Chubu files Hamaoka 3 and 4 withdrawal; NRA issues no disposition
Chubu Electric Power's withdrawal of the Hamaoka units 3 and 4 applications is now on file, and Japan's Nuclear Regulation Authority (NRA) has closed the applications without ruling on them. A withdrawal request dated September 25, 2026 and signed by Kingo Hayashi as president asks to withdraw six applications, and an NRA letter of the same date tells Chubu the regulator will issue no disposition on them. Both were distributed at the NRA commission's September 30, 2026 meeting.
The six go back to 2014: the reactor installation change permit applications for unit 3 (June 16, 2015) and unit 4 (January 26, 2015); three construction plan approval applications (February 14, April 24 and August 28, 2014); and a safety regulation change approval application (February 14, 2014). Chubu's September 25 release footnotes the set as the two permit applications plus unit 4's construction plan and safety regulation applications. The reason given: serious doubt about the reliability of the application materials and later review responses after the investigation committee's report received September 11, 2026. The unit 4 permit application has been withdrawn once before: the NRA's record of Chubu's February 14, 2014 unit 4 filing marks that installation change application withdrawn on January 26, 2015, the date the new request gives for unit 4's.
Jiji Press, citing the NRA, reported on September 25, 2026 that this is the first time a screening application has been withdrawn because of misconduct. The NRA's inspection continues. A secretariat paper for the NRA's September 17, 2026 meeting says that after receiving a further part of Chubu's ordered report on September 14, the inspection will keep checking three matters (hybrid-synthesis connection periods, response-spectrum-matched simulated ground motions, and helpline handling), then go to a SERP (significance evaluation and regulatory measures) meeting for a provisional evaluation before the Commission decides the final result.
Hayashi, who resigned as president on September 30, 2026, said that day that Hamaoka's importance and necessity have not changed and that being recognized locally as qualified to re-apply will be a long road. The board decision behind the filing is in Chubu withdraws Hamaoka 3 and 4 applications after seismic-data inquiry.
Sources
Primary
- 中部電力浜岡原子力発電所の設置変更許可申請等の取下げ (Withdrawal of Chubu Electric's Hamaoka installation change permit applications, etc.), distributed paper, 33rd NRA Commission meeting of 2026-09-30 · Nuclear Regulation Authority (原子力規制庁 secretariat)
Supporting
- 中部電力株式会社から核原料物質、核燃料物質及び原子炉の規制に関する法律に基づき浜岡原子力発電所第4号機の設置変更許可申請書等を受理しましたので公表します (NRA announcement of receipt of Chubu Electric's Hamaoka unit 4 installation change permit application, etc.) · Nuclear Regulation Authority (N-ADRES)
- 資料1 中部電力株式会社の不正行為に係る対応状況 (Status of the response to Chubu Electric's misconduct), 32nd NRA Commission meeting of 2026-09-17 · Nuclear Regulation Authority (原子力規制庁)
- 浜岡原子力発電所3号機・4号機の設置変更許可申請書などに関する申請取下げの提出 (Submission of a request to withdraw applications including the installation change permit applications for Hamaoka units 3 and 4) · Chubu Electric Power Co., Inc.
- Chubu Electric Withdraws N-Reactor Restart Screening Applications · nippon.com (Jiji Press)
- 2026年9月度 定例記者会見 林社長挨拶 (September 2026 regular press conference: President Hayashi's remarks) · Chubu Electric Power Co., Inc.