Roundup

Chashma-5 dome set, TVA moves on Watts Bar renewal, CANDU study for Türkiye

Watts Bar Unit 2's license already runs to 2055, TVA's board materials show, and the AtkinsRéalis study for Türkiye, due before the end of 2027, names no site.

Three nuclear stories from November 10 to 12, 2026: Pakistan set the inner containment dome on what will be its largest reactor, TVA's board handed its chief executive the decision on renewing both Watts Bar reactor licenses, and AtkinsRéalis signed on to study CANDU reactors for Türkiye.

Chashma-5 gets its dome

The Pakistan Atomic Energy Commission has placed the dome on Chashma-5, a 1,200 MW unit expected to begin generating electricity in September 2030, at a ceremony on November 10, 2026 attended by Prime Minister Shehbaz Sharif, the Prime Minister's Office said. Sharif, per the release, praised the engineers, technicians and workers from Pakistan and China for reaching the milestone well ahead of the schedule. The piece hoisted into place was the inner dome of the unit's double-layered containment, World Nuclear News reported. Chashma-5 will be the third Hualong One, China National Nuclear Corporation's design, built in Pakistan, after Karachi units 2 and 3.

The schedule so far has been brisk. The groundbreaking ceremony was held in July 2023, and Pakistan's nuclear regulator issued the construction licence on December 26, 2024, per WNN. The PAEC chairman's case is utilization: he told the ceremony that nuclear plants make up only 8.6% of the country's installed capacity but around 16.6% of its electricity generation, rising to 26% in winter, and that the fleet is generating 3,530 MW. Chashma-5 alone would add about a third to that figure, by our arithmetic.

TVA's board hands Watts Bar renewal to the CEO

TVA's board delegated authority to the chief executive to approve requesting Nuclear Regulatory Commission license extensions for Watts Bar Units 1 and 2 at its November 10, 2026 meeting in Knoxville, TVA said. The board presentation spells out the request: the CEO decides whether to submit the renewal applications after the environmental review under NEPA is complete, with total cost for the application process not to exceed $40 million and a target submittal of the end of 2026.

The deadline that matters is Unit 1's. Its license expires in 2036, and before a unit enters its period of extended operation it needs significant aging management inspections, several of which can only be done during outages with limited vendor availability. The presentation, by chief nuclear officer Matt Rasmussen, warns that delay risks losing outage windows and jeopardizing completion of Unit 1's mandatory inspections by 2036. Unit 2, licensed in 2015, already runs to 2055; TVA received a one-time exemption permitting early filing for it, so a reactor with nearly three decades left on its license is in line to file alongside its older twin.

The board's other vote was for a smelter. It approved serving a load greater than 100 megawatts, the threshold above which TVA needs board approval for firm power. The release does not name the customer; the presentation does: Crucible Zinc, a subsidiary of Korea Zinc, which announced in April 2026 its acquisition of Nyrstar's Tennessee operations, including the zinc smelter in Clarksville that TVA serves directly. Korea Zinc intends to expand it to produce zinc, copper, lead and other critical minerals, and per the presentation will retain 340 employees, create 400 jobs and invest more than $6.5 billion. The board also heard a FY 2026 review whose "Nuclear Innovation" entry was the NRC's construction permit for a BWRX-300 at Clinch River.

AtkinsRéalis signs to study CANDU for Türkiye

AtkinsRéalis subsidiary Candu Energy has signed a memorandum of agreement with state-owned Türkiye Nükleer Enerji Anonim Şirketi (TÜNAŞ) at COP31 in Antalya, under which AtkinsRéalis will carry out a feasibility study and front-end engineering design (FEED) for the expansion of Türkiye's nuclear program, the company announced on November 12, 2026. The study is expected to be completed before the end of 2027. For a potential multi-unit deployment, it will evaluate the site's characteristics, infrastructure requirements and environmental considerations, and how local supply chains and domestic nuclear expertise could be developed. The release names neither the site nor a number of units.

Türkiye's side treats it as groundwork for spending. The feasibility and FEED process "will provide an extremely reliable basis for our final investment decisions by ensuring the project's technical and commercial maturity," Energy and Natural Resources Minister Alparslan Bayraktar said, per Anadolu Agency. Anadolu describes the agreement as an assessment of CANDU reactor technology for a potential new nuclear power plant, building on a nuclear cooperation memorandum signed during Bayraktar's visit to Canada in March.

It is AtkinsRéalis's second CANDU study agreement in less than a month, after the Indiana memorandum announced on October 19 to explore up to eight reactors. Both are studies rather than orders, and the company's release counts 34 CANDU reactors built on four continents.