeyance order, SPP's requested order date and second-quarter 2028 implementation target in ER27-578, and the dates NYISO and MISO give in their own filings for their non-firm services.
Sources
Primary
- Southwest Power Pool, Inc., Submission of Tariff Revisions to Add the Price Adaptive Load Service, Docket No. ER27-578-000 · Southwest Power Pool (filed with the Federal Energy Regulatory Commission)
Supporting
- Letter order granting abeyance, Southwest Power Pool, Inc. et al., Docket No. EL26-68-000 (196 FERC ¶ 61,128) · Federal Energy Regulatory Commission
- ISO New England Inc. et al., Revisions to ISO New England Inc. Transmission, Markets and Services Tariff Related to the Integration of Large Loads to the Transmission System, Docket No. ER27-484-000 (transmittal letter and testimony) · ISO New England Inc., NEPOOL Participants Committee and Participating Transmission Owners (filed with the Federal Energy Regulatory Commission)
- Midcontinent Independent System Operator, Inc., Grid Responsive Integration Transmission Service Filing, Docket No. ER27-527-000 · MISO (filed with the Federal Energy Regulatory Commission)
- New York Independent System Operator, Inc., Proposed Tariff Revisions to Establish New Large Load Integration Procedures and Related Market Participation Provisions, Docket No. ER27-517-000 · NYISO (filed with the Federal Energy Regulatory Commission)
- Southwest Power Pool, Inc., Submission of Tariff Revisions to Enhance Transmission Service Provisions for High Impact Large Loads and Clarify Interconnection and Market Registration Requirements for Non-Transmission Facilities in Response to Show Cause Order, Docket No. ER27-559-000 · Southwest Power Pool (filed with the Federal Energy Regulatory Commission)
- FERC, Combined Notice of Filings #1, November 19, 2026 · Federal Energy Regulatory Commission
- Southwest Power Pool, Inc., Submission of Tariff Revisions to Establish Load Safe Harbor Limit for Delivery Point Costs, Docket No. ER27-577-000 · Southwest Power Pool (filed with the Federal Energy Regulatory Commission)
Copies of cited sources are retained where available. If a link no longer resolves, request a copy at contact@theduckcurve.com.