Batteries top gas in NERC's winter additions; FERC staff flag drought, oil
ISO New England expects more than 30,000 MW against a 20,483 MW peak, with a full winter of a Québec line among its new supply; FERC staff say that line may carry less power than envisioned.
North America's grid enters winter 2026-27 with more capacity than in winter 2025-26 and a better outlook in several regions, according to outlooks published between November 16 and 19, 2026 by the North American Electric Reliability Corp., FERC staff and ISO New England. By NERC's count, batteries added more winter peak capacity than natural gas. The worries are water and fuel: FERC staff expect drought to restrict western hydropower and imports from Hydro-Québec, and New England still leans on oil in cold snaps. PJM's outlook, published November 5, forecasts a winter record peak near 147,500 MW.
NERC: batteries add more winter capacity than gas
Batteries added 9.2 GW of winter on-peak capacity across North America since last winter, ahead of natural gas at 8.7 GW, according to NERC's 2026-2027 Winter Reliability Assessment, released November 18, 2026. The battery figure is 20.6 GW of nameplate, so less than half of it counts at the winter peak, by our arithmetic. Total resources grew 26 GW (2.4%) while aggregate peak demand rose 21 GW (2.6%), and retirements have slowed: as of September, US retirements of thermal generators 50 MW and larger came to under 700 MW for 2026.
Resources cover a normal winter peak everywhere, NERC says, but three areas face risks of supply shortfalls in more extreme conditions. They are NPCC-Maritimes; NPCC-Québec, where an increase in known outages takes 1,500 MW off certain generation capacity; and SERC-East, a historically summer-peaking area whose limited loss-of-load risk is concentrated in early-morning hours in January. ERCOT, WECC-Basin and WECC-Northwest drew a lower risk determination than last winter, ERCOT after adding 1.7 GW of gas and nearly 3.5 GW of installed battery capacity.
Demand response grew to 43.6 GW from 41.7 GW as more data centers and other large loads enrolled, though some of it can be called only after an energy emergency is declared. NERC lists six plants held available under DOE 202(c) emergency orders, among them J.H. Campbell and Eddystone, with order expirations from November 20, 2026 to February 12, 2027, and left them out of the resources it counted.
FERC staff: drought in the West, oil in New England
SERC-East may have elevated risks under extreme conditions, FERC staff warn in their Winter Energy Market and Electric Reliability Assessment, dated November 19, 2026. New England is not expected to run short of electricity but remains vulnerable to rapid depletion of stored fuel in prolonged extreme weather, and import-dependent parts of MISO and SPP may face local reliability challenges. Staff draw those warnings from NERC's analysis of the 15 U.S. assessment areas, all of which anticipate adequate supplies and reserve margins under normal conditions.
Drought covers 45% of the continental United States, and low reservoirs have the Glen Canyon and Hoover dams constrained to about a third of their maximum output going into winter, the staff report says. Southwest hydropower already hit a record low in summer 2026. Staff look to new markets to fill the gap: CAISO launched its Extended Day-Ahead Market on May 1, 2026, SPP expanded into the Western Interconnection on April 1, and imbalance reserve requirements have fallen as much as 66% in some months since EDAM went live.
In New England the cold-weather fuel is oil. On January 25, 2026, oil-fired and dual-fuel units produced 7,864 MW in a single hour, roughly 40% of ISO-NE's net generation, and New England's distillate stocks were 2.5 million barrels for the week ending October 2, 46% below the prior five-year average. ISO-NE cut its capacity performance pay rate to $3,500 per MWh from $9,337 on September 1, 2026, which staff say should lower prices in emergency conditions, other factors remaining the same.
ISO New England: more than 30,000 MW for a 20,483 MW peak
ISO New England expects more than 30,000 MW of available capacity against a forecast peak of 20,483 MW in normal weather and 21,457 MW in extreme cold, the grid operator said on November 16, 2026. New sources since last winter include additional offshore wind, with Vineyard Wind 1 and Revolution Wind both reaching full operation in October 2026, and a full winter of the New England Clean Energy Connect line. The ISO expects stored fuel supplies entering the winter to be slightly higher than at the start of winter 2025-26, a different measure from the regional distillate stocks, heating oil included, that FERC staff put 46% below the five-year average.
Last winter, the coldest in 20 years, demand peaked at 20,182 MW on January 25, 2026, the highest in seven years and the day of FERC's 40% oil hour. The new line is where the outlooks part ways. NECEC can carry up to 1,200 MW from Hydro-Québec, but Québec is in a record drought and the power flowing through the line may be less than originally envisioned, FERC staff write. NERC does list Québec among its three shortfall-risk areas, but the driver it names there is an increase in known outages, partly offset by net firm exports falling about 500 MW, and it anticipates no hydropower performance or fuel supply issues.
Sources
Primary
- New England expected to have sufficient electricity supplies this winter · ISO New England (ISO Newswire)
- 2026-2027 Winter Reliability Assessment · North American Electric Reliability Corporation
- Winter Energy Market & Electric Reliability Assessment 2026-2027 (staff report) · Federal Energy Regulatory Commission
Copies of cited sources are retained where available. If a link no longer resolves, request a copy at contact@theduckcurve.com.