Port Lincoln runs on local generators; rooftop solar asked to stay off

The 19 November storm brought down towers on a line the regulator funded partly so consumers could stop paying for backup generation at Port Lincoln, where local generators, one of them under an AEMO direction, now carry the town.

Satellite image of South Australia's Eyre Peninsula: green and brown farmland on a triangular peninsula between dark blue ocean to the west and the turquoise waters of Spencer Gulf to the east, with red-brown arid land and white salt lakes across the top of the frame.
NASA (MODIS, Aqua satellite), via Wikimedia Commons; image from October 2010, not of the storm

Households across the lower Eyre Peninsula in South Australia, from Port Lincoln north towards Elliston and Arno Bay, are being asked to keep their rooftop solar switched off until SA Power Networks says otherwise. A storm on 19 November 2026 brought down towers on the 132 kV line from Cultana to Port Lincoln, and about 10,000 customers around Port Lincoln are now supplied by local generation running as an island, cut off from the rest of the grid.

The request still stood on 23 November. The state government's emergency page, updated that morning, thanks residents who switched off and asks them to stay off "until SA Power Networks advises otherwise", which will "help keep the temporary generators operating reliably." SA Power Networks had posted the same request on 20 November.

On a grid this small, a sunny afternoon of rooftop exports is a hazard rather than a help. Energy Minister Tom Koutsantonis wrote on X, as pv magazine Australia reported, that panels in the islanded region "could trip the temporary generators supplying the township." SA Power Networks' instructions have owners turn off the solar supply main switch at the switchboard and the PV array DC isolator at the inverter, which stops the system outright. Renew Economy reported on 23 November that households with batteries can keep using their solar for themselves as long as nothing is exported; the official notices ask for systems to be switched off and do not draw that distinction. Battery owners are a growing group nationally (Australia added 276,011 batteries and 1,894 MW of rooftop solar in H1 2026).

An island under direction

Port Lincoln became an island on the afternoon of 19 November, when both circuits of the 132 kV line, Cultana to Port Lincoln No.1 and No.2, tripped together and about 30 MW of load went off supply, AEMO's market notice records. AEMO was itself directed, under section 27C of the Emergency Management Act 2004, to issue a direction, and it directed Synergen Power to run its POR01 unit at Port Lincoln to "synchronise and maintain the local load and manage frequency control in the island", until further notice. ElectraNet says local generation had restored power to about 10,000 customers, mostly in Port Lincoln, by 9.45pm. None of AEMO's market notices through 23 November cancels the direction.

ElectraNet says the storm damaged three transmission towers between Port Lincoln and Cleve and interrupted supply to around 24,000 customers. The minister's declaration says two towers were destroyed on the double-circuit 132 kV line from Cultana to Port Lincoln, and AEMO's statement that evening said two were down, with "no broader impact" on the National Electricity Market. The declaration, an electricity supply emergency under the Emergency Management Act 2004, took effect at 6:15pm Adelaide time on 19 November for 14 days.

From 1pm on 20 November ElectraNet began progressively restoring transmission services across the peninsula through what it calls an interim solution, with temporary towers and then permanent repairs to follow. Renew Economy reports that many customers in the northern part of the area are back on the main grid after a network reconfiguration, and that the 62 MW Cathedral Rocks wind farm, the peninsula's only wind facility, is offline. ElectraNet's Alex Trento told reporters the towers would be standing again "in a few months' time", the ABC reported.

The backup the line was meant to retire

The line is the Eyre Peninsula Link, which ElectraNet completed in February 2023 before removing the 50-year-old line it replaced, 510 towers over 210 km. When the Australian Energy Regulator approved its funding in September 2020, allowing $280 million in 2017-18 dollars, it listed among the benefits "saving consumers the ongoing cost of paying for back-up generation and the costs for repairing the existing transmission line." ElectraNet was then buying network support that let it call on diesel generation at Port Lincoln when the old line was interrupted, and the regulator called avoiding those payments "one of the primary benefits of the new transmission line." Generation at Port Lincoln is what the town is running on now.

Who pays for the gap is the next argument. Koutsantonis told 891 ABC Adelaide there would be "a lot of questions" about how "over $300 million worth of upgrades on the Eyre Peninsula" had failed, upgrades "that we've all paid for in our power bills". Premier Peter Malinauskas said an investigation would test whether this was a genuine one-in-2,000-year event or whether "something went wrong in terms of the specifications of that infrastructure," per Renew Economy.

ElectraNet holds a "strong belief" that the wind exceeded 172 km/h, above what the towers were built to withstand, the ABC reported. Trento said a secondary circuit was explored when the project was proposed, "But that would have been double the cost," and put a second line at $600 million. By the ABC's account he conceded that repair costs, not yet known, would also reach consumers through their bills. The emergency declaration is due to lapse on 3 December unless it is revoked earlier.