Roundup

StarCharge's 4 GWh Inner Mongolia battery is online; ORIX dates Shiga plant

ORIX sets December 1 for a 548 MWh battery in Shiga, L&T wins a 900 MWh order in Gujarat, Energy Vault finances a Texas battery, and Sungrow Renewables and Actuate agree a deal they call Spain's largest.

Aerial view in low sunlight of rows of white battery cabinets on flat grassland, with a line of trucks carrying white containers on a road in front and transmission towers around the site
StarCharge (via PR Newswire)

Grid battery news from November 19 to 27, 2026 ran from a four-hour plant in Inner Mongolia that its builder says has been running for three months to a Spanish portfolio whose projects are not all ready to build. Three of the five items arrive with a superlative from the companies involved. One arrives with an SEC filing that says more than the press release.

StarCharge says its 1 GW / 4 GWh Inner Mongolia battery is on the grid

StarCharge has connected a 1 GW / 4 GWh lithium iron phosphate battery in Xilin Gol League, Inner Mongolia, to the grid, the Changzhou company said on November 27, calling it the world's largest single-site grid-forming standalone battery. The four-hour system (1 GW of power, 4 GWh of energy) uses 800 of StarCharge's own 5 MWh battery cabinets on 28 hectares and represents about RMB 3 billion (about US$420 million) of investment. The release names no owner, only the central state-owned enterprise partners StarCharge says it worked alongside.

The headline is newer than the plant. The release says the station has operated stably for three months since connecting to the grid, and that it is designed to supply about 1 TWh a year to Sonid Left Banner and surrounding areas, which by our arithmetic is about 250 full discharges of its 4 GWh. Unlike a grid-following battery, StarCharge says, this one sets voltage and frequency itself, can operate in island mode and responds rapidly to grid faults; RTE is trialing a switch to grid-forming by software update alone on Neoen's 92 MW battery in Brittany.

ORIX schedules its 134 MW / 548 MWh Maibara battery for December 1

ORIX will begin commercial operation of the Maibara Koto Energy Storage Plant in Maibara, Shiga, on December 1, 2026, the company said on November 24. The plant has a rated output of 134 MW and a rated capacity of 548 MWh, roughly four hours by our arithmetic, from 140 containers of lithium-ion batteries on about 25,000 m2 leased from Maibara City. ORIX calls it one of Japan's largest storage plants, citing in-house research.

The auction revenue starts four months after the plant does. The project is covered by Japan's Long-Term Decarbonized Power Source Auction, under which OCCTO, the cross-regional grid coordinator, provides revenue equivalent to fixed costs for 20 years in principle, but it begins operating under that system only in April 2027. ORIX currently operates one other storage plant, Kinokawa in Wakayama, and is developing two more at Yufu and Yonezawa.

L&T wins a 300 MW / 900 MWh battery order at Khavda

Two Larsen & Toubro businesses, its Renewables arm and L&T Electronic Products & Systems, have jointly won an order to develop a 300 MW / 900 MWh three-hour battery at Khavda in Gujarat, L&T said on November 25. The system will use liquid cooling.

L&T names neither the client nor the price. It classifies the order as "significant," which on the company's own scale means a value of ₹1,000 crore to ₹2,500 crore. India may soon require storage as well as order it: a Central Electricity Authority draft would require ground-mounted solar and onshore wind plants commissioned after July 1, 2027 to carry co-located storage.

Energy Vault finances its 150 MW / 300 MWh SOSA battery in Texas

Energy Vault has closed $78 million in construction and bridge financing for SOSA Energy Center, a 150 MW / 300 MWh battery in Madison County, Texas, the company said on November 23. The bridge is to be repaid from an already committed $80 million preferred equity investment when the project is complete. SOSA will sell into ERCOT's North market on a merchant basis, and Energy Vault, its own EPC contractor, expects commercial operation in the third quarter of 2027. SOSA was the first storage asset Energy Vault formally acquired and placed into development under Asset Vault, its ownership platform, which later took on the Goshe development portfolio.

The SEC filing adds names and a deadline that the release leaves out. Asset Vault president Cory Magnuson says "a bank, a strategic partner and an institutional investor have each backed SOSA on those terms"; the 8-K Energy Vault filed on November 20 names First-Citizens Bank & Trust Company as agent on a $78.0 million preferred equity bridge loan facility and an $8.7 million letter of credit facility, lists Siemens Financial Services as a party to the credit agreement and puts the unnamed third-party investor's commitment at $79.6 million. If SOSA is not placed in service by December 31, 2027, a quarter after the target and extendable by 90 days for a fee, either member may start a repurchase process, which, unless the project is placed in service within 30 days of the notice, requires paying the investor 108% of its funded contributions.

Sungrow Renewables and Actuate agree a 380 MW / 1.5 GWh Spanish portfolio

Sungrow Renewables, the development and investment platform of Sungrow Power Supply, and Actuate Energy, a storage platform backed by NGP, have agreed a deal covering seven standalone battery projects in Spain totalling 380 MW / 1.5 GWh, the companies announced in a release dated November 19. They call it the largest battery storage transaction in Spain to date and give no price. The projects include the Valencia Cluster in La Vall d'Uixó (Castellón), Santiago in Lousame (A Coruña), Berja in Almería and the Navarra Cluster in Olite and Cordovilla, with commercial operation expected between 2027 and the first half of 2028.

The schedule runs in an unusual order: the first assets are already under construction, while the full portfolio is expected to reach ready-to-build status during 2027. The release does not spell out who buys what, but Actuate, founded in 2026, describes its business as acquiring storage projects at the ready-to-build stage and operating them, and its chief executive, Ben Skinner, says it looks forward to operating these.