Four hydrogen stories from November 17 to 20, 2026: a Finnish e-methane plant that now has its money, a Chinese pipeline sized far beyond its home city's green hydrogen production capacity, a British project one step closer to a subsidy contract, and a California electrolyzer with about half the daily capacity its site was first billed for.

Nordic Ren-Gas takes FID on its Tampere e-methane plant

Nordic Ren-Gas has reached a final investment decision on its e-methane plant in Tampere, Finland, an investment of more than €300 million, the company said on November 20, 2026. Construction starts immediately, with completion scheduled for 2029, and Ren-Gas calls it the world's largest e-methane facility to reach that point. At full capacity the plant is to make about 190 GWh of e-methane a year, using around 40,000 tonnes a year of biogenic CO₂ captured at a local waste-to-energy plant; Ren-Gas describes its process as converting renewable hydrogen and captured biogenic carbon dioxide into renewable gas.

The fuel leaves and the heat stays. The e-methane will travel through the European gas network to Germany, mainly for heavy-duty road transport, while up to 200 GWh a year of recovered process heat goes into Tampere's district heating network, a ceiling about the size of the fuel output. Equity comes from Allianz, Tesi, Japan Hydrogen Fund and Schroders Greencoat; the debt from the European Investment Bank, Societe Generale, Standard Chartered, Nordea and Finnvera, with the EIB's share a €60 million loan backed by InvestEU. Finland issued its first guarantees of origin for e-methane, for gas from the P2X Solutions plant, in October (as we reported).

A 195 km pure hydrogen pipeline starts up in Inner Mongolia

A 195 km pipeline carrying pure hydrogen from Darhan Muminggan United Banner to Baotou's city districts has formally started operation, Xinhua reported on November 19, 2026, from an announcement at a hydrogen industry conference in Baotou that day. Xinhua calls it China's first pure hydrogen long-distance pipeline longer than 100 km, and says the project was selected for the National Energy Administration's first batch of energy-sector hydrogen pilot projects. Wang Xinyu, a director of the developer, Huadian's Inner Mongolia hydrogen company, said the line has a design pressure of 6.3 MPa, a DN450 bore and an approved throughput of 100,000 tonnes of hydrogen a year, and that it can cut green hydrogen transport costs from 13 yuan a kilogram to about 3. People's Daily adds that throughput could reach 240,000 tonnes a year in the long term, and that the line has four stations and six valve rooms.

The pipe is sized well ahead of Baotou's green hydrogen production capacity, which has reached 7,800 tonnes a year, built on Huadian's 200 MW wind and solar hydrogen project, Mayor Meng Qingwei said; by our arithmetic, the approved throughput is about 13 times that. The steel had to be special too: Xinhua's English report says Baotou Iron and Steel Group developed anti-hydrogen-embrittlement steel for the line.

Protium's South Tees project reaches HAR2's offer stage

The Department for Energy Security and Net Zero has invited Protium's South Tees Net Zero project to the Invitation to Offer stage of the second Hydrogen Allocation Round (HAR2) after due diligence, Protium said on November 19, 2026; its South Wales Net Zero project was invited too. The 70 MW Teesside plant is to produce up to 11,000 tonnes of green hydrogen a year (around 433 GWh), which Protium expects to supply to existing Teesside businesses switching from fossil fuels and to new e-fuels processes looking to locate in the region, by pipeline and tube trailer. The stage brings it closer to a Low Carbon Hydrogen Agreement, the revenue support contract that would help fund construction.

An invitation is still short of an award. DESNZ shortlisted 27 electrolytic projects on April 7, 2025, South Tees Net Zero among them, and warned then that "it is unlikely that all projects will be successful." Christopher Jackson, Protium's chief executive and founder, points to the next round of talks: "We now look forward to working closely with DESNZ during commercial negotiations ahead of any future HAR2 contract award decisions."

Plug's Vernon electrolyzer starts, and GenEco Scale gets a first customer

Avina Clean Hydrogen's plant in Vernon, California, about 10 miles from the Port of Long Beach, is now operational with a 5 MW containerized GenEco PEM electrolyzer, Plug Power said on November 19, 2026. Plug says the unit provides 2.1 metric tons a day of production capacity and that the site is designed to fuel more than 50 heavy-duty trucks a day, with 35 MPa and 70 MPa dispensing and tube-trailer deliveries across the Los Angeles region.

Plug's figure is about half what the site was first billed for, and it arrives late. At its October 30, 2024 groundbreaking, Avina described a facility designed to produce up to 4 metric tons a day and said the project was on schedule to start commercial operations from July 2025.

On November 17, Plug launched GenEco Scale, an integrated electrolyzer plant offering built from standardized 20 MW blocks for projects of approximately 100 MW and above, with Arcadia eFuels as first customer for the 280 MW hydrogen plant at Project ARC in Texas, designed to make about 23.2 million gallons of electro-sustainable aviation fuel a year. Plug's work at Project ARC so far is engineering: it says it has completed the technical evaluation and front-end engineering design study, and its risk statement lists the chance that the project does not obtain final investment approval. For scale, Plug says it has shipped more than 320 MW of electrolyzer capacity globally.