Australia seeks 5 GW; Ireland provisionally picks 1,367 MW of solar
A Brazilian judge refused to halt the December 2 and 4 battery capacity auctions, leaving the generators-only cost rule to be fought out later.
Three procurement rounds moved between November 25 and November 27, 2026, on the heels of Italy's second storage auction (Italy's second MACSE auction buys 16 GWh of storage, average price down 12%): Australia opened bidding for an indicative 5 GW of renewable generation, Ireland's sixth onshore auction named its provisional winners, and a Brazilian federal judge declined to stop the country's first battery capacity auctions, set for December 2 and 4.
Australia opens CIS Tender 12 for 5 GW, NSW excluded
Australia's Capacity Investment Scheme opened Tender 12 on November 27, 2026, seeking an indicative 5 GW of renewable generation in every National Electricity Market region except New South Wales, according to the tender guidelines. The government may settle on a greater or lesser volume if the change fits the tender's policy objectives. Registration closes on January 22, 2027 and bids on February 5, with successful bids to be announced in June 2027. Projects with generation assets in NSW are pointed to the state's own Roadmap tenders, though projects in the Australian Capital Territory that use shared infrastructure in NSW can bid.
The new condition is about the developer. For the first time in a NEM generation tender, bidders must take part in the government's Developer Rating Scheme and must have signed a letter of engagement with the scheme provider before they bid, according to Assistant Minister Josh Wilson's release. Bidders can opt into a First Nations set-aside of at least 500 MW. To qualify, a project must commit to equity or revenue sharing equivalent to at least a 5% economic interest for an eligible First Nations organisation, among other tests; projects that skip the set-aside are still assessed.
Victoria is where the leftover state allocation sits. About 1 GW of the target is aimed at Victorian projects, and solar-only projects there are capped at 0.47 GW in aggregate at the Victorian government's request, per the guidelines. The scheme is also running out of planned rounds: after Tender 12 the government will assess whether a further generation tender is needed in 2027, the release says, and winners of Tender 9, the current NEM generation round, are expected in early December 2026.
Ireland's RESS 6 provisionally picks 1,367 MW of solar
EirGrid published the provisional results of RESS 6, Ireland's sixth onshore renewables auction, on November 25, 2026: 28 projects totalling 1,555.30 MW, of which 22 are in the solar pot with 1,367.25 MW and six in the onshore wind pot with 188.05 MW, per its results report. The weighted average offer price was €102.42/MWh in the solar pot and €99.35/MWh in the wind pot.
The two technologies ran in separate pots, with offers ranked within each, so wind's lower price never competed with solar's. The wind pot was simply small. Only 10 wind projects qualified against 36 solar projects, seven wind projects withdrew from the process, and wind ended up with about 12% of the provisionally successful capacity, by our arithmetic. Six of the 10 wind offers won, leaving 50.65 MW unsuccessful; the solar pot left 1,014.60 MW unsuccessful. "It is clear that we are not seeing enough onshore wind farms entering these auctions in recent years, with onshore wind being outpaced by solar developments," Minister Darragh O'Brien said.
Price was not the only test in RESS 6. RESS 6 is the first RESS auction to apply the non-price criteria of Article 26 of the EU Net-Zero Industry Act, ranking offers within each pot on a composite score of price, resilience and energy system integration, EirGrid says. The results remain subject to the minister's approval; final results are due on December 9 and notices of award on January 11, 2027.
Brazilian judge lets the battery auctions go ahead
Judge Diego Câmara Alves of the 17th Federal Civil Court in the Federal District refused on November 25, 2026 to suspend ANEEL auctions 05/2026 and 06/2026, the battery capacity auctions set for December 2 and 4, in a decision on a public civil action brought by the wind association Abeeólica against the federal government and ANEEL. They are the auctions whose notices ANEEL approved in October (Brazil sets its first battery capacity auctions for December 2 and 4).
The fight is over who pays. Law 15,269/2025 has the cost of battery capacity contracts split only among generators; Abeeólica says the charge could reach about R$17/MWh, roughly 10% of a generator's reference revenue in the free market, and argues the rule is unconstitutional and the auctions premature while ANEEL's apportionment rules are still in consultation. The judge found that the generators-only rule was the legislature's choice, and saw reason for restraint in Abeeólica's own pending challenge at the Supreme Federal Court and in bill PL 3.716/2026 in Congress. He also found that no rule makes the auctions wait for ANEEL's apportionment, and that striking down the cost rule would change who pays without invalidating the auctions or contracts. Nothing is collected before supply starts on August 1, 2028, so he saw no imminent harm.
He did see harm in delay. An energy ministry note filed by the government says the PDE 2036 ten-year plan and the 2026 operation plan identified breaches of Brazil's power-adequacy criteria from 2027, even after the capacity auctions of March 2026, the decision records. Bidders are already lined up: ANEEL's filing, as the decision records it, counts 5,296 registered projects in the Armazenamento Nacional product and 5,734 in the Armazenamento product, with bid guarantees posted.
Only the injunction is settled. The ruling summons the government and ANEEL to answer the suit on its merits. Abeeólica's parallel challenge at the Supreme Federal Court, ADI 8.050, filed on November 19, showed no ruling on its injunction request on the court's docket as of November 27, when the case went back to Justice Cristiano Zanin.
Sources
Primary
- RESS 6 Provisional Auction Results (R6PAR) · EirGrid plc (Auction Administrator)
- Decisão, Ação Civil Pública 1135740-19.2026.4.01.3400 (Abeeólica v. União and ANEEL), 17ª Vara Federal Cível da SJDF · Justiça Federal, Seção Judiciária do Distrito Federal (court decision; copy hosted by Poder360)
- Capacity Investment Scheme Tender 12: National Electricity Market – Generation, Tender Guidelines (November 2026) · Department of Climate Change, Energy, the Environment and Water / AusEnergy Services Limited
Supporting
- Minister O'Brien welcomes results of sixth national auction for new onshore wind and solar energy projects · Department of Climate, Energy and the Environment (Ireland)
- More clean, reliable energy for Australia's electricity grid · Assistant Minister for Climate Change and Energy Josh Wilson
- ADI 8.050, docket (andamentos) · Supremo Tribunal Federal
Copies of cited sources are retained where available. If a link no longer resolves, request a copy at contact@theduckcurve.com.