Brief

NRC draft EIS preliminarily backs license for Orano's Oak Ridge plant

Nuclear Regulatory Commission staff have issued a draft environmental impact statement for Project IKE, the gas centrifuge enrichment plant Orano Enrichment USA wants to build in Oak Ridge, Tennessee, and their preliminary recommendation is that the NRC issue the license "unless safety issues mandate otherwise." The draft, posted to the NRC docket on November 20, 2026, evaluates a 40-year license and concludes that impacts "would be SMALL with mitigation," with some socioeconomic impacts SMALL to MODERATE, "with the latter being beneficial impacts." The plant would enrich uranium to a maximum of 10 percent uranium-235 by weight on a 188-acre portion of a 624-acre parcel.

The Department of Energy, which left the review in September, is running its own review of the same ground. No agency is formally cooperating on the EIS, the draft says; DOE "will now complete its regulatory action under a separate NEPA review" with the Army Corps of Engineers, covering site preparation that needs a deed amendment from DOE and a Clean Water Act Section 404 permit. The NRC counts that site work anyway, calling its totals "a conservative assessment of impacts." Orano puts the construction cost, site preparation included, at $5 billion.

The safety review is running later than the environmental one. In an October 27 letter, NRC staff granted Orano more time: Orano now expects to answer all of the staff's requests for additional information by December 14, 2026, and staff expect to finish its review by June 2027 rather than April. Staff have treated Orano's structural design criteria as "a high-impact technical issue" from the outset, with no resolution as of the letter. The original schedule also assumed a crosswalk to Eagle Rock, an Idaho enrichment plant the NRC licensed in October 2011 to AREVA Enrichment Services, since renamed Orano USA; it was never built. The crosswalk was not provided, and staff found "limited similarities" between the two applications that could speed the review.

The final EIS is scheduled for April 2027. Staff will consider comments on the draft before making a final recommendation; as of November 21, no Federal Register notice had set a comment deadline.

Sources

Primary

Supporting

Copies of cited sources are retained where available. If a link no longer resolves, request a copy at contact@theduckcurve.com.