#geothermal
New England heat pump claims top 25,000; NY sets low-income solar rates
The New England Heat Pump Accelerator paid incentives on nearly 27,000 heat pumps and heat pump water heaters sold January 1 to September 16, 2026, across 25,672 claims by our count, and NYSERDA set NY-Sun rates of $0.40 to $0.60 per watt for low- and moderate-income home solar with no new market-rate money. Bedrock Energy raised $24 million and Darcy Geothermal about $15 million for geothermal in commercial buildings.
Google signs 50 MW superhot geothermal PPA with Quaise in Oregon
Google signed a power purchase agreement for 50 MW from Quaise Energy's Project Obsidian in Central Oregon, Quaise announced November 17, 2026, with deliveries as early as 2030 to support Google's data center operations in The Dalles. The first phase uses conventional drilling; Quaise's millimeter wave drill is slated for the second, and OPB reports a 10-mile line to La Pine is needed.

Mazama says CO2-cooled drilling ran 20% faster in 645°F Oregon rock
Mazama Energy says its Carbon Chill system, which uses supercritical carbon dioxide as a drilling fluid, cooled its bottom hole assembly to 195°F in 645°F rock during an August 2026 test at its Athena project in Newberry, Oregon, and drilled 20% faster than conventional drilling, at 92 feet per hour. The company calls it the first field use of the method in a deep geothermal well.

ARPA-E picks eight superhot geothermal projects for up to $30 million
DOE's ARPA-E selected eight projects on November 12, 2026 for up to a combined $30 million under SUPERHOT, its program for geothermal resources above 375°C and 22 megapascals. Four national labs, two universities, XGS Energy and Blade Energy Partners were selected for award negotiation, not yet funded.
Fervo puts Cape Station capacity potential at 8.4 GW as GeoBlock 2 syncs
Fervo Energy's third-quarter 2026 results, released November 9, cite a Fervo-commissioned DeGolyer and MacNaughton study supporting approximately 8.4 GW of capacity potential at Utah's Cape Station, nearly double the prior 4.3 GW, and report GeoBlock 2 synced to the grid. Fervo cut second-half capital spending guidance to $700–750 million, saying spending on its Google-contracted GeoBlocks moved later with no change to total investment.

Enphase guides Q4 lower, Western Australia drafts plug-in solar rules
Enphase Energy expects fourth-quarter 2026 revenue of $225 million to $255 million after third-quarter revenue of $293.3 million; third-quarter US sell-through fell 35% year over year and European sell-through fell 12% from the second quarter. SunPower is expanding in Texas with VPP financier SOLRITE, LADWP's board paused residential disconnections through 2026, Western Australia opened consultation on legal plug-in solar, and Micron gave $2.5 million toward geothermal heat for Boise affordable housing.
Singapore maps deep geothermal heat; Nevada lease sale takes in $4.8M
Singapore's Energy Market Authority said on October 26, 2026 that a 2024-26 geophysical survey puts the technical potential of its deep geothermal resource at over sixty times current annual electricity use, and appointed Surbana Jurong and GLJ to study next-generation plants. BLM's October 20 Nevada sale took in $4.83 million for 60 parcels, and Mitsubishi Power says Darajat Unit 3 now runs at 129 MW.
DOE picks 63 tribe-led energy projects for over $125 million
The US Department of Energy's Office of Indian Energy selected 63 tribe-led projects in 16 states for award negotiations on October 22, 2026, for over $125 million, against a funding notice that sought applications for up to $50 million. Thirteen deployment projects, including Alaska hydroelectric and power plants, account for $70.1 million of the $137.2 million in federal funds requested on DOE's list, by The Duck Curve's sum.
Endurance says its subsea geothermal plant ran net-positive for 8.7 seconds
Endurance Energy said on October 19, 2026 that its Adélie test plant at Axial Seamount, 300 miles off Oregon, generated more power than it used for 8.7 seconds on September 27, at a median of about 2 kW net. The run used a natural vent because the company's new 52-foot well was too restrictive.

Vermont Gas will fund and own Riggs Meadow ground loops; Dandelion drills
Dandelion Energy said on October 1, 2026 that Vermont Gas Systems (VGS) will pay the upfront cost of geothermal ground loops at Riggs Meadow, a 44-unit affordable housing development in Hinesburg, Vermont, with Dandelion designing and drilling; drilling is to begin in early 2027. VGS's June 27, 2025 filing in Vermont PUC Case No. 25A-0742 puts the $400,000 loop scope on VGS, $260,000 of it from the Climate Action and Innovation Budget in its Alternative Regulation Plan; the Department of Public Service did not object on July 28, 2025.

Fervo declares commercial operation at Cape Station's first 33 MW GeoBlock
Fervo Energy said on October 1, 2026 that the first of Cape Station Phase I's three 33 MW GeoBlocks in Beaver County, Utah declared commercial operation on September 30, 2026, one day before its contractual date, and that revenue is now being generated under a power purchase agreement; the company's August 10-Q risk factors had put first power in the fourth quarter of 2026. Fervo expects the remaining two GeoBlocks to reach contractual COD by January 1, 2027.

XGS names Baker Hughes, NM Tech and Sandia for DOE-selected New Mexico well
XGS Energy said on September 28, 2026 that the Department of Energy selected it for federal funding to support drilling a deep vertical appraisal well in New Mexico with Baker Hughes, New Mexico Tech and Sandia National Laboratories, within the more than $99 million DOE announced for geothermal development. DOE's list for its September 21, 2026 announcement puts the well in Socorro County among 16 exploration drilling selections; neither document gives a per-project amount, and the release says selection for award negotiations is not a commitment by DOE to issue an award or provide funding.
DOE selects five EGS field tests and 16 geothermal drilling projects
The US Department of Energy said on September 21, 2026 that it selected 21 geothermal projects for award negotiations: five field-scale enhanced geothermal system tests (Fervo, Zanskar, AlterG, the University of Utah and Quaise) and 16 exploration drilling projects. The press release says more than $99 million; the Geothermal Technologies Office's article says up to $99 million for the first budget period. None of the three DOE pages lists per-project amounts.
Fervo reports first power from Cape Station's first 33 MW GeoBlock in Utah
Fervo Energy said on September 24, 2026 that Cape Station, its enhanced geothermal development in Beaver County, Utah, reached what it calls First Power: the first of Phase I's three 33-megawatt GeoBlocks is synchronized to the grid and exporting electricity, with a contractual commercial operation date it expects to reach by October 1, 2026, the other two by January 1, 2027. Fervo's August 13 10-Q guided first power to the fourth quarter of 2026; its May prospectus defines a GeoBlock as 50 MW and puts its first Cape Station project at approximately $7,000/kW in overnight capital costs.

Mazama Energy raises $135M for superhot geothermal wells at Newberry
Mazama Energy announced $135 million in new capital on September 17, 2026, including an oversubscribed Series B led by Centaurus Capital and Doerr Capital, for its Newberry, Oregon engineered geothermal system, which it calls the hottest ever built at 629°F. The money funds Project Ceres, DOE-supported horizontal wells; the BLM issued a categorical-exclusion decision record on a Project Ceres geothermal operations plan on July 24, 2026, and the company now says Ceres will demonstrate power generation in 2027, where its October 2025 release had placed a 15 MW pilot in 2026.

BLM sets October 27 auction for 19 California geothermal parcels
The Bureau of Land Management announced on September 11, 2026 a competitive geothermal lease sale on October 27, 2026 for 19 parcels covering 39,723.81 acres of public land in Inyo, Mono, Lake, Sonoma, Modoc, and Imperial counties, California. It is the fourth sale listed on the bureau's California geothermal page since 2014; the August 2025 sale took $2,711,858 on 13 parcels, and a December 2025 instruction memorandum directs BLM state offices to hold geothermal sales annually where nominations are pending.
Hexagon leases geothermal rights on 145,000 acres of Weyerhaeuser forest
Hexagon Energy announced on September 10, 2026 that it has leased the geothermal rights on approximately 145,000 acres of Weyerhaeuser timberland in Washington and Oregon and says the portfolio could bring over 3 GW of power online once operational. The release names no project site, schedule, or technology. Weyerhaeuser optioned nearly 667,000 acres of geothermal rights to AltaRock Energy in 2008, and the largest plant on the Oregon Department of Energy's geothermal list is 22 MW.

Fervo and Google sign 396 MW geothermal PPA for possible Utah data center
Fervo Energy subsidiary Cape Generating Station 6 LLC signed a 15-year, 396 MW power purchase agreement with Google Energy LLC on August 26, 2026, announced September 1, for enhanced geothermal output from Cape Station in Beaver County, Utah, delivered in four 99 MW sub-tranches with target commercial operation dates beginning in the third quarter of 2028. Fervo has agreed to offer Google an expansion of approximately 600 MW, for total contracted capacity of not less than approximately 950 MW with a guaranteed commercial operation date no later than June 2030, and says the project is intended to use delivery pathways under Utah's S.B. 132, subject to regulatory approvals.

Sage Geosystems puts its 3 MW Texas geothermal plant in service
Sage Geosystems placed its SMECI enhanced geothermal facility in Christine, Texas in service on August 19, 2026, after more than 120 days of grid-connected operation. The company says the 3 MW plant held water losses below 10 percent across cycles and matched its reservoir model's predictions, results it is now applying to a planned commercial project at an Ormat site in Nevada.