Dieppe-Le Tréport finishes turbines; Zelestra tolls 700 MWh to Statkraft
Estonia's Lihula solar park adds a 55 MW / 250 MWh battery, NSW hands the Hunter Transmission Project to Transgrid, Downer and UGL, and Ember puts stored solar in Italy up to 49% below gas.
France's Dieppe-Le Tréport offshore wind farm has all 62 turbines in the water, Italy has a 700 MWh battery contracted outside its state auctions, a solar park in Estonia has what its owners call the Baltics' largest-capacity battery, and New South Wales has named the companies that will build the Hunter Transmission Project. In between, Ember priced Italy's stored solar against gas.
Dieppe-Le Tréport installs its last turbine
The 500 MW Dieppe-Le Tréport offshore wind farm off Normandy now has all 62 of its turbines installed, Ocean Winds said on November 27, 2026. The turbine campaign began in June 2026 and ran around six months, and the farm has been generating progressively since first power in July, with turbines connected as they went in. Commissioning continues, and Ocean Winds, the EDP Renewables and ENGIE joint venture, gives no date for full power beyond "the coming weeks."
The project's director, Frédéric Flaus, put the installation at the end of "more than ten years of development, consultation and collective effort." The 62 turbines stand on jacket foundations, and at full power the farm will generate the equivalent of the annual consumption of approximately 850,000 people, Ocean Winds says. Like Poland's Baltic Power in October, it finished installing turbines while already sending power to the grid.
Zelestra tolls a 700 MWh Italian battery to Statkraft
Zelestra has signed an 8-year physical tolling agreement with Statkraft covering the whole of a 175 MW / 700 MWh, 4-hour battery to be connected to an existing Terna substation in Central Italy, Zelestra said on November 26, 2026. Zelestra builds and operates the fully authorised plant, due to operate in 2028; Statkraft uses its market access and optimisation to maximise the plant's revenues across all relevant markets. It is Statkraft's first tolling agreement in Southern Europe and Zelestra's fourth in Italy, taking Zelestra to 5.4 GWh of contracted batteries worldwide, 3.5 GWh of them in Italy.
Zelestra presents bilateral tolls as a complement to Italy's regulated storage procurement. Italy's second MACSE auction had procured 16 GWh of storage two days earlier (Italy's second MACSE auction buys 16 GWh of storage, average price down 12%), and Zelestra Italy chief executive Eliano Russo said that "a bilateral market is developing in parallel, one that rewards solid, connection-ready projects."
Ember prices stored solar against gas in Italy
Solar or wind power stored in a battery and shifted in time could cost on average up to €106-122/MWh in Italy, against an average of €210/MWh for gas power at October 2026 gas prices, or up to 49% less, according to an analysis Ember published on November 26, 2026 with Cleantech for Italy and Energy Square. The estimate uses what Ember calls a conservative charging price, the €57-73/MWh of Italy's 2025 renewable auctions, and battery costs consistent with the systems awarded in the first MACSE auction.
Batteries are still a small part of Italy's evening. They met an average of 2.8% of evening peak demand in the first half of 2026, Ember says, more than double the 1.3% a year earlier but small next to fossil power's 40% share. Grid-scale capacity was 7 GWh in June 2026, and auctions are expected to bring it to 38 GWh by 2029, below the 76-96 GWh of storage that Terna and Snam's scenarios need by 2035. Bulgaria, with a much smaller power system, had 16 GWh of grid-scale batteries by August 2026, overtaking Italy's fleet. The analysis still describes the second MACSE auction of November 24 as upcoming and hedges on whether it "is fully subscribed"; by Terna's count it covered 100% of the requirement.
Estonia's Lihula hybrid park adds a 250 MWh battery
Evecon and Mirova have added a 55 MW / 250 MWh battery to the 77.5 MW Kirikmäe solar park near Lihula, which was completed in October 2024, Evecon said on November 26, 2026 (in Estonian). The two invested about €110 million in the hybrid park in total, and Mirova calls the battery the largest-capacity storage system in the Baltics. Construction of the battery began in January 2026.
The owner is the Baltic Renewable Energy Platform, held 90% by Mirova Energy Transition 5 and 10% by Evecon. It has a ten-year flexibility and power purchase agreement with Germany's Pure Energy covering the output of three solar parks and the new battery, backed by Swedbank financing of nearly €85 million. The owners call the park completed; their builder, WiSo Engineering, says the battery is technically finished and the last grid and market tests are being completed.
Transgrid, Downer and UGL to build the Hunter Transmission Project
The NSW Government has awarded Transgrid the contract to deliver the 110-kilometre, 500 kV Hunter Transmission Project, EnergyCo said on November 23, 2026, after a procurement process overseen by the Australian Energy Regulator. Transgrid will deliver, operate and maintain the line, and construction contracts have gone to Downer for the transmission lines and UGL for the substations, Transgrid said the same day.
The line is meant to carry power from the Central-West Orana and New England renewable energy zones (New England's own line went on exhibition in October) and to help create a 500 kV ring as coal plants retire. It received planning approval in July 2026 with 115 conditions, and Transgrid puts its added transfer capacity at 5 GW and says construction begins in 2027. Neither release puts a price on the contract.
Sources
Primary
- Deal is sealed to build the backbone of the NSW electricity grid · Energy Corporation of New South Wales (EnergyCo)
- Zelestra and Statkraft sign 700 MWh long-term battery tolling agreement in Italy · Zelestra
- Evecon ja Mirova avasid Lihulas 110 miljonit maksva Baltimaade võimsaima hübriidpargi · Evecon
- Energy storage can help cut Italy's power prices · Ember
- Ocean Winds completes turbine installation at Dieppe-Le Tréport offshore wind farm · Ocean Winds
Supporting
- Jobs and lower-cost energy one step closer as Hunter Transmission Project moves into delivery · Transgrid
- Baltic's most powerful hybrid park completed near Lihula · Mirova